Construction Contract (Hong Kong)
CONSTRUCTION CONTRACT
Buildings Ordinance (Cap. 123), Factories and Industrial Undertakings Ordinance (Cap. 59), Hong Kong SAR
This Construction Contract is made on [Contract Date] between:
(1) [Employer Name] (CRN: [Employer CRN]) of [Employer Address] (“the Employer”); and
(2) [Contractor Name] (CRN: [Contractor CRN]) of [Contractor Address] (“the Contractor”).
1. THE WORKS
1.1 Project: [Project Name] at [Site Address].
1.2 The Contractor shall carry out and complete the following works: [Scope of Works].
1.3 The Works shall be executed in accordance with the drawings, specifications, and bills of quantities (if any) forming part of this Contract.
1.4 The Contractor shall comply with the Buildings Ordinance (Cap. 123), Building (Planning) Regulations, Building (Construction) Regulations, and all applicable codes of practice.
2. TIME FOR COMPLETION
2.1 The Contractor shall complete the Works within [Completion Period].
2.2 If the Contractor fails to complete the Works by the completion date (as extended), the Contractor shall pay or allow liquidated damages of [Liquidated Damages] per calendar day of delay.
2.3 The Contractor is entitled to an extension of time for delays caused by: variations instructed by the Architect; force majeure events; exceptionally adverse weather; and other events specified in the Contract.
3. CONTRACT SUM AND PAYMENT
3.1 Contract sum: [Contract Sum]. Basis: [Contract Basis]. No GST or VAT applies in Hong Kong.
3.2 Interim payments: [Interim Payment Frequency], based on the value of work properly executed, less retention of [Retention Rate].
3.3 The Employer shall pay each interim certificate within 28 days of the Architect’s certification.
3.4 Half of the retention shall be released upon practical completion. The remaining retention shall be released upon expiry of the defects liability period and issue of the Defects Rectification Certificate.
4. SAFETY
4.1 The Contractor shall comply with the Factories and Industrial Undertakings Ordinance (Cap. 59), the Construction Sites (Safety) Regulations, the Construction Sites (Safety Management) Regulations, and the Occupational Safety and Health Ordinance (Cap. 509).
4.2 The Contractor shall prepare and implement a safety plan for the Works and appoint a qualified safety officer.
4.3 The Contractor shall indemnify the Employer against all claims, liabilities, and costs arising from safety breaches on the site.
5. DEFECTS LIABILITY
5.1 The defects liability period is [Defects Liability Period] from the date of practical completion.
5.2 The Contractor shall rectify all defects notified during the DLP at the Contractor’s own cost within a reasonable time.
5.3 If the Contractor fails to rectify defects, the Employer may engage others and recover the costs from the Contractor.
6. VARIATIONS
6.1 The Architect may issue variation instructions adding to, omitting from, or changing the Works.
6.2 Variations shall be valued using: contract rates where applicable; fair rates where contract rates are not applicable; or daywork rates for work that cannot be measured.
7. GOVERNING LAW AND DISPUTES
7.1 This Contract is governed by the laws of the Hong Kong Special Administrative Region of the People’s Republic of China.
7.2 Disputes: [Dispute Resolution].
EXECUTION
IN WITNESS WHEREOF, the Parties have executed this Construction Contract as of the date first written above.
Employer (Authorised Signatory)
________________
Signature
Contractor (Authorised Signatory)
________________
Signature
What Is a Construction Contract (Hong Kong)?
Construction Contract in Hong Kong is the legally binding agreement between a project owner (Employer) and a contractor under which the contractor undertakes to execute specified construction, renovation, or engineering works in exchange for payment, governed by the Buildings Ordinance (Cap. 123), the Construction Industry Council Ordinance (Cap. 587), the Employees' Compensation Ordinance (Cap. 282), the Occupational Safety and Health Ordinance (Cap. 509), and the Arbitration Ordinance (Cap. 609) — the principal statutes that frame construction relationships in the Hong Kong SAR.
