Contract Variation Order (Kenya)
CONTRACT VARIATION ORDER
Law of Contract Act Cap. 23 | Public Procurement and Asset Disposal Act No. 33 of 2015 | National Construction Authority Act No. 41 of 2011
Variation Order No.: [Variation Order Number]
Date: [Variation Order Date]
ORIGINAL CONTRACT DETAILS
Contract Title: [Original Contract Title]
Contract Reference No.: [Original Contract Number]
Contract Date: [Original Contract Date]
Original Contract Value: [Original Contract Value]
Contract Type: [Contract Type]
PARTIES
Employer / Client: [Employer Name], of [Employer Address]
Contractor / Service Provider: [Contractor Name], of [Contractor Address]
1. DESCRIPTION OF VARIATION
1.1 Type of variation: [Variation Type].
1.2 The following variation is hereby ordered / agreed:
[Variation Description]
1.3 Clause(s) varied: [Clause Varied].
1.4 Original provision: [Original Provision]
1.5 Varied provision: [Varied Provision]
2. FINANCIAL IMPACT
2.1 Value of this Variation Order: [Variation Value]
2.2 Basis of valuation: [Valuation Basis]
2.3 Original contract value: [Original Contract Value]
2.4 Revised contract value: [Revised Contract Value]
2.5 Cumulative variation as percentage of original contract value: [Cumulative Variation Percent]
2.6 Public procurement declaration: [Public Procurement Declaration]. PPRA / National Treasury approval status: [PPRA Confirmation].
3. PROGRAMME IMPACT
3.1 Original contract completion date: [Original Completion Date]
3.2 Extension of time granted: [Extension Of Time Days]
3.3 Revised contract completion date: [Revised Completion Date]
3.4 Where an extension of time is granted, the contractor shall not be liable for liquidated damages during the extended period from [Original Completion Date] to [Revised Completion Date].
4. EFFECT ON REMAINING CONTRACT TERMS
4.1 Except as expressly varied by this Variation Order, all other terms and conditions of the original contract dated [Original Contract Date] remain in full force and effect and are not modified by this Variation Order.
4.2 This Variation Order is supported by the consideration of the revised contract value and the parties' mutual agreement to adjust the contract scope, price, and programme as set out above.
4.3 The Limitation of Actions Act Cap. 22 provides a 6-year limitation period from the date of breach of any term of this Variation Order. Parties should retain this document for at least 6 years from the date hereof.
5. AUTHORISATION
Contract administrator / engineer issuing this Variation Order: [Contract Administrator]
This Variation Order is governed by the laws of Kenya, including the Law of Contract Act Cap. 23.
IN WITNESS WHEREOF, the authorised representatives of both parties have signed this Variation Order on the date set out above.
Employer / Client (Authorised Signatory)
________________
Signature
Contractor / Service Provider (Authorised Signatory)
________________
Signature
Contract Administrator / Engineer
________________
Signature
Witness
________________
Signature
What Is a Contract Variation Order (Kenya)?
A Contract Variation Order in Kenya sets out a binding instruction or authorisation for the action it directs.
Under the Law of Contract Act Cap. 23, a variation of an existing contract is itself a new contract and must satisfy the essential requirements for contractual validity: offer (one party proposes the variation), acceptance (the other party agrees), and fresh consideration or acknowledgment that the variation is supported by consideration — typically the mutual benefits flowing from the adjusted contract terms. Where consideration for the variation is absent — for example, where one party simply agrees to do what it was already obliged to do under the original contract at no additional benefit — a Kenyan court may decline to enforce the variation unless it is executed as a deed. Executing the Variation Order before an advocate of the High Court of Kenya as a deed removes the consideration requirement under the Law of Contract Act Cap. 23.
Variation Orders are particularly common in Kenya's construction industry. The Public Procurement and Asset Disposal Act No. 33 of 2015, administered by the Public Procurement Regulatory Authority (PPRA), governs Variation Orders in public procurement contracts. Under the PPRA Regulations, a Variation Order in a public construction or supply contract may not exceed 15% of the original contract sum without fresh approval from the procuring entity's board or the National Treasury. Exceeding this threshold without proper authority constitutes an irregularity reviewable by the PPRA and the Public Procurement Administrative Review Board (PPARB).
The National Construction Authority (NCA), established under the National Construction Authority Act No. 41 of 2011 and the NCA Regulations 2014, regulates construction contracts in Kenya. Building contracts governed by the NCA standard forms — including the JBCC (Joint Building Contracts Committee) and NCA standard building contract forms — include express provisions for Variation Orders, specifying the procedure for the architect or engineer to issue a formal variation instruction, the contractor's entitlement to claim additional time and money, and the valuation methodology for the varied work.
