Construction Contract (Kenya)
CONSTRUCTION CONTRACT
National Construction Authority Act No. 41 of 2011 | Architects and Quantity Surveyors Act (Cap. 525) | Engineers Act No. 43 of 2011
THIS CONSTRUCTION CONTRACT (the "Contract") is made on [Contract Date]
BETWEEN:
(1) [Employer Name] (BRS No: [Employer BRS Number]), of [Employer Address] (the "Employer"); and
(2) [Contractor Name] (BRS No: [Contractor BRS Number], NCA Registration No: [NCA Number]), of [Contractor Address] (the "Contractor").
1. WORKS AND SITE
1.1 Project: [Project Title]
1.2 Site: [Site Address]
1.3 Scope of Works: [Works Description]
1.4 Planning Approval Reference: [Planning Approval]. Planning permission has been or will be obtained from the relevant county government authority under the Physical and Land Use Planning Act No. 13 of 2019.
1.5 The Contractor warrants that it holds a valid NCA registration certificate under Section 15 of the National Construction Authority Act No. 41 of 2011 and will maintain such registration throughout the contract period.
2. CONTRACT SUM AND PAYMENT
2.1 Contract Sum: [Contract Sum] (subject to adjustment for variations and fluctuations as agreed).
2.2 NCA Development Levy: [NCA Levy], representing 0.5% of the Contract Sum, payable by the Employer to the National Construction Authority before commencement of works under the National Construction Authority (Levy) Regulations 2014.
2.3 Payment terms: [Payment Terms]. The Contract Administrator is [Contract Administrator].
2.4 Retention: [Retention Rate] of each certified amount, held as security for defects liability obligations. Released 50% at practical completion; 50% at the end of the defects liability period.
2.5 The Employer shall pay each certified amount within [Payment Period] of the payment certificate. VAT at 16% under the Value Added Tax Act No. 35 of 2013 shall be charged by the Contractor where it is VAT-registered with the Kenya Revenue Authority (KRA).
3. CONSTRUCTION PROGRAMME AND COMPLETION
3.1 The Contractor shall commence the Works on [Commencement Date] and shall achieve practical completion by [Completion Date].
3.2 Liquidated and Ascertained Damages: If the Contractor fails to achieve practical completion by [Completion Date], the Contractor shall pay liquidated damages of [Liquidated Damages] to the Employer for each week (or part week) of delay, deductible from sums otherwise due.
3.3 Defects Liability Period: [DLP] from the date of practical completion. During this period, the Contractor shall rectify all defects notified by the Employer at no additional cost.
4. INSURANCE, SAFETY, AND COMPLIANCE
4.1 The Contractor shall maintain, at its own cost throughout the contract period: (a) all-risks / contractors' all-risks insurance covering the works and materials on site; (b) public liability insurance; and (c) employer's liability (workmen's compensation) insurance under the Work Injury Benefits Act No. 13 of 2007 (WIBA), placed with an insurer licensed by the Insurance Regulatory Authority (IRA).
4.2 The Contractor shall comply with the Occupational Safety and Health Act No. 15 of 2007 (OSHA) in the management of the construction site, including the appointment of a safety officer for sites with more than 20 workers.
4.3 The Contractor shall comply with all conditions imposed by the National Environment Management Authority (NEMA) under the Environmental Management and Co-ordination Act (No. 8 of 1999) in relation to the construction works.
5. GOVERNING LAW AND DISPUTE RESOLUTION
5.1 This Contract shall be governed by and construed in accordance with the laws of Kenya.
5.2 Any dispute arising from or in connection with this Contract shall be referred first to the Contract Administrator for a decision. If not resolved within 14 days, either Party may refer the dispute to arbitration at the Nairobi Centre for International Arbitration (NCIA) under the Arbitration Act No. 4 of 1995 (revised 2022). In the absence of an arbitration reference, the courts of [Governing County] shall have jurisdiction.
IN WITNESS WHEREOF, the Parties have signed this Contract on the date first written above.
Employer / Authorised Signatory
________________
Signature
Contractor / Authorised Signatory
________________
Signature
Witness
________________
Signature
What Is a Construction Contract (Kenya)?
A Construction Contract in Kenya records the obligations the parties accept and the terms governing their arrangement.
The National Construction Authority (NCA), established under the National Construction Authority Act No. 41 of 2011, is the primary regulatory body for the construction industry in Kenya. Every contractor undertaking construction works in Kenya must be registered with the NCA and must hold a valid NCA certificate in the appropriate category — NCA 1 through NCA 8, with NCA 1 being the highest classification for large-scale national and international projects. The NCA levy of 0.5% of the contract sum is payable by the employer before construction commences, remitted to the NCA, and must be referenced in the construction contract.
