Skip to main content

Construction Contract (Ireland)

Construction Contract (Ireland)

Building works contract under Construction Contracts Act 2013 and Building Control Acts

Construction Contract

CONSTRUCTION CONTRACT This Contract is entered into on [Start Date] between: [Employer Name], of [Employer Address] (the "Employer") and [Contractor Name], of [Contractor Address] (the "Contractor"). RCT / Tax Status: [Contractor C I S] This Contract is governed by the laws of the Republic of Ireland, including the Construction Contracts Act 2013 and the Building Control Acts 1990 and 2014.

1. Works and Site

1.1 The Contractor agrees to carry out and complete the following works (the "Works") at the site specified below: DESCRIPTION OF WORKS: [Project Description] SITE ADDRESS: [Site Address] PLANNING PERMISSION: [Planning Reference] 1.2 The Contractor shall carry out the Works in strict accordance with: the drawings and specifications agreed between the parties; any relevant planning permission and conditions; the Building Regulations (Technical Guidance Documents); and all applicable health and safety legislation including the Safety, Health and Welfare at Work (Construction) Regulations 2013 (SI 291 of 2013). 1.3 The Contractor shall appoint a competent Project Supervisor for the Construction Stage (PSCS) where required under the 2013 Regulations. 1.4 Assigned Certifier: [Assigned Certifier] — appointed under Building Control (Amendment) Regulations 2014 (SI 9 of 2014).

2. Programme and Completion

2.1 The Contractor shall commence the Works on [Start Date] and shall complete them by [Completion Date] ('Completion Date'), subject to any extension of time granted under this Contract. 2.2 The Contractor shall proceed regularly and diligently with the Works and shall maintain adequate labour, plant, and materials on site to meet the programme. 2.3 EXTENSION OF TIME: The Contractor may apply for an extension of the Completion Date where delay is caused by: variations instructed by the Employer; force majeure events; exceptionally adverse weather conditions; or delay caused by the Employer or their agents. Extensions must be applied for in writing with supporting evidence. 2.4 LIQUIDATED DAMAGES: If the Works are not practically complete by the Completion Date (as extended), the Employer shall be entitled to deduct liquidated damages at the rate of [Liquidated Damages] for each week of delay. This sum is agreed as a genuine pre-estimate of the Employer's loss.

3. Contract Sum and Payment

3.1 The Employer shall pay the Contractor the Contract Sum of [Contract Sum] plus VAT at 13.5% (the applicable rate for construction services under the Value-Added Tax Consolidation Act 2010), for the completion of the Works. 3.2 PAYMENT SCHEDULE: Payments shall be made on a [Payment Schedule] basis. The Contractor shall issue Payment Applications (or Interim Certificates, if an architect or certifier is appointed) in accordance with the Construction Contracts Act 2013. 3.3 PAYMENT NOTICE: The Employer shall issue a Payment Notice within 5 days of receiving each Payment Application, specifying the amount proposed to be paid. If the Employer wishes to pay less than the notified sum, a Pay Less Notice must be issued no later than 5 days before the final date for payment. 3.4 RETENTION: The Employer shall retain [Retention Percentage] of each interim payment as security. One half of the total retention shall be released on practical completion. The remaining half shall be released on the expiry of the Defects Liability Period, subject to satisfactory completion of defects. 3.5 In accordance with the Construction Contracts Act 2013, 'pay when paid' clauses are void under this Contract. Payment is not conditional on the Employer receiving payment from any third party.

4. Variations

4.1 The Employer may instruct variations to the scope of Works at any time before practical completion. All variations must be instructed in writing. 4.2 Variations shall be valued on the basis of: agreed rates in the contract; daywork rates where no contract rates apply; or fair and reasonable valuation by a quantity surveyor if rates cannot be agreed. 4.3 No variation shall vitiate this Contract. The Contractor shall not carry out any varied work until a written variation instruction has been issued by the Employer. 4.4 The Contractor shall notify the Employer in writing of any instruction it believes constitutes a variation before executing the work where practicable.

5. Defects and Insurance

5.1 DEFECTS LIABILITY PERIOD: The Defects Liability Period is [Defects Liability Period] from the date of practical completion. During this period, the Contractor shall remedy at its own cost any defects, shrinkages, or other faults in the Works that are due to materials or workmanship not being in accordance with the Contract. 5.2 INSURANCE: The Contractor shall maintain throughout the Contract: (a) Public Liability Insurance: not less than [Public Liability Amount] per occurrence; (b) Employer's Liability Insurance (where applicable): [Employers Liability] — as required under Irish law; (c) Contractors' All Risks (CAR) Insurance covering the Works to their full reinstatement value. 5.3 Evidence of all required insurances shall be provided to the Employer before commencement of Works on site. 5.4 DISPUTE RESOLUTION: Any payment dispute under this Contract may be referred by either party to adjudication under the Construction Contracts Act 2013. An adjudicator will be appointed by the Construction Contracts Adjudication Service (CCAS). Any other dispute shall be referred to mediation or, failing that, to arbitration under the Arbitration Act 2010 or litigation in the Irish courts.

