Construction Contract (Ghana)
Construction Contract
This Construction Contract (this "Contract") is entered into on [Contract Date] between:
OWNER: [Owner Name], registration number [Owner Registration Number], of [Owner Address] (the "Owner"); and
CONTRACTOR: [Contractor Name], registration number [Contractor Registration Number], of [Contractor Address] (the "Contractor").
The Owner and the Contractor are collectively referred to as the "Parties".
1. Works and Site
The Contractor shall design (if applicable), construct, complete, and maintain the following works (the "Works"): [Project Description].
The site of the Works is at [Site Address] (the "Site"). Building Permit No. [Building Permit Number] has been obtained from the relevant District Assembly in accordance with the National Building Regulations 1996 (LI 1630).
The Works shall comply with the approved drawings, specifications, and Bills of Quantities (BOQ) appended to this Contract, and with all applicable Ghanaian building standards.
2. Contract Price and Payment
The Owner shall pay the Contractor a total Contract Price of GHS [Contract Price], inclusive of VAT at 15%, NHIL at 2.5%, and GETFund Levy at 2.5% under the Value Added Tax Act 2013 (Act 870).
A mobilisation advance of [Mobilisation Advance] of the Contract Price shall be paid to the Contractor within 14 days of the signing of this Contract, against an advance payment guarantee.
Interim payments shall be made within [Payment Terms] of the supervising professional's payment certificate. A retention of [Retention Rate] shall be deducted from each interim payment.
The Owner shall withhold VAT, NHIL, and GETFund Levy on all payments and remit to the Ghana Revenue Authority (GRA) in compliance with the Value Added Tax Act 2013 (Act 870).
3. Programme and Completion
The Contractor shall commence the Works on [Commencement Date] and shall achieve practical completion by [Completion Date].
The defects liability period shall be [Defects Liability Period] from the date of practical completion. During this period the Contractor shall remedy, at its own cost, any defect attributable to the Contractor's workmanship or materials.
Half the retention sum shall be released on practical completion, and the balance at the end of the defects liability period.
4. Variations
The Owner may instruct variations to the scope of Works by written variation order. No additional payment is due for work carried out without a written variation order.
5. Termination
Either Party may terminate this Contract upon 14 days' written notice for material breach that is not remedied within the notice period.
Upon termination, the Parties shall account for all works executed to date and materials on Site, with payment due for the fair value of work done.
6. Governing Law and Disputes
This Contract is governed by the laws of the Republic of Ghana, including the Contracts Act 1960 (Act 25) and the Public Procurement Act 2003 (Act 663) where applicable.
Any dispute arising out of or in connection with this Contract shall be referred to [Dispute Resolution] under the Alternative Dispute Resolution Act 2010 (Act 798).
Signatures
IN WITNESS WHEREOF the Parties have executed this Construction Contract on the date first written above.
Owner
________________
Signature
Contractor
________________
Signature
What Is a Construction Contract (Ghana)?
A Construction Contract in Ghana is a legally binding written agreement between a property owner or employer and a contractor that governs the design, construction, renovation, or alteration of a building or civil engineering structure in accordance with the Contracts Act 1960 (Act 25) and applicable construction law in Ghana. The Construction Contract (Ghana) sets out the scope of works, contract price in Ghana Cedis (GHS), payment schedule, programme of works, variations procedure, defects liability obligations, and the circumstances under which either party may terminate the agreement.
The legal framework governing construction contracts in Ghana draws primarily on the Contracts Act 1960 (Act 25), which codifies the common law rules of offer, acceptance, consideration, and contractual capacity applicable to all binding agreements in Ghana. Construction contracts for public sector projects are additionally regulated by the Public Procurement Act 2003 (Act 663), which requires that public bodies follow the procurement processes administered by the Public Procurement Authority (PPA) before entering into any construction agreement above the prescribed threshold. The PPA publishes standard form contracts that public entities in Ghana are obligated to use for procurement of works.
In the private sector, the Ghana Institution of Engineering (GhIE) and the Ghana Institute of Architects (GIA) both publish standard form contracts widely used for building and civil engineering works in Ghana. Many sophisticated construction projects in Ghana — particularly those financed by international development finance institutions such as the World Bank, the African Development Bank (AfDB), or the European Investment Bank (EIB) — use FIDIC (Federation Internationale des Ingenieurs-Conseils) standard form contracts, which are internationally recognised and enforceable in Ghanaian courts.
The National Building Regulations 1996 (LI 1630) require that construction works in Ghana be carried out in accordance with approved building plans. Before commencing construction, the owner must obtain a Building Permit from the relevant District Assembly or Metropolitan Authority — such as the Accra Metropolitan Assembly (AMA) or the Kumasi Metropolitan Assembly (KMA). The Environmental Protection Agency (EPA) may also require an Environmental Impact Assessment (EIA) for large construction projects under the Environmental Assessment Regulations 1999 (LI 1652).
A Construction Contract in Ghana must be distinguished from a Consulting Agreement, which governs the services of an architect, engineer, or quantity surveyor providing professional advice rather than executing physical works, and from a Supply Agreement, which covers the provision of building materials without construction obligations. The Construction Contract is also distinct from a Sub-Contract Agreement, under which a main contractor delegates specific portions of the works to a specialist sub-contractor.