The Buildings Ordinance (Cap. 123) is the foundational statute for building works in Hong Kong. Section 14 of Cap. 123 prohibits any person from carrying out, or permitting to be carried out, any building works or street works in Hong Kong without the prior approval of the Building Authority (the Director of Buildings) unless the works fall within the exempted works categories under the Minor Works Control System introduced by the Building (Minor Works) Regulation. Building plans must be submitted by an Authorised Person — a registered architect, engineer, or surveyor — under Section 16 of Cap. 123. All contractors engaged in building works must be registered under the Contractors Registration System maintained by the Buildings Department.
The Construction Industry Council (CIC), established under the Construction Industry Council Ordinance (Cap. 587), maintains the Register of Construction Workers and the Register of Contractors. Under the Construction Workers Registration Ordinance (Cap. 583), construction workers engaged in prescribed trades must hold a valid Construction Worker Registration Card. A Construction Contract should require the contractor to warrant that all workers employed on the project hold valid registrations.
Employers' liability for injuries to construction workers is governed by the Employees' Compensation Ordinance (Cap. 282), which requires employers to maintain employees' compensation insurance covering all employees. The Occupational Safety and Health Ordinance (Cap. 509) and the Construction Sites (Safety) Regulations (Cap. 59I) impose detailed safety obligations on contractors at Hong Kong construction sites — the site safety supervisor, safety officer, and safety committee requirements depend on the contract value and number of workers.
Payment in construction contracts is frequently governed by the standard form contracts adopted in Hong Kong, including the Hong Kong Government General Conditions of Contract (GCC) for public works, the Hong Kong Institute of Architects (HKIA) Standard Form of Building Contract, and the Hong Kong Institute of Engineers (HKIE) conditions for engineering contracts. For private construction projects, the parties may adopt standard forms or negotiate bespoke terms. The Construction Industry Council has promoted the adoption of fair payment terms — typically 30-day payment cycles from submission of payment claims — to address cash flow challenges in the industry.
Dispute resolution in Hong Kong construction contracts typically uses HKIAC arbitration under the Arbitration Ordinance (Cap. 609) or adjudication under the Construction Industry Payment and Adjudication Act framework, which is currently being developed for legislative implementation in Hong Kong following the model of Singapore's SOPA.
When Do You Need a Construction Contract (Hong Kong)?
Construction Contract in Hong Kong is needed for any project involving building, renovation, fitting-out, demolition, or engineering works — regardless of project value — to allocate risk, define scope and payment terms, establish the programme, and create a framework for managing variations, delays, and disputes.
New residential and commercial development projects in Hong Kong require Construction Contracts between the developer (as Employer) and the main contractor. The contract must address: Buildings Ordinance (Cap. 123) compliance including appointment of an Authorised Person; CIC contractor registration; Mandatory Provident Fund (MPF) obligations under Cap. 485 for all construction workers; employees' compensation insurance under Cap. 282; and site safety compliance under Cap. 509 and Cap. 59I.
Fitting-out and renovation works in commercial premises — offices, retail units, restaurants, and industrial buildings — require Construction Contracts even for relatively modest projects. Fit-out contractors must comply with the Minor Works Control System under the Buildings Ordinance (Cap. 123) and the property management company's requirements for approved contractors.
Government and public sector construction projects are awarded under standard Government General Conditions of Contract by the Architectural Services Department, the Civil Engineering and Development Department (CEDD), and the Housing Department. Private projects on government land must obtain consent from the relevant land lessor under the Lands Department.
Demolition contracts require Construction Contracts with specific safety plans approved by the Buildings Department under Cap. 123. Contractors carrying out demolition works must hold a Specialist Contractor registration in the Demolition Works category.
MEP (mechanical, electrical, and plumbing) specialist subcontracts require sub-contract agreements consistent with the main Construction Contract in terms of insurance, safety, and payment provisions. The main contractor remains responsible to the Employer for the performance of all subcontractors.
Small works and minor repairs on private residential property in Hong Kong require Construction Contracts even for low-value projects, because the Buildings Ordinance (Cap. 123) Minor Works Control System classifies minor works by risk level and mandates specific contractor registration. Section 38B of Cap. 123 makes it an offence to carry out prescribed building works without using a registered contractor. A Construction Contract documents the contractor's registration details and provides recourse if the works are defective.