Architectural designs for any building requiring planning approval must be prepared by a registered architect under the Architects and Quantity Surveyors Act (Cap. 525), administered by the Board of Registration of Architects and Quantity Surveyors (BORAQS). Structural drawings must be prepared or supervised by a registered engineer under the Engineers Act No. 43 of 2011, regulated by the Engineers Board of Kenya (EBK). Quantity surveying services — including preparing bills of quantities (BOQ) that form the pricing basis of a construction contract — must be provided by a registered quantity surveyor under the same Cap. 525 Act.
Planning permission for any building works that alter the exterior of a property, change its use, or exceed specified dimensions must be obtained from the county government planning authority — in Nairobi, this is the Nairobi City County Government under the Physical and Land Use Planning Act No. 13 of 2019. Building approval from the county engineer and relevant approvals from the National Environment Management Authority (NEMA) for developments with potential environmental impact are prerequisites before construction commences.
A Kenya Construction Contract should be distinguished from a Consultancy Agreement with an architect or engineer (which governs professional advisory services) and from an Independent Contractor Agreement for minor works or labour-only contracts. The Construction Contract covers the full scope of building works — materials, labour, plant, and programme — and typically incorporates industry-standard conditions such as the JBCC (Joint Building Contracts Committee) suite, FIDIC (International Federation of Consulting Engineers) conditions, or the NCA standard form for public sector projects.
The legal framework governing the Construction Contract (Kenya) in Kenya draws on several key statutes and regulatory bodies. Under the Land Act No. 6 of 2012, the National Land Commission (NLC) manages public land in Kenya. Section 56 of the Land Registration Act No. 3 of 2012 governs land transfers. The Environment and Land Court (ELC) has exclusive jurisdiction under Article 162(2)(b) of the Constitution of Kenya 2010. The Land Control Act (Cap. 302) requires Land Control Board consent for agricultural land transactions. The Stamp Duty Act (Cap. 480) imposes duty on property transfers at rates of 2% (rural) and 4% (urban). Parties executing a Construction Contract (Kenya) in Kenya should confirm the document reflects current law, including any amendments enacted since the original drafting date. The National Construction Authority Act No. 41 of 2011 sets the foundational requirements.
When Do You Need a Construction Contract (Kenya)?
A Kenya Construction Contract is required at the outset of any significant building or infrastructure project, and is specifically necessary in the following situations.
A Construction Contract is required when a property owner or developer in Kenya engages a registered NCA contractor to construct a residential house, commercial building, industrial facility, or infrastructure works. Under the National Construction Authority Act No. 41 of 2011, the NCA requires evidence of a written contract and proof of payment of the NCA levy (0.5% of the contract sum) before issuing project registration. Projects commenced without NCA registration expose both the employer and the contractor to fines and the risk of a stop-works order.
A Construction Contract is needed when a real estate developer registered with the lands registry under the Land Registration Act No. 3 of 2012 intends to build on a plot in Nairobi, Mombasa, Kisumu, or any other county and wishes to secure the contractor's obligations on scope, quality, programme, and price before investing the contract sum. Without a written contract, disputes about variations, delay penalties, and defective work are decided by implication — invariably to the disadvantage of one party.
A Construction Contract is required when a contractor registered under the NCA in a specific category (NCA 1 to NCA 8) submits a tender for private or public works and the award is made by the employer. The contract formalises the tender acceptance, converts the contractor's priced bill of quantities (BOQ) into a binding obligation, and establishes the payment certification procedure.
A Construction Contract is needed when the works involve government or county government procurement. The Public Procurement and Asset Disposal Act No. 33 of 2015, enforced by the Public Procurement Regulatory Authority (PPRA), requires all public sector construction contracts to be in writing and to comply with PPRA standard bidding documents.
A Construction Contract is required when the employer wishes to impose liquidated and ascertained damages (LADs) for delayed completion — a contractual penalty clause for delay that must be expressly stated in the written contract to be enforceable before the High Court of Kenya (Commercial Division) or the Nairobi Centre for International Arbitration (NCIA).
What to Include in Your Construction Contract (Kenya)
A Kenya Construction Contract must include the following core provisions to be enforceable and consistent with the National Construction Authority Act No. 41 of 2011 and Kenyan construction industry standards.
Parties and NCA Registration: Full legal names, BRS registration numbers, KRA PIN numbers, and NCA contractor registration numbers of both the employer and the contractor. The contractor's NCA category (NCA 1 through NCA 8) must be stated. Section 15 of the National Construction Authority Act No. 41 of 2011 prohibits any person from undertaking construction works without NCA registration.
Scope of Works: A precise description of the building or civil works to be carried out, ideally by reference to the architectural drawings prepared by a registered architect under Cap. 525, the structural drawings, and the priced bill of quantities (BOQ) prepared by a registered quantity surveyor — all incorporated by reference as contract documents. Ambiguity in scope is the most common cause of construction disputes in Kenya.