In commercial contracts beyond construction, Variation Orders are commonly used to adjust the scope of IT service agreements, professional consultancy retainers, supply agreements, and outsourcing contracts. The Kenya Information and Communications Act No. 2 of 1998 and the sector regulations of the Communications Authority of Kenya (CA) do not prescribe a specific form for contract variations in the ICT sector, but standard commercial practice in Nairobi's ICT market requires written Variation Orders signed by authorised signatories of both parties.
The Limitation of Actions Act Cap. 22 is relevant to Variation Orders: a variation of contract executed in writing creates a new contractual obligation, and the 6-year limitation period for contract claims under Section 4(1) of the Act runs from the date of the breach of the varied term, not from the date of the original contract. Parties should therefore confirm that Variation Orders are dated and retained for at least 6 years.
When Do You Need a Contract Variation Order (Kenya)?
A Contract Variation Order in Kenya is required whenever the parties to an existing contract wish to formally amend one or more terms without voiding and replacing the entire contract.
A Variation Order is needed when a building contractor in Kenya and the employer wish to adjust the scope of works — for example, to add extra rooms, upgrade specifications, or delete portions of the original building contract — after the construction project has commenced. Without a written Variation Order, additional work done by the contractor may not be compensable, and the contractor may lose the right to claim additional payment for the extra work under the National Construction Authority (NCA) Act No. 41 of 2011.
A Variation Order is required when a public sector procuring entity in Kenya — a Ministry, county government, or state agency — needs to change the scope or price of a contracted supply or service. Under the Public Procurement and Asset Disposal Act No. 33 of 2015 and the PPRA Regulations, any modification to a public contract must be effected through a written Variation Order, and modifications exceeding 15% of the original contract value require fresh procurement authority approval.
A Variation Order is needed when an IT systems integrator and a Kenyan client agree to expand the scope of a software development or IT services contract to include additional modules, extended support periods, or upgraded service levels not covered by the original contract. Writing the agreed scope change into a formal Variation Order prevents disputes about what the supplier is obliged to deliver and what additional fee is payable.
A Variation Order is required when an employer and a consulting engineer, architect, or quantity surveyor agree to extend the duration of a professional services retainer, add new project phases to the scope, or adjust the fee structure. Professional service firms in Kenya governed by the Engineers Board of Kenya (EBK) under the Engineers Act No. 43 of 2011 or the Architects and Quantity Surveyors Act Cap. 525 follow standard form contracts that include Variation Order provisions.
A Variation Order is needed when supply chain disruptions — such as port delays at the Port of Mombasa, currency fluctuations affecting import costs, or material shortages — require the parties to a supply agreement to adjust delivery timelines, substitute materials, or revise unit prices. Documenting the agreed adjustment in a Variation Order protects both the supplier and the buyer from disputes about whether the original contract terms still apply.
A Variation Order is also required when a county government or national government agency in Kenya and a service provider agree to reduce the contracted scope of services due to budget cuts, confirming that the reduction in obligations is matched by a corresponding reduction in the contract price, and that the provider's liability is limited to the varied scope.
What to Include in Your Contract Variation Order (Kenya)
A Kenya Contract Variation Order under the Law of Contract Act Cap. 23 must contain the following elements to be enforceable and commercially effective.
Identification of the Original Contract: The full title of the original contract, the contract reference number, the date of execution, the names of the original parties, and a brief description of the subject matter of the original contract. This identification anchors the Variation Order to the principal agreement and confirms that the parties intend to vary — not replace — the original contract.
Variation Order Number and Date: A unique Variation Order number (e.g., VO-001, VO-002) for record-keeping and reference, and the date on which the Variation Order is issued. Sequential numbering is essential where a contract has multiple Variation Orders, to track the cumulative impact on price and scope.
Description of the Variation: A precise description of what is being changed — the clause or term being varied, what the original provision stated, and what the varied provision now states. In construction contracts, this typically includes a description of the additional, omitted, or substituted work, with reference to drawings or specifications. Ambiguous descriptions of the variation are a common source of disputes before the Kenya High Court's Commercial Division.
Impact on Contract Price: The adjustment to the contract price resulting from the variation — whether an addition, an omission, or a net change — stated in Kenya Shillings (KES). For construction Variation Orders, the valuation should follow the methodology in the original contract (bill rates, schedule of rates, or reasonable cost) or, where no applicable rate exists, a new rate agreed by the parties and the quantity surveyor. For public contracts governed by the Public Procurement and Asset Disposal Act No. 33 of 2015, the Variation Order must confirm that the cumulative variation does not exceed 15% of the original contract price without PPRA approval.