Public infrastructure projects under the Capital Works Programme administered by the Works Branch of the Development Bureau use standard Government General Conditions of Contract (GCC) incorporating Bills of Quantities measured according to the Hong Kong Standard Method of Measurement. Private clients adopting GCC terms for their projects benefit from decades of adjudication precedent in Hong Kong's Construction Industry Arbitration Centre (CIAC).
What to Include in Your Construction Contract (Hong Kong)
Construction Contract in Hong Kong must contain the following essential elements to allocate risk appropriately, comply with the Buildings Ordinance (Cap. 123) and associated regulations, and provide a clear framework for managing the project from commencement to completion and beyond.
Party Identification records the full legal names and Company Registration Numbers from the Companies Registry (Cap. 622) of the Employer and the Contractor, and identifies any Authorised Person (AP), Registered Structural Engineer (RSE), and Registered Geotechnical Engineer (RGE) appointed under the Buildings Ordinance (Cap. 123).
Scope of Works defines in precise detail the construction works to be executed by the Contractor: the works description, reference drawings, specification documents, bill of quantities, and any Employer's Requirements for design-and-build contracts. Ambiguity in the scope of works is the most common source of construction disputes in Hong Kong.
Contract Sum and Payment Terms states the contract sum in HKD, the payment schedule (interim valuations, payment milestones, or a lump sum), the timeframe for issuing payment certificates (typically 14-21 days after submission), the period for payment after certification (typically 14-28 days), and the rate of interest on overdue amounts.
Variation Mechanism establishes the procedure for instructing and valuing variations — changes to the scope, quality, or quantity of works. Variations must be instructed in writing by the Employer or Architect. The valuation methodology — using contract rates, daywork rates, or fair valuation — must be agreed in advance.
Programme and Delay establishes the contract period, the completion date, the sectional completion dates (if any), the notice requirements for delay events, the mechanism for awarding extensions of time, and the liquidated damages rate (in HKD per day or per week) payable by the Contractor for culpable delay.
Site Safety Obligations requires the Contractor to comply with Cap. 509, Cap. 59I, and the project-specific Site Safety Plan. The Contractor must appoint a Safety Officer and a Site Safety Supervisor meeting the qualifications specified by the Labour Department and the Buildings Department.
Insurance requirements mandate: employers' compensation insurance under Cap. 282 for all workers; contractors' all-risks (CAR) insurance; and third-party liability insurance with minimum coverage amounts specified in HKD.
Defects Liability Period specifies the period (typically 12 months from practical completion) during which the Contractor must rectify defects at no cost to the Employer. A retention sum — typically 5-10% of the contract sum — is withheld until the expiry of the defects liability period.
Dispute Resolution specifies HKIAC arbitration under Cap. 609 as the dispute resolution mechanism, with Hong Kong as the seat of arbitration. The forms-legal.com Construction Contract template includes a variation log, a payment certificate schedule, a defects list, and an HKIAC arbitration clause.
Environmental and Nuisance Control requirements under the Noise Control Ordinance (Cap. 400) and the Air Pollution Control Ordinance (Cap. 311) must be addressed in the Construction Contract. Percussive piling and other construction noise is regulated under Cap. 400 — permits from the Environmental Protection Department (EPD) are required for construction noise in residential areas. Dust suppression measures under the Air Pollution Control (Construction Dust) Regulation (Cap. 311P) must be implemented and documented.
Sources & Citations
Statutory citations link to official government sources.
