Skip to main content

Building Contract (Ireland)

Building Contract (Ireland)

Construction Contract — Construction Contracts Act 2013

BUILDING CONTRACT

Construction Contracts Act 2013 (Ireland)

This Building Contract ("Contract") is entered into on [Contract Date] between:

[Client Name], of [Client Address], Phone: [Client Phone], Email: [Client Email] ("Client"); and

[Contractor Name], of [Contractor Address], CRO: [Contractor CRO], Phone: [Contractor Phone], Email: [Contractor Email] ("Contractor").

1. WORKS

1.1 The Contractor shall carry out and complete the following works ("Works"):

[Works Description]

1.2 Site Address: [Site Address]

1.3 Planning Permission Reference: [Planning Ref]

1.4 The Contractor shall carry out the Works in a good and workmanlike manner, using materials of good quality, and in accordance with the drawings, specifications, and any applicable planning conditions.

2. CONTRACT SUM AND PAYMENT

2.1 Contract Sum: [Contract Sum] (exclusive of VAT at 13.5%)

2.2 Payment Schedule: [Payment Schedule]

2.3 Retention Rate: [Retention Rate]

2.4 Payment Period: Payments are due within [Payment Period] of a valid payment claim being submitted. This Contract complies with the payment provisions of the Construction Contracts Act 2013.

2.5 The Contractor may issue a payment claim at each stage specified above. The Client shall issue a payment response within 21 days of receiving a payment claim. Failure to issue a payment response does not relieve the Client of the obligation to pay the sum claimed.

2.6 Overdue payments shall attract interest at the rate prescribed by the European Communities (Late Payment in Commercial Transactions) Regulations 2012 (S.I. 580/2012).

3. PROGRAMME

3.1 Commencement Date: [Commencement Date]

3.2 Target Practical Completion Date: [Completion Date]

3.3 Liquidated Damages for Delay: [Liquidated Damages]

3.4 Defects Liability Period: [Defects Liability Period]

3.5 The Contractor shall be entitled to an extension of time where delay is caused by the Client, variations, adverse weather beyond normal seasonal levels, or other matters outside the Contractor's control.

4. INSURANCE AND SAFETY

4.1 The Contractor shall maintain public liability insurance of not less than [Public Liability Insurance] per event throughout the duration of the contract.

4.2 Project Supervisor for the Construction Stage (PSCS): [PSCS Name]

4.3 The Contractor shall comply with all obligations under the Safety, Health and Welfare at Work Act 2005 and the Safety, Health and Welfare at Work (Construction) Regulations 2013 (S.I. 291/2013).

4.4 The Contractor shall ensure that all sub-contractors and workers on site hold current Safe Pass cards and, where applicable, CSCS qualifications as required under Irish construction safety legislation.

5. VARIATIONS

5.1 The Client may instruct variations to the Works. All variations must be confirmed in writing before commencement.

5.2 The Contractor shall submit a variation quotation for the Client's approval before proceeding with any variation that increases or decreases the Contract Sum.

6. ADJUDICATION

6.1 In accordance with the Construction Contracts Act 2013, either party has the right to refer a payment dispute to adjudication at any time. Adjudication is a fast-track dispute resolution process administered by the Construction Contracts Adjudication Panel.

6.2 Adjudication decisions are temporarily binding and may be reviewed by arbitration or litigation.

7. GOVERNING LAW

7.1 This Contract shall be governed by and construed in accordance with the laws of Ireland. Any disputes not resolved by adjudication shall be referred to arbitration under the Arbitration Act 2010 or to the courts of Ireland.

Client

________________

Signature

Date: ________________

Contractor

________________

Signature

Date: ________________

Maintained by Vladislav Sergienko, Founder·Template last modified: ·Report an error

What Is a Building Contract (Ireland)?

A Building Contract in Ireland sets the scope of works, price, programme, and payment terms for the building or installation project, under the framework of the Construction Contracts Act 2013.

The Construction Contracts Act 2013 (commenced on 25 July 2016) is the most significant piece of legislation specifically affecting construction contracts in Ireland. It applies to all written construction contracts for the carrying out of construction operations in the State, except contracts below EUR 10,000 in value or contracts with a private individual for works on their own home where the contract value does not exceed EUR 10,000. The Act introduces mandatory payment provisions, prohibits pay-when-paid clauses (section 4), and creates a statutory right to adjudicate payment disputes before the Construction Contracts Adjudication Service.

The Sale of Goods and Supply of Services Act 1980 implies a number of terms into contracts for the supply of services in Ireland. Under section 39 of the 1980 Act, where a supplier supplies a service in the course of a business, there is an implied warranty that the supplier has the necessary skill to render the service, that the service will be rendered with due skill, care and diligence, and that any materials supplied in connection with the service will be sound and reasonably fit for the purpose for which they are required. These implied warranties cannot be excluded in consumer contracts.