Employer

________________

Signature

Contractor

________________

Signature

Maintained by Vladislav Sergienko, Founder·Template last modified: ·Report an error

What Is a Construction Contract (Ireland)?

A Construction Contract in Ireland sets the scope of works, price, programme, and payment terms for the building or installation project, and is governed by the Companies Act 2014.

When Do You Need a Construction Contract (Ireland)?

A Construction Contract is needed whenever parties in Ireland wish to formalize their arrangement regarding business operations, corporate governance, and commercial transactions. There are numerous situations in which this document becomes essential for protecting the interests of all involved parties. In a business context, you may need a Construction Contract when entering into new commercial relationships, when formalizing existing arrangements that have previously been informal, when expanding your business operations, or when restructuring existing agreements. Companies registered with CRO should confirm proper documentation is maintained for all significant business transactions. You should also consider using a Construction Contract when there has been a change in circumstances that affects an existing arrangement, when you need to comply with new regulatory requirements, when you wish to update outdated documentation, or when professional advisors recommend formalizing certain aspects of your affairs. In Ireland, maintaining current and accurate legal documentation is considered established standards and can help prevent costly disputes. It is generally advisable to prepare a Construction Contract before any issues arise, rather than trying to document terms after a dispute has already begun. Proactive documentation provides clarity and reduces the potential for misunderstandings. If you are unsure whether you need this document for your specific situation in Ireland, consulting with a qualified legal professional can provide guidance tailored to your circumstances. The timing of executing a Construction Contract is also important. In Ireland, certain documents must be executed before specific actions are taken or within prescribed time periods to be effective. Delaying the preparation of necessary legal documents can result in complications, lost rights, or additional costs. Therefore, it is recommended to prepare this document as early as possible once the need has been identified.

What to Include in Your Construction Contract (Ireland)

A well-drafted Construction Contract for use in Ireland should contain several essential elements to confirm it is legally effective and provides adequate protection for all parties. Party Identification: The document should clearly identify all parties involved, including their full legal names, addresses, and relevant identification numbers. For individuals in Ireland, this may include identity card or passport numbers. For companies, registration numbers and registered addresses should be specified. Clear identification prevents disputes about who is bound by the agreement. Recitals and Background: The document should include background information explaining the context and purpose of the arrangement. This helps establish the parties' intentions and can be important in interpreting the terms of the document if any ambiguity arises later. The recitals section provides valuable context for the operative provisions that follow. Operative Terms: The core terms and conditions should be set out clearly and thoroughly. This includes the rights and obligations of each party, any conditions or prerequisites, the duration of the arrangement, and any limitations or restrictions. All key terms should be defined precisely to avoid ambiguity and potential disputes. Payment and Financial Terms: Where applicable, the document should specify any payments, fees, deposits, or other financial considerations. The amounts, currency (EUR), payment schedules, and methods of payment should be clearly stated. Any provisions for late payment, interest charges, or adjustments should also be included. Term and Termination: The document should specify its duration, including the start date, end date or conditions for expiry, and any provisions for renewal or extension. The circumstances under which either party may terminate the arrangement early should be clearly defined, along with any notice requirements and the consequences of termination. Dispute Resolution: The document should include provisions for resolving any disputes that may arise, such as negotiation, mediation, arbitration, or litigation. In Ireland, parties may choose to specify the jurisdiction of Irish courts and the applicable law. Including a clear dispute resolution mechanism can save significant time and expense if disagreements occur. Governing Law and Jurisdiction: The document should specify that it is governed by the laws of Ireland and that disputes shall be subject to the jurisdiction of Irish courts. This is particularly important in cross-border transactions or where parties are based in different jurisdictions. Signatures and Execution: The document must be properly signed by all parties or their authorised representatives. In Ireland, certain documents may need to be witnessed, notarised, or executed as deeds to be legally effective. The date of execution should be clearly recorded, and each party should retain an original signed copy for their records. The forms-legal.com Construction Contract (Ireland) template covers the mandatory elements under Companies Act 2014.

Cite this page

Reference this free template in an article, syllabus, or research note:

APA

Forms Legal. (2026). Construction Contract (Ireland) (Ireland) [Legal document template]. Forms Legal. https://forms-legal.com/ireland/business/construction/construction-contract-ireland

MLA

"Construction Contract (Ireland) (Ireland)." Forms Legal, 2026, https://forms-legal.com/ireland/business/construction/construction-contract-ireland.

BibTeX
@misc{formslegal-construction-contract-ireland,
  author       = {{Forms Legal}},
  title        = {Construction Contract (Ireland) (Ireland)},
  year         = {2026},
  howpublished = {\url{https://forms-legal.com/ireland/business/construction/construction-contract-ireland}},
  note         = {Free legal document template. Based on Companies Act 2014}
}

Frequently Asked Questions

Based on Companies Act 2014 — Template last modified June 2026Verify the source →

This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer

Found an error? Let us know