- Buildings Ordinance (Cap. 123)HK official
- Construction Industry Council Ordinance (Cap. 587)HK official
- Employees' Compensation Ordinance (Cap. 282)HK official
- Occupational Safety and Health Ordinance (Cap. 509)HK official
- Arbitration Ordinance (Cap. 609)HK official
- The Buildings Ordinance (Cap. 123)HK official
- Council (CIC), established under the Construction Industry Council Ordinance (Cap. 587)HK official
- Under the Construction Workers Registration Ordinance (Cap. 583)HK official
- The Occupational Safety and Health Ordinance (Cap. 509)HK official
- HKIAC arbitration under the Arbitration Ordinance (Cap. 609)HK official
- Minor Works Control System under the Buildings Ordinance (Cap. 123)HK official
- Contracts even for low-value projects, because the Buildings Ordinance (Cap. 123)HK official
- Registered Geotechnical Engineer (RGE) appointed under the Buildings Ordinance (Cap. 123)HK official
- Nuisance Control requirements under the Noise Control Ordinance (Cap. 400)HK official
- Air Pollution Control Ordinance (Cap. 311)HK official
Cite this page
Reference this free template in an article, syllabus, or research note:
Forms Legal. (2026). Construction Contract (Hong Kong) (Hong Kong) [Legal document template]. Forms Legal. https://forms-legal.com/hong-kong/business/construction/construction-contract-hong-kong
"Construction Contract (Hong Kong) (Hong Kong)." Forms Legal, 2026, https://forms-legal.com/hong-kong/business/construction/construction-contract-hong-kong.
@misc{formslegal-construction-contract-hong-kong,
author = {{Forms Legal}},
title = {Construction Contract (Hong Kong) (Hong Kong)},
year = {2026},
howpublished = {\url{https://forms-legal.com/hong-kong/business/construction/construction-contract-hong-kong}},
note = {Free legal document template. Based on Buildings Ordinance (Cap. 123)}
}Frequently Asked Questions
Hong Kong uses several standard form construction contracts depending on the project type, client, and procurement method. The Government of the HKSAR General Conditions of Contract (GCC) is used for all government construction projects. There are separate editions for building works, civil engineering works, electrical and mechanical works, and design and build projects. These are mandatory for government contracts and are administered by the Development Bureau. The HKIA Standard Form of Building Contract is published by the Hong Kong Institute of Architects and is the most widely used standard form for private sector building projects. It is available in several editions: the Standard Form (for contracts with quantities), the Agreement and Schedule of Conditions (for contracts without quantities), and the Sub-Contract form. The FIDIC (International Federation of Consulting Engineers) forms are used for large-scale infrastructure and international projects. The FIDIC Red Book (construction), Yellow Book (plant and design-build), and Silver Book (EPC/turnkey) are all used in Hong Kong, particularly for projects involving international contractors. The NEC (New Engineering Contract) forms are increasingly used in Hong Kong, particularly for MTR Corporation projects and some government works. NEC emphasises collaborative project management. For smaller projects and fit-out works, bespoke contracts are common.
Construction safety in Hong Kong is primarily governed by the Factories and Industrial Undertakings Ordinance (Cap. 59) and its subsidiary regulations, and the Occupational Safety and Health Ordinance (Cap. 509). Cap. 59 applies to all construction sites (which are classified as industrial undertakings). The proprietor of an industrial undertaking (typically the main contractor) has a duty to ensure, so far as is reasonably practicable, the health and safety of all persons employed at the undertaking. Specific duties include: providing safe plant and systems of work; ensuring safe access and egress; providing information, instruction, training, and supervision; and maintaining safe premises. The Construction Sites (Safety) Regulations under Cap. 59 impose detailed requirements for: excavations, scaffolding, and temporary works; lifting operations and cranes; fire safety; personal protective equipment; working at height; and confined space work. The Construction Sites (Safety Management) Regulations require contractors carrying out construction work valued at HK$100 million or more (or employing 200 or more workers at any time) to implement a safety management system. For works valued at HK$15-100 million, a safety plan is required. The Occupational Safety and Health Ordinance (Cap. 509) imposes general duties on employers to ensure the safety and health of employees at work. Penalties for safety breaches are significant. Under Cap.
Hong Kong does not have security of payment legislation equivalent to Australia’s Building and Construction Industry Security of Payment Act or the UK’s Housing Grants, Construction and Regeneration Act. Payment disputes in Hong Kong construction are resolved through contractual mechanisms and general dispute resolution processes. Contractual payment provisions are the primary mechanism. A well-drafted construction contract should include: interim payment certificates (typically monthly, based on the value of work completed); the architect’s or engineer’s role in certifying payments; the employer’s obligation to pay within a specified period after certification (typically 14-28 days); retention provisions (typically 10% of each interim payment, reduced to 5% at practical completion, released at the end of the defects liability period); and final account provisions. If the employer fails to pay in accordance with the contract, the contractor’s remedies include: suspension of work (if permitted by the contract); termination of the contract for non-payment; a claim for interest on late payments; and legal proceedings for recovery of the debt. Mediation is widely used for construction payment disputes in Hong Kong. The HKIA Standard Form and the Government GCC both include mediation provisions. The Hong Kong Mediation Council provides construction mediation services. Arbitration is the most common formal dispute resolution mechanism in Hong Kong construction contracts.
