Skip to main content

Demolition Contract (Ireland)

Demolition Contract (Ireland)

This Demolition Contract (the "Contract") is entered into on [Contract Date] by and between:

[Client Name], registered with the Companies Registration Office under number [Client CRO], whose registered address is [Client Address] (the "Client"); and

[Contractor Name], registered with the Companies Registration Office under number [Contractor CRO], VAT No. [Contractor VAT], whose registered address is [Contractor Address] (the "Contractor").

1. WORKS

1.1 The Contractor shall carry out and complete the following demolition works at [Site Address] (the "Works"): [Works Description].

1.2 The Works shall be carried out in a good and workmanlike manner, in accordance with this Contract, all applicable planning permissions and bye-law approvals, the Building Control Acts 1990–2020, the Safety, Health and Welfare at Work (Construction) Regulations 2013 (S.I. No. 291 of 2013), and all other applicable Irish legislation and regulations.

2. PROGRAMME

2.1 The Contractor shall commence the Works on [Commencement Date] and shall achieve practical completion by [Completion Date] (the "Completion Date").

2.2 If the Contractor fails to complete the Works by the Completion Date, the Contractor shall pay to the Client liquidated and ascertained damages at the rate of [Liquidated Damages Rate] for each week or part week of delay beyond the Completion Date. The Parties agree this sum represents a genuine pre-estimate of the Client's loss and is not a penalty.

2.3 The Completion Date may be extended where delay is caused by events beyond the Contractor's reasonable control, including severe weather, archaeological discovery, or variation instructions from the Client, subject to the Contractor giving written notice of delay within 5 Business Days of becoming aware of the delaying event.

3. CONTRACT SUM AND PAYMENT

3.1 The Client shall pay the Contractor the contract sum of [Contract Sum] (exclusive of VAT at 13.5%) for the Works, subject to the payment schedule set out in this Clause.

3.2 Payment shall be made in instalments as follows: (a) 30% upon commencement of Works on site; (b) 40% upon completion of 50% of the Works as certified by the Client's Representative; and (c) 30% balance upon practical completion and sign-off by the Client's Representative.

3.3 All invoices shall be paid within 30 days of receipt. Overdue amounts shall accrue interest at the rate prescribed under the European Communities (Late Payment in Commercial Transactions) Regulations 2012 (S.I. No. 580 of 2012).

3.4 The Client shall be entitled to retain 5% of each instalment payment ("Retention") until the expiry of a 6-month defects liability period following practical completion.

4. HEALTH AND SAFETY

4.1 The Contractor shall comply with the Safety, Health and Welfare at Work Act 2005 and all related Regulations, including the Safety, Health and Welfare at Work (Construction) Regulations 2013 (S.I. No. 291 of 2013), in respect of all Works carried out under this Contract.

4.2 The Contractor shall prepare and maintain a site-specific Safety Plan covering all demolition activities, and shall submit it to the Client for approval before commencement of Works on site.

4.4 The Contractor shall not commence demolition without all required notifications to the Health and Safety Authority (HSA) under the Construction Regulations, where applicable.

5. WASTE DISPOSAL AND ENVIRONMENTAL OBLIGATIONS

5.1 The Contractor shall remove all demolition debris, rubble, and waste from the site and dispose of it in accordance with the Waste Management Acts 1996–2011 and applicable EPA regulations. The Contractor shall use only licensed waste collectors and approved waste facilities.

5.2 The Contractor shall maximise recycling and reuse of demolition materials where practicable and shall provide the Client with waste transfer documentation upon completion of the Works.

5.3 The Client shall be responsible for obtaining any required planning permissions or local authority consents for demolition works prior to the commencement date, including any demolition consent required under the Planning and Development Act 2000 (as amended).

6. INSURANCE

6.1 The Contractor shall maintain throughout the duration of the Works: (a) public liability insurance of not less than [Public Liability Amount] per occurrence; (b) employer's liability insurance as required by the Social Welfare (Consolidation) Act 2005; and (c) contractor's all-risks insurance covering the Works.