The Safety, Health and Welfare at Work (Construction) Regulations 2013 impose detailed duties on clients, project supervisors, designers, and contractors to manage health and safety throughout the design and construction process. The Regulations require the appointment of a Project Supervisor Design Process (PSDP) and a Project Supervisor Construction Stage (PSCS) for notifiable construction projects (those lasting more than 30 working days with more than 20 simultaneous workers, or exceeding 500 person-days of work). The Health and Safety Authority (HSA) enforces these Regulations.

The Building Control Acts 1990 and 2007 establish the framework of building control in Ireland, requiring that all construction works comply with the Building Regulations. The Building Control (Amendment) Regulations 2014 introduced mandatory certification by an Assigned Certifier for residential buildings, requiring a Certificate of Compliance on Completion before occupation. The building contract should allocate responsibility for compliance with these requirements clearly between the employer and the contractor.

In practice, most significant construction projects in Ireland use one of the standard forms of building contract — most the RIAI Standard Form of Building Contract (published by the Royal Institute of the Architects of Ireland), which has been developed over many decades specifically for the Irish market and is widely accepted by the construction industry, solicitors, and the courts. The RIAI form provides for an independent architect or engineer to administer the contract, certify payments, issue instructions, and grant extensions of time. For public sector projects, the Government Contracts Committee for Construction (GCCC) publishes standard forms of public works contract that must be used for all capital works projects funded by the Exchequer, as required under the Capital Works Management Framework (CWMF) administered by the Office of Government Procurement. These public works contracts differ significantly from the RIAI form and include fixed-price arrangements, detailed risk allocation provisions, and specific payment procedures designed for public sector procurement. Employers and contractors engaged in publicly funded construction projects should confirm they use the appropriate GCCC form and comply with the Procurement Guidelines for Capital Works Projects issued by the Department of Public Expenditure, NDP Delivery and Reform.

The Construction Contracts Act 2013 applies to all written construction contracts for the carrying out of construction operations in the State valued above EUR 10,000, with the exception of contracts with a residential occupier for works on their principal private residence. The Act prohibits pay-when-paid clauses (section 4), requires every construction contract to contain adequate mechanisms for determining payment due dates and amounts, and grants either party the right to refer payment disputes to a registered adjudicator through the Construction Contracts Adjudication Service (CCAS) at any time during the project. For notifiable construction projects (lasting more than 30 working days with more than 20 simultaneous workers, or exceeding 500 person-days), the Safety, Health and Welfare at Work (Construction) Regulations 2013 (S.I. No. 291 of 2013) require the client to appoint a Project Supervisor Design Process (PSDP) and a Project Supervisor Construction Stage (PSCS), and to prepare a Safety File for handover at completion. These roles and responsibilities must be clearly allocated in the building contract.

When Do You Need a Building Contract (Ireland)?

An Irish Building Contract is needed whenever a property owner, developer, or business commissions a building contractor to carry out construction works in Ireland. Without a written contract, the parties have no clear record of the agreed scope of works, the contract price, the programme, or the consequences of delay or defects — all of which are fertile ground for disputes.

You need a Building Contract when you are: commissioning the construction of a new home, extension, or commercial building; engaging a contractor to carry out significant renovation, refurbishment, or fit-out works; undertaking a commercial development or mixed-use project where the employer needs certainty about cost, programme, and contractor obligations; or entering into any arrangement where a builder will be on site for an extended period with responsibility for the structural integrity, safety, and habitability of the finished works.

From the employer's perspective, a written building contract is essential for several reasons. It defines the scope of works precisely — preventing later disputes about what is included in the contract price and what constitutes a variation. It establishes the contract sum and the procedures for agreeing and valuing variations, which are inevitable on any significant construction project. It sets the completion date and the mechanism for extensions of time (for example, where delays are caused by the employer, inclement weather, or force majeure), and provides for liquidated and ascertained damages (LADs) in the event of contractor delay. LADs must be a genuine pre-estimate of loss and not a penalty — a distinction that Irish courts have considered in cases such as Dunlop Pneumatic Tyre Co v New Garage and Motor Co [1915] AC 79 (applied in Ireland) and in the Supreme Court's landmark analysis of penalty clauses in Sheehan v Breccia [2018] IESC 43.

From the contractor's perspective, the building contract protects the right to receive timely payment under the Construction Contracts Act 2013 (commenced 25 July 2016), to be paid for instructed variations, to claim extensions of time for employer-caused delays, and to have a fair mechanism for resolving disputes — including the statutory right to refer any payment dispute to a registered adjudicator through the Construction Contracts Adjudication Service (CCAS). The number of adjudicator appointments under the 2013 Act has grown significantly year-on-year since commencement, reflecting the increasing importance of statutory adjudication as the primary fast-track payment remedy in Irish construction.