The defects liability period (DLP) in Hong Kong construction contracts is the period after practical completion during which the contractor is obliged to return to site and rectify defects in the works at the contractor’s own cost. The typical DLP in Hong Kong is 12 months from the date of practical completion. This is the standard period in the HKIA Standard Form, the Government GCC, and most bespoke construction contracts. For specialist works (e.g. waterproofing, mechanical systems), longer warranty periods of 2-5 years may be specified as supplementary warranties in addition to the standard DLP. During the DLP, the architect or engineer inspects the works and issues a schedule of defects to the contractor, typically near the end of the DLP. The contractor must rectify all defects within a reasonable time. If the contractor fails to do so, the employer may engage others to carry out the rectification and recover the costs from the contractor (or deduct them from retention). At the end of the DLP, once all defects have been rectified, the architect or engineer issues the Defects Rectification Certificate (or equivalent). This triggers the release of the final retention monies. The DLP should be distinguished from the limitation period for latent defects. Under Hong Kong’s Limitation Ordinance (Cap. 347), the limitation period for breach of contract is 6 years from the date of breach, and for negligence (tort) is 6 years from the date the damage is discoverable.
The Buildings Department (BD) administers the Buildings Ordinance (Cap. 123) and imposes regulatory requirements that directly affect Construction Contracts in Hong Kong. Authorised Person appointment: Section 4 of Cap. 123 requires the Employer (the owner of the building works) to appoint an Authorised Person (AP) — a registered architect, engineer, or surveyor — for all building works other than minor works. The AP is responsible for coordinating and supervising the building works, submitting building plans to the BD for approval under Section 16 of Cap. 123, and certifying completion of works. The AP's appointment should be formalised in a separate professional services agreement. Contractor registration: all contractors carrying out building works in Hong Kong must be registered in the appropriate category of the General Building Contractor Register or the Specialist Contractor Register maintained by the BD. Section 8A of Cap. 123 prohibits engagement of unregistered contractors. The Construction Contract should warrant that the contractor holds valid registration throughout the project duration. Minor Works Control System: the Minor Works Control System (MWCS) under the Building (Minor Works) Regulation divides minor works into three classes based on complexity and risk. Class I minor works require submission by a prescribed registered contractor with supervision by an AP or other registered professional. Class II and III works may be carried out by a registered minor works contractor without AP supervision.
This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer
Found an error? Let us knowRelated Documents
You may also find these documents useful:
Architect Agreement (Hong Kong)
An Architect Agreement for Hong Kong engaging a registered architect for design, planning, and construction supervision services. Governed by the Architects Registration Ordinance (Cap. 408), Buildings Ordinance (Cap. 123), and common law. Covers project scope, fees, IP ownership, professional indemnity, and compliance with Buildings Department requirements.
Design and Build Agreement (Hong Kong)
A Design and Build Agreement for Hong Kong where the contractor is responsible for both design and construction. Governed by the Buildings Ordinance (Cap. 123), common law, and industry practice. Covers employer’s requirements, contractor’s proposals, single-point responsibility, design liability, and fitness for purpose.
Performance Bond (Hong Kong)
A Performance Bond for Hong Kong construction projects issued by a bank or insurance company guaranteeing the contractor’s performance obligations. Governed by common law. Covers on-demand and conditional bonds, bond amount, expiry, and call procedures. Typically 10% of the contract sum.
Quantity Surveyor Agreement (Hong Kong)
A Quantity Surveyor Agreement for Hong Kong engaging a registered surveyor for cost management, bills of quantities, tender evaluation, interim valuations, and final account services. Governed by the Surveyors Registration Ordinance (Cap. 417) and common law. Covers scope, fees, professional indemnity, and dispute resolution.