6.2 The Contractor shall provide the Client with certificates of insurance upon request and shall ensure all policies remain in force until practical completion.

7. GENERAL PROVISIONS

7.1 This Contract shall be governed by and construed in accordance with the laws of Ireland. Any dispute arising under this Contract shall be referred to arbitration under the Arbitration Act 2010 or to the courts of Ireland.

7.2 This Contract constitutes the entire agreement between the Parties in relation to the Works and supersedes all prior negotiations and representations.

7.3 Any variation to this Contract must be in writing and signed by both Parties.

IN WITNESS WHEREOF, the Parties have executed this Demolition Contract as of the date first written above.

Client

________________

Signature

Date: ________________

Contractor

________________

Signature

Date: ________________

Maintained by Vladislav Sergienko, Founder·Template last modified: ·Report an error

What Is a Demolition Contract (Ireland)?

A Demolition Contract in Ireland sets the scope of works, price, programme, and payment terms for the building or installation project, under the framework of the Planning and Development Act 2000.

The Safety, Health and Welfare at Work (Construction) Regulations 2013 are the primary safety legislation governing demolition works in Ireland. Demolition is classified as high-risk construction work under Schedule 2 of the Regulations, which triggers additional requirements including the appointment of a Project Supervisor Design Process (PSDP) and a Project Supervisor Construction Stage (PSCS), the preparation of a Preliminary Safety and Health Plan and a Construction Stage Safety and Health Plan, and the maintenance of a Safety and Health File. The Regulations also require a specific method statement for demolition works, setting out the sequence and method of demolition to confirm the safety of workers and the public.

The Health and Safety Authority (HSA) has published a Code of Practice for Safety in Demolition Works (2012) that provides detailed guidance on the planning, sequencing, and execution of demolition projects in a safe manner. While compliance with the Code of Practice is not legally mandatory, it represents accepted good practice and would be highly relevant in any personal injuries or enforcement action following a demolition incident. The HSA also publishes guidance on demolition-specific hazards including structural instability, buried services, asbestos, and lead paint, and the demolition contractor is expected to be familiar with all relevant HSA publications.

The Planning and Development Act 2000 regulates the requirement for planning permission for demolition works, with the position varying depending on whether the structure is a protected structure, is located in an Architectural Conservation Area, or is otherwise subject to specific planning conditions. The Construction Contracts Act 2013 applies to demolition contracts (as demolition is explicitly included in the definition of construction operations) and confers mandatory payment rights and adjudication rights on both parties.

Environmental compliance is central to any demolition project. The Waste Management Acts require that all demolition waste — including hazardous materials such as asbestos, lead paint, and contaminated soil — be managed, segregated, and disposed of in accordance with the waste hierarchy. The Environmental Protection Agency (EPA) and local authorities actively enforce waste management requirements on demolition sites.

The Safety, Health and Welfare at Work Act 2005 imposes general duties on employers and employees to confirm safety at work. Under section 8 of the 2005 Act, every employer must provide and maintain a safe place of work, a safe system of work, and safe equipment. Demolition contractors are subject to these duties as employers of their workers on site. The employer who commissions the demolition is the 'Client' under the Construction Regulations 2013 and has statutory duties to appoint competent project supervisors, confirm the Preliminary Safety and Health Plan is prepared before design begins, and retain the Safety and Health File after completion.

Additionally, the Building Control Acts 1990 to 2014 and the Building Control Regulations may apply where the demolition is connected to proposed new construction. The Building Control (Amendment) Regulations 2014 (S.I. No. 9 of 2014) introduced a more rigorous system of oversight for construction and demolition works, including requirements for design certification, inspection plans, and completion documentation. The employer should also consider utility disconnection requirements — gas, electricity, water, and telecommunications services must be disconnected or made safe by the relevant utility operators (Gas Networks Ireland, ESB Networks, Irish Water, and communications providers) before demolition commences. The demolition contract should clearly allocate responsibility for coordinating utility disconnections as a pre-commencement condition.