Contract Sum and Payment: The agreed contract sum in Kenya Shillings (KES) and the payment schedule — typically milestone payments tied to the construction programme or monthly valuations certified by the contract administrator. The NCA levy of 0.5% of the contract sum must be noted, confirmed as paid or payable. Section 13 of the National Construction Authority Act requires the levy to be paid before work commences.
NCA Levy: Confirmation that the NCA development levy of 0.5% of the total contract sum has been or will be paid by the employer to the National Construction Authority before work commences, as required under the National Construction Authority (Levy) Regulations 2014.
Construction Programme: A baseline programme (typically in the form of a Gantt chart) showing the key milestones, the agreed completion date, and any sectional completion dates. Liquidated and ascertained damages (LADs) for delay beyond the completion date — expressed as a daily or weekly sum in KES — must be agreed in writing before the contract is executed to be enforceable.
Variations: The procedure for instructing and valuing changes to the scope of works. The contract administrator — typically the architect or project manager — must issue a written variation instruction before any additional work is carried out. Oral instructions without written confirmation have limited enforceability before the High Court of Kenya.
Defects Liability: A defects liability period — typically 12 months after practical completion — during which the contractor must rectify any defects notified by the employer, at no additional cost. A retention sum (typically 5% to 10% of the contract sum) is held by the employer as security for the contractor's defects liability obligations, released in two tranches: 50% at practical completion and 50% at the end of the defects liability period.
Insurance and OSHA Compliance: Requirements for the contractor to maintain all risks insurance (covering the works and materials on site), public liability insurance, and employer's liability insurance under the Work Injury Benefits Act No. 13 of 2007 (WIBA). Compliance with the Occupational Safety and Health Act No. 15 of 2007 (OSHA) is mandatory on all construction sites. The forms-legal.com Kenya Construction Contract template covers all eight elements above in a structured questionnaire aligned with NCA and industry standards.
Governing Law and Dispute Resolution: The contract shall be governed by the laws of Kenya. Disputes may be referred to the Nairobi Centre for International Arbitration (NCIA) under the Arbitration Act No. 4 of 1995 (revised 2022), or to the High Court of Kenya. Many construction contracts in Kenya incorporate a tiered dispute resolution clause: engineer's decision, then mediation, then arbitration.
Cite this page
Reference this free template in an article, syllabus, or research note:
Forms Legal. (2026). Construction Contract (Kenya) (Kenya) [Legal document template]. Forms Legal. https://forms-legal.com/kenya/real-estate/property/construction-contract-kenya
"Construction Contract (Kenya) (Kenya)." Forms Legal, 2026, https://forms-legal.com/kenya/real-estate/property/construction-contract-kenya.
@misc{formslegal-construction-contract-kenya,
author = {{Forms Legal}},
title = {Construction Contract (Kenya) (Kenya)},
year = {2026},
howpublished = {\url{https://forms-legal.com/kenya/real-estate/property/construction-contract-kenya}},
note = {Free legal document template}
}Also available for these jurisdictions:
Frequently Asked Questions
Yes. Under Section 15 of the National Construction Authority Act No. 41 of 2011, no person may carry out construction works in Kenya without being registered with the National Construction Authority (NCA). The NCA classifies contractors into eight categories — NCA 1 (highest, for major national and international projects) through NCA 8 (smallest, for minor works) — based on the contractor's financial capacity, technical expertise, and experience. A contractor who undertakes works without NCA registration commits an offence under the Act and is liable to a fine. The employer who engages an unregistered contractor also risks NCA enforcement, including a stop-works order. NCA registration must be renewed annually, and the contractor must hold a valid NCA certificate at the time the construction contract is signed. Before awarding a construction contract, the employer should verify the contractor's NCA registration number and category on the NCA online register at nca.go.ke. Engaging an NCA-registered contractor in the appropriate category is also a prerequisite for obtaining planning and building approval from county government authorities.
The NCA development levy is a statutory charge of 0.5% of the total contract sum, payable by the employer (project owner) to the National Construction Authority before construction works commence. The levy is established under the National Construction Authority (Levy) Regulations 2014, made under the National Construction Authority Act No. 41 of 2011. The employer pays the levy to the NCA — not to the contractor — and must obtain a receipt or project registration certificate from the NCA as proof of payment. This receipt is typically required by county government building control departments as a prerequisite for issuing a building permit. Failure to pay the NCA levy before commencing works is an offence, and the NCA may issue a stop-works order for projects commenced without levy payment. The NCA levy is not VAT — it is a separate statutory charge. The employer should budget for the NCA levy separately from the contract sum and from the 16% VAT charged by the contractor under the Value Added Tax Act No. 35 of 2013 if the contractor is VAT-registered with the Kenya Revenue Authority.