Impact on Programme and Delivery Date: Any extension of the contract completion date or delivery timeline resulting from the variation, stated as additional calendar days. In construction contracts regulated by the National Construction Authority (NCA) Act No. 41 of 2011, the contractor's entitlement to an extension of time for Variation Orders must comply with the contract's extension of time clause to avoid a claim for liquidated damages on the extended period.
Consideration and Enforceability: The Variation Order should expressly state the consideration supporting the varied terms — typically the revised contract price — to satisfy the enforceability requirement under the Law of Contract Act Cap. 23. Where consideration is not obvious, the parties should execute the Variation Order as a deed before an advocate of the High Court of Kenya.
Effect on Remaining Contract Terms: An express statement that all other terms of the original contract remain in full force and effect and are not varied by this Variation Order. This confirmation clause prevents arguments that the Variation Order has inadvertently affected other contract terms.
Authorised Signatories: Signatures of authorised representatives of both parties — with names, titles, and company seals where applicable — confirming agreement to the variation. For corporate parties, the signatory must be authorised under the company's board resolution or the Companies Act No. 17 of 2015. The forms-legal.com Kenya Contract Variation Order template covers all mandatory and best-practice elements for construction contracts, service agreements, and supply contracts across Kenya's public and private sectors, and is formatted for use with standard NCA and PPRA contract frameworks. Under Kenya law, Section 3 of the Companies Act 2015 (No. 17 of 2015) and Section 15 of the Employment Act 2007 (No. 11 of 2007) govern the core requirements for this type of document.
Under the Companies Act No. 17 of 2015, the Registrar of Companies at the Office of the Attorney General maintains the register of Kenyan companies. Section 3 of the Law of Contract Act (Cap. 23) governs contractual obligations. The Competition Authority of Kenya (CAK) enforces the Competition Act No. 12 of 2010. The Kenya Revenue Authority (KRA) administers corporate tax under the Income Tax Act (Cap. 470). The High Court of Kenya has unlimited original jurisdiction under Article 165 of the Constitution of Kenya 2010.
Cite this page
Reference this free template in an article, syllabus, or research note:
Forms Legal. (2026). Contract Variation Order (Kenya) (Kenya) [Legal document template]. Forms Legal. https://forms-legal.com/kenya/business/contracts/variation-order-kenya
"Contract Variation Order (Kenya) (Kenya)." Forms Legal, 2026, https://forms-legal.com/kenya/business/contracts/variation-order-kenya.
@misc{formslegal-variation-order-kenya,
author = {{Forms Legal}},
title = {Contract Variation Order (Kenya) (Kenya)},
year = {2026},
howpublished = {\url{https://forms-legal.com/kenya/business/contracts/variation-order-kenya}},
note = {Free legal document template}
}Frequently Asked Questions
A Contract Variation Order is legally binding in Kenya under the Law of Contract Act Cap. 23, provided it satisfies the requirements of a valid contract variation: an agreement between the parties (offer and acceptance), consideration supporting the variation, and authorised signatures from both parties. A written, signed Variation Order is the most effective form: it creates a clear documentary record of the agreed changes, the adjusted price, and the revised timeline. Where a Variation Order is executed as a deed — signed, witnessed, and sealed before an advocate of the High Court of Kenya — the consideration requirement is dispensed with, which is useful where the variation benefits only one party. An oral agreement to vary a contract is technically enforceable under Kenyan law but is very difficult to prove in court, particularly in construction and commercial disputes before the High Court of Kenya's Commercial and Tax Division. The Limitation of Actions Act Cap. 22 gives parties 6 years from the date of breach of the varied term to bring a claim in Kenyan courts.
Yes, but subject to strict limits under the Public Procurement and Asset Disposal Act No. 33 of 2015 and the Public Procurement and Asset Disposal Regulations 2020, administered by the Public Procurement Regulatory Authority (PPRA). A Variation Order in a public contract must be in writing and signed by the authorised officer of the procuring entity. The cumulative value of all Variation Orders on a single public contract must not exceed 15% of the original contract sum, unless a fresh competitive procurement process is conducted for the additional scope. A Variation Order that causes the cumulative variation to exceed 15% without PPRA or National Treasury approval constitutes a procurement irregularity, reviewable by the Public Procurement Administrative Review Board (PPARB) on application by an aggrieved tenderer. The procuring entity must maintain a variation order register and report all approved variations in its annual procurement report to the PPRA. Construction Variation Orders on government projects must also be signed by the government's project architect or engineer before they take effect.