When Do You Need a Demolition Contract (Ireland)?

An Irish Demolition Contract is needed whenever a property owner, developer, or public authority engages a demolition contractor to pull down and remove an existing structure as a precursor to new construction, site clearance, or redevelopment. A written demolition contract is essential to define the scope of works, allocate risk, confirm compliance with extensive safety and environmental legislation, and protect both parties in the event of a dispute.

You need a Demolition Contract when you are: commissioning the full demolition of an existing residential, commercial, or industrial building; engaging a contractor to carry out partial demolition or structural alteration (removing an existing structure to make way for an extension or a new element); engaging a demolition contractor to clear a development site of existing structures, hardstanding, services, and vegetation in preparation for new construction; or in any situation where a contractor is being paid to bring down and remove an existing structure as a standalone operation.

From the employer's perspective, the demolition contract must clearly define the scope — precisely identifying which structures are to be demolished and which (if any) are to be retained, the extent of below-ground demolition and foundation removal, and the required end condition of the site. The contract must allocate responsibility for obtaining planning permission, building control approvals, and HSA notifications — all of which are required before demolition may lawfully commence.

From the demolition contractor's perspective, the contract must document the agreed price (or basis of pricing), the programme, the employer's obligations to provide site access and utility disconnection certificates, and the contractor's right to payment for additional works where the site conditions encountered differ from those assumed in the tender (for example, previously unknown asbestos, contamination, or undisclosed underground structures).

The demolition contract must address the very significant health, safety, and environmental risks inherent in demolition work. It must require the contractor to maintain all required insurances, prepare a method statement and Construction Stage Safety and Health Plan, appoint a competent PSCS, comply with the HSA Code of Practice for Safety in Demolition Works, and carry out all required asbestos surveys and licensed removal works before structural demolition commences.

For projects involving protected structures, structures in Architectural Conservation Areas, or structures with sensitive neighbours (such as hospitals, schools, or densely developed urban sites), the demolition contract must include additional provisions to protect the employer against planning enforcement, nuisance claims from neighbours, and damage to adjacent structures.

Under the Companies Act 2014, the Companies Registration Office (CRO) maintains the register of Irish companies. Section 343 of the Companies Act 2014 sets annual confirmation obligations. The Competition and Consumer Protection Commission (CCPC) enforces the Consumer Rights Act 2022. The Central Bank of Ireland regulates financial services under the Central Bank Act 1971. The High Court of Ireland has jurisdiction under Section 212 of the Companies Act 2014.

What to Include in Your Demolition Contract (Ireland)

A thorough Irish Demolition Contract must address the following key provisions.

The parties and project description clause identifies the employer and the demolition contractor, and describes the project — including the location (with Eircode), a description of the structures to be demolished, and the required end condition of the site after demolition and removal. The project description should reference relevant planning permissions or building regulations approvals and confirm that the employer holds or will obtain all necessary consents before work commences.

The scope of works clause must precisely define what is to be demolished, cleared, and removed from the site, including above-ground structures, basements, foundations, services (drainage, electricity, gas, water), hardstanding, and any materials specified for retention or salvage. The clause should distinguish clearly between inclusive scope items, provisional items, and excluded items, to avoid disputes about what is included in the agreed price.

The pre-demolition obligations clause requires the contractor to carry out an asbestos survey in accordance with the Safety, Health and Welfare at Work (Exposure to Asbestos) Regulations 2006 (S.I. No. 386 of 2006), prepare a demolition method statement and structural engineer's assessment where required, obtain all required planning approvals and HSA notifications under the Construction Regulations 2013, and submit and have approved a Construction Stage Safety and Health Plan before commencing work. The contractor must also carry out pre-condition surveys of all neighbouring structures and record their condition photographically before demolition commences, to establish a baseline in the event of any damage claims.

The price and payment clause specifies the contract price (lump sum or measurement-based) and must comply with the mandatory payment provisions of the Construction Contracts Act 2013. This includes specifying the payment due date (no more than 30 days from the payment claim date), the requirement for Pay Less Notices, and the contractor's right to suspend works for non-payment after the relevant notice period. The payment clause should also address valuation of any daywork or additional instructed works, and the process for agreeing the final account.