For residential construction projects in Ireland, the consumer protection provisions of the Sale of Goods and Supply of Services Act 1980 and the Consumer Protection Act 2007 apply, giving homeowners additional rights to quality workmanship and materials. The building contract should not seek to exclude or limit these statutory rights. The Building Control (Amendment) Regulations 2014 (S.I. No. 9 of 2014) require the appointment of an Assigned Certifier and a Certificate of Compliance on Completion before any new residential building can be occupied — responsibility for arranging this certification should be clearly allocated in the building contract.

For commercial projects funded by banks or institutional investors, lenders will typically require a copy of the building contract as a condition of drawdown. The contract must include assignment provisions allowing the lender to step in in the event of the employer's insolvency. Public sector construction contracts above the relevant procurement thresholds must use the Government Contracts Committee for Construction (GCCC) standard forms of public works contract under the Capital Works Management Framework (CWMF) administered by the Office of Government Procurement.

Under the Companies Act 2014, the Companies Registration Office (CRO) maintains the register of Irish companies. Section 343 of the Companies Act 2014 sets annual confirmation obligations. The Competition and Consumer Protection Commission (CCPC) enforces the Consumer Rights Act 2022. The Central Bank of Ireland regulates financial services under the Central Bank Act 1971. The High Court of Ireland has jurisdiction under Section 212 of the Companies Act 2014.

What to Include in Your Building Contract (Ireland)

A thorough Irish Building Contract should address the following key provisions to be effective and enforceable.

The parties clause identifies the employer and the contractor by full legal name, address, and (where applicable) company registration number. The contract should also name the contract administrator — typically the project architect, engineer, or quantity surveyor — who will administer the contract on behalf of the employer. For projects requiring the appointment of a Project Supervisor Design Process (PSDP) and Project Supervisor Construction Stage (PSCS) under the Safety, Health and Welfare at Work (Construction) Regulations 2013, the names of the appointed supervisors should be recorded.

The works description clause sets out the scope of the construction works in detail, by reference to the drawings, specifications, and bills of quantities prepared by the design team. The more precise the description of the works, the less scope for dispute about what is included in the contract price. The clause should also address the status of the design — whether the employer provides a complete design (traditional procurement) or whether the contractor is also responsible for design (design-and-build).

The contract sum clause specifies the agreed price for the works — either a fixed lump sum, a remeasured contract sum, or a cost-plus arrangement. The contract should set out the procedure for agreeing and valuing variations (additional or reduced works instructed by the contract administrator) and any prime cost sums or provisional sums included in the contract.

The commencement and completion dates clause specifies the date on which the contractor is required to commence works and the agreed date for practical completion. The contract must include clear provisions for extensions of time in specified circumstances (including employer delays, neutral events such as inclement weather, and force majeure), and the process by which extensions must be claimed and granted. Liquidated and ascertained damages (LADs) for contractor delay must represent a genuine pre-estimate of loss rather than a penalty — a distinction applied by the Irish courts.

The payment provisions must comply with the Construction Contracts Act 2013. The contract must specify the due dates for interim payments, the procedure for issuing payment claim schedules and pay less notices, the final date for payment, and the contractor's right to suspend works for non-payment. The contract should also specify the interest rate applicable to late payments — by reference to the European Communities (Late Payment in Commercial Transactions) Regulations 2012 for commercial contracts. Pay-when-paid clauses are void under Section 4 of the 2013 Act.

The defects liability clause sets out the contractor's obligation to remedy any defects, shrinkages, or other faults in the works that appear within the defects liability period (typically 12 months after practical completion). The employer is entitled to withhold retention moneys until the defects liability certificate is issued.

The insurance clause must require the contractor to maintain public liability, employers' liability, and contractors' all risks insurance in amounts appropriate to the project, and must specify which party is responsible for insuring the works against damage during construction. Evidence of insurance should be provided before work commences on site.

The dispute resolution clause should provide for adjudication under the Construction Contracts Act 2013 as the primary mechanism for payment disputes, followed by arbitration or litigation for other disputes. The governing law and jurisdiction clause should confirm that the contract is governed by the laws of Ireland. The forms-legal.com Building Contract (Ireland) template covers the mandatory elements under Companies Act 2014.

Cite this page

Reference this free template in an article, syllabus, or research note:

APA

Forms Legal. (2026). Building Contract (Ireland) (Ireland) [Legal document template]. Forms Legal. https://forms-legal.com/ireland/business/construction/building-contract-ireland

MLA

"Building Contract (Ireland) (Ireland)." Forms Legal, 2026, https://forms-legal.com/ireland/business/construction/building-contract-ireland.

BibTeX
@misc{formslegal-building-contract-ireland,
  author       = {{Forms Legal}},
  title        = {Building Contract (Ireland) (Ireland)},
  year         = {2026},
  howpublished = {\url{https://forms-legal.com/ireland/business/construction/building-contract-ireland}},
  note         = {Free legal document template. Based on Companies Act 2014}
}

Also available for these jurisdictions:

Frequently Asked Questions

Based on Companies Act 2014 — Template last modified June 2026Verify the source →

This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer

Found an error? Let us know