Where a contractor in Kenya carries out additional work without an authorised Variation Order, the contractor's right to payment for that work is at significant risk. Most standard construction contracts in Kenya — including the NCA standard building contract and the FIDIC suite used on infrastructure projects — require the contractor to obtain a written variation instruction from the architect or engineer before commencing varied work, except in emergency situations. Without a written Variation Order, the employer may refuse to pay for the extra work on the ground that no variation was authorised. The contractor may attempt to claim on a quantum meruit basis — that is, the reasonable value of the work done — before the High Court of Kenya under the Law of Contract Act Cap. 23 principles of unjust enrichment, but such claims are contested and uncertain. The National Construction Authority (NCA) Act No. 41 of 2011 and the NCA Conditions of Contract support the practice of prior written authorisation for variations. Contractors in Kenya should always insist on a written Variation Order — however informal the project — before committing resources to additional work.
The valuation of a Variation Order in a Kenya construction contract follows the methodology specified in the original contract. Under NCA-standard and FIDIC-based contracts commonly used in Kenya, the primary valuation basis is the bill of quantities rates or schedule of rates agreed in the original contract. Where the additional or substituted work is of the same character and executed under similar conditions as work in the original bill, the contract rate applies directly. Where the work is of a similar character but executed under different conditions or in significantly different quantities, a rate pro-rated from the original bill rate is used. Where no applicable rate exists — for entirely new scope — the parties, assisted by the quantity surveyor, agree a new rate based on the cost of labour, materials, plant, and overheads plus a reasonable mark-up for profit. On public contracts under the Public Procurement and Asset Disposal Act No. 33 of 2015, the valuation must be certified by the procuring entity's quantity surveyor and approved by the head of the procuring entity. Disputes about Variation Order valuations are common in Kenya's construction industry and are regularly adjudicated before arbitration panels under the Arbitration Act No. 4 of 1995 and the Nairobi Centre for International Arbitration (NCIA).
Yes. A Variation Order that increases the scope of work or changes the character of the work in a way that requires additional time to complete entitles the contractor to an extension of time under the extension of time clause of the original contract. In Kenya construction contracts based on the NCA standard form or the FIDIC Red Book (Conditions of Contract for Construction), the contractor must notify the architect or engineer of a claim for extension of time within the period specified in the contract — typically 28 days of the variation instruction — failing which the right to an extension may be lost. The extension of time should be stated in the Variation Order itself, as additional calendar days to the original contract completion date, to avoid the contractor being penalised by liquidated damages for late completion during the extended period. The architect or engineer values the time impact of the variation and issues an extension certificate. Where the parties cannot agree on the extension, the dispute may be referred to adjudication or arbitration under the contract's dispute resolution clause.
In Kenya, a Contract Variation Order and a Contract Addendum are both instruments that modify an existing contract, but they are used in different contexts and serve different purposes. A Variation Order is predominantly used in construction, engineering, and procurement contracts where variations to the scope of work, price, or programme arise during the execution phase of an ongoing project. A Variation Order is typically issued under authority given by the original contract — the architect, engineer, or project manager issues the instruction and the parties confirm the price and time impact. The term and the associated procedure are defined in the contract itself, often referencing the NCA or FIDIC conditions of contract. A Contract Addendum is a broader term covering any supplemental document that adds to, amends, or modifies a contract after execution — it is not limited to scope changes during execution but may add entirely new obligations, extend the term of a service contract, or document agreed price revisions in a commercial supply agreement. Both instruments require the written agreement and authorised signatures of both contracting parties to be binding under the Law of Contract Act Cap. 23. For construction and government procurement contracts in Kenya, the term Variation Order is standard; for commercial and service contracts, Contract Addendum is more commonly used.
This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer
Found an error? Let us knowRelated Documents
You may also find these documents useful:
Construction Contract (Kenya)
A Kenya Construction Contract between an employer and a contractor for building works, compliant with the National Construction Authority Act No. 41 of 2011, the Architects and Quantity Surveyors Act (Cap. 525), and the Kenya Building Code.
Contract Extension Notice (Kenya)
A Kenya Contract Extension Notice formally extending the term of an existing contract under the Law of Contract Act (Cap. 23), with revised end date, amended terms, and mutual acknowledgment.
Deed of Novation (Kenya)
A Kenya Deed of Novation transferring all rights and obligations under an existing contract from an outgoing party to an incoming party, governed by the Law of Contract Act (Cap. 23) and executed as a deed.