The waste management clause requires the contractor to prepare a Waste Management Plan before commencement, segregate waste on site into appropriate categories, engage only registered waste collectors under the Waste Management Act 1996, complete consignment notes for all hazardous waste movements in accordance with the Waste Management (Hazardous Waste) Regulations 1998, pay all applicable landfill levies, and provide the employer with copies of all waste disposal documentation, transfer notes, and certificates on completion.

The asbestos and hazardous materials clause must require the contractor to engage a licensed asbestos removal contractor for all asbestos removal works, notify the HSA at least 14 days before commencing asbestos removal, conduct air monitoring in accordance with the 2006 Regulations, and provide the employer with clearance certificates confirming all asbestos-containing materials have been lawfully removed and disposed of before structural demolition commences.

The insurance and indemnity clause requires the contractor to maintain public liability insurance (minimum EUR 6.5 million per occurrence), employers' liability insurance, and contractors' all risks insurance in specified amounts, and to provide the employer with copies of valid insurance certificates before commencement. The clause should require the contractor to indemnify the employer against all claims by third parties arising from the contractor's operations.

The programme and completion clause sets out the commencement date, the completion date, and the procedure for extensions of time. Liquidated and ascertained damages (LADs) for delay should be included where the employer has a genuine pre-estimate of the loss from delayed site possession, to avoid the difficulties associated with proving actual loss in delay claims.

The adjudication and dispute resolution clause must comply with the Construction Contracts Act 2013, which confers on any party the right to refer a payment dispute to adjudication at any time. The clause should identify the nominating body for the appointment of an adjudicator — the Department of Enterprise, Trade and Employment (DETE) operates the Construction Contracts Adjudication Service, which maintains a panel of registered adjudicators and appoints adjudicators on application. Under the Construction Contracts Act 2013, the adjudicator must reach a decision within 28 days of referral (extendable to 42 days with the referring party’s consent, or longer by agreement of both parties), and the decision is binding on an interim basis and enforceable as a court judgment pending final resolution by arbitration or litigation. The 2013 Act applies to construction contracts with a value exceeding EUR 10,000 (excluding VAT). Late payments on construction contracts also attract statutory interest under the European Communities (Late Payment in Commercial Transactions) Regulations 2012 (S.I. No. 580 of 2012) at the ECB reference rate plus 8 percentage points — from 1 January 2026 the applicable rate is 10.15% per annum — plus tiered debt recovery compensation of EUR 40 (debts below EUR 1,000), EUR 70 (EUR 1,000 to EUR 10,000), or EUR 100 (above EUR 10,000).

The governing law clause confirms the contract is governed by the laws of Ireland and that disputes are subject to Irish adjudication, mediation under the Mediation Act 2017, and ultimately the jurisdiction of the Irish courts. The forms-legal.com Demolition Contract (Ireland) template covers the mandatory elements under Companies Act 2014.

Cite this page

Reference this free template in an article, syllabus, or research note:

APA

Forms Legal. (2026). Demolition Contract (Ireland) (Ireland) [Legal document template]. Forms Legal. https://forms-legal.com/ireland/business/construction/demolition-contract-ireland

MLA

"Demolition Contract (Ireland) (Ireland)." Forms Legal, 2026, https://forms-legal.com/ireland/business/construction/demolition-contract-ireland.

BibTeX
@misc{formslegal-demolition-contract-ireland,
  author       = {{Forms Legal}},
  title        = {Demolition Contract (Ireland) (Ireland)},
  year         = {2026},
  howpublished = {\url{https://forms-legal.com/ireland/business/construction/demolition-contract-ireland}},
  note         = {Free legal document template. Based on Companies Act 2014}
}

Also available for these jurisdictions:

Frequently Asked Questions

Based on Companies Act 2014 — Template last modified June 2026Verify the source →

This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer

Found an error? Let us know