Liquidated and ascertained damages (LADs) in a Kenya Construction Contract are a pre-agreed contractual penalty that the contractor must pay to the employer for each day or week that the works are not completed beyond the agreed completion date. LADs must be expressly stated in the written contract as a fixed sum in Kenya Shillings (KES) per day or week — they cannot be implied. The High Court of Kenya (Commercial Division) enforces LADs clauses provided the sum represents a genuine pre-estimate of the employer's loss and is not a penalty intended to punish rather than compensate. The principles established in Dunlop Pneumatic Tyre Co v New Garage and Motor Co [1915] AC 79 — received English case law applied in Kenya under Section 3 of the Judicature Act (Cap. 8) — continue to guide Kenyan courts in assessing whether an LADs clause is enforceable. The contractor may be entitled to an extension of time, cancelling the LADs obligation, if the delay was caused by the employer, by force majeure events, or by variations instructed by the contract administrator. The extension of time procedure must be specified in the contract.
A defects liability period (DLP) in a Kenya Construction Contract is the period — typically 12 months after practical completion — during which the contractor remains obligated to return to site and rectify any defects, shrinkages, or other faults in the works notified by the employer, at no additional cost to the employer. The DLP is enforced through a retention mechanism: the employer retains a percentage of the contract sum (typically 5% to 10%) as security for the contractor's DLP obligations. One half of the retention is typically released at practical completion and the second half at the end of the DLP, after a final inspection confirms all defects have been remedied. The concept of a DLP is recognised in standard Kenyan construction contracts, including the NCA standard form, the JBCC suite adapted for use in Kenya, and FIDIC conditions used for international projects. Practical completion is certified by the contract administrator (typically the architect registered under the Architects and Quantity Surveyors Act Cap. 525) when the works are substantially complete and the employer can take beneficial occupation. Disputes about DLP defects and retention releases are among the most common subjects of construction arbitration at the Nairobi Centre for International Arbitration (NCIA).
A contractor undertaking construction works in Kenya must maintain several categories of insurance under Kenyan law and standard construction contract requirements. Employer's liability insurance (also called workmen's compensation insurance) is mandatory under the Work Injury Benefits Act No. 13 of 2007 (WIBA), which requires employers — including contractors — to compensate employees injured during the course of employment. Failure to maintain WIBA cover is a criminal offence. All-risks or contractors' all-risks (CAR) insurance covers the works, materials on site, and plant and equipment against physical loss or damage during construction. Public liability insurance covers the contractor's legal liability to third parties — members of the public, neighbours, or bystanders — for injury or property damage caused by the construction works. Professional indemnity insurance applies to design-and-build contractors who both design and construct the works. Insurance policies must be placed with an insurer licensed by the Insurance Regulatory Authority (IRA) under the Insurance Act (Cap. 487). The construction contract should specify the minimum insured amounts, the requirement to name the employer as a co-insured on relevant policies, and the obligation to produce insurance certificates before works commence.
Yes. A Kenya Construction Contract may be terminated early by either party in defined circumstances. The employer may typically terminate the contract if the contractor abandons the works, persistently fails to proceed regularly and diligently, becomes insolvent under the Insolvency Act No. 18 of 2015, or fails to remedy a material breach after written notice and a reasonable cure period. The contractor may typically terminate if the employer fails to pay certified amounts within the agreed period, prevents the contractor from carrying out the works, or becomes insolvent. Upon employer termination for contractor default, the employer may engage a replacement contractor at the defaulting contractor's cost. Upon contractor termination for employer default, the contractor is entitled to recover the value of work executed to the termination date plus loss of profit on the uncompleted portion. Disputes about the validity and consequences of termination are frequently referred to arbitration at the Nairobi Centre for International Arbitration (NCIA) under the Arbitration Act No. 4 of 1995 (revised 2022). The High Court of Kenya (Commercial Division) has jurisdiction over construction contract disputes where no arbitration agreement exists.
This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer
Found an error? Let us knowRelated Documents
You may also find these documents useful:
Construction Payment Certificate (Kenya)
A Kenya Construction Payment Certificate issued by an architect or contract administrator certifying the value of works completed and the amount due to the contractor, consistent with the Architects and Quantity Surveyors Act (Cap. 525) and standard Kenyan construction contract practice.
Promissory Note (Kenya)
A Kenya Promissory Note — an unconditional written promise to pay a specified sum — governed by the Bills of Exchange Act Cap. 27 and enforceable in the High Court of Kenya or the Small Claims Court.
Independent Contractor Agreement (Kenya)
A Kenya Independent Contractor Agreement clearly establishing a service relationship — not employment — under the Employment Act No. 11 of 2007, Income Tax Act Cap. 470, and Data Protection Act No. 24 of 2019.