The Ghana Revenue Authority (GRA) treats construction contracts as taxable supplies for Value Added Tax (VAT) purposes under the Value Added Tax Act 2013 (Act 870), with VAT charged at the standard rate of 15% plus the National Health Insurance Levy (NHIL) of 2.5% and the Ghana Education Trust Fund Levy (GETFund) of 2.5%. Contractors registered with the Ghana Revenue Authority must include these levies in their contract prices and remit them to the GRA. Contractors are also required to register with the Ghana Revenue Authority and obtain a Tax Identification Number (TIN) before execution of any public sector construction contract.
When Do You Need a Construction Contract (Ghana)?
A Construction Contract in Ghana is required whenever any party engages a contractor to carry out building, civil engineering, or infrastructure works, and is particularly important in the following circumstances.
A Construction Contract is required when a private individual, company, or government body in Ghana commissions the construction of a new residential or commercial building in any of Ghana's 16 administrative regions. Without a written contract, disputes over the scope of works, payment, and completion date are left to be determined by oral evidence, which Ghanaian courts treat as inherently unreliable.
A Construction Contract is needed when the project value exceeds GHS 20,000, as this threshold triggers significant documentation requirements under the Public Procurement Act 2003 (Act 663) for public sector projects, and any dispute of this magnitude will be heard by the High Court (Commercial Division) in Accra or the relevant regional High Court.
A Construction Contract is required for any construction project requiring a Building Permit from the Accra Metropolitan Assembly (AMA), the Kumasi Metropolitan Assembly (KMA), or any District Assembly in Ghana, because the Building Permit application process typically requires submission of contractual documentation.
A Construction Contract is needed when a developer in Ghana sells off-plan residential units and must demonstrate to purchasers that the construction programme is governed by binding contractual commitments with a reputable contractor, particularly where the development is marketed to members of the diaspora or to foreign investors.
A Construction Contract is required when the project is financed by a bank licensed by the Bank of Ghana (BoG), as lenders providing construction finance in Ghana require a copy of the executed construction contract before advancing drawdowns against the facility.
A Construction Contract is needed when engaging a contractor registered with the Ghana Contractors Association (GCA) for works covered by the National Building Regulations 1996 (LI 1630), to confirm that the contractual obligations align with the regulatory standards enforced by the Architectural and Engineering Services Limited (AESL) on behalf of government.
Parties in Ghana should execute a Construction Contract before any site mobilisation begins. Retrospective contracts are difficult to enforce in the High Court (Commercial Division), Accra, particularly where works have already been partially completed and the scope is in dispute.
What to Include in Your Construction Contract (Ghana)
A valid Construction Contract in Ghana under the Contracts Act 1960 (Act 25) must contain the following essential elements.
Parties and Background: Full legal names, addresses, and registration numbers of the owner and the contractor. If the contractor is a company incorporated under the Companies Act 2019 (Act 992), the contract should state the company's registration number issued by the Office of the Registrar of Companies (ORC). If the contractor is a sole trader or partnership, the contract should reference the relevant business registration.
Description of Works: A precise description of the construction works to be carried out, by reference to drawings, specifications, and a Bills of Quantities (BOQ) prepared by a certified quantity surveyor. The drawings and specifications should be appended to the contract or incorporated by reference. The description must identify the site address, the building type, and the approved Building Permit number issued by the relevant District Assembly.
Contract Price and Payment Schedule: The total contract price in Ghana Cedis (GHS), inclusive of all applicable taxes and levies — VAT at 15%, NHIL at 2.5%, and GETFund Levy at 2.5% — under the Value Added Tax Act 2013 (Act 870). The payment schedule should set out milestone payments tied to measurable stages of completion: mobilisation advance (typically 10-15% of contract price), upon completion of foundations, upon completion of roofing, upon completion of plastering and services, and upon practical completion. Interim payments must be supported by a payment certificate issued by the supervising engineer or architect.
Programme of Works: A detailed programme setting out the sequence and timing of the works, the contract completion date, and the number of calendar days allowed for completion. Provisions for extension of time should cover force majeure events, exceptional weather conditions, and employer-caused delays in accordance with Ghanaian construction practice.
Variations: A formal procedure for instructing and valuing variations to the scope of works. Variations must be instructed in writing by the owner or the supervising professional. No additional payment is due for works carried out without a written variation order.
Defects Liability: A defects liability period of at least 12 months following practical completion, during which the contractor is obliged to remedy any defects attributable to the contractor's workmanship or materials at no additional cost. A retention of 5-10% of the contract price is typically held back until expiry of the defects liability period.
Termination: Circumstances in which either party may terminate the contract, including employer termination for contractor default — such as persistent failure to proceed with diligence or insolvency — and contractor termination for non-payment extending beyond a specified grace period.
Dispute Resolution: A tiered dispute resolution mechanism providing for negotiation, followed by referral to the Ghana Arbitration Centre (GAC) for binding arbitration under the Alternative Dispute Resolution Act 2010 (Act 798), or litigation before the High Court (Commercial Division) in Accra. Forms-legal.com provides this template as a starting point for Ghana-compliant construction documentation.
Governing Law: Ghana law, with specific reference to the Contracts Act 1960 (Act 25), the Public Procurement Act 2003 (Act 663) where applicable, and the Alternative Dispute Resolution Act 2010 (Act 798). The contract should also reference the National Building Regulations 1996 (LI 1630) to confirm that all works will comply with the applicable building standards enforced by the relevant Metropolitan or District Assembly.
Additional compliance elements for a Construction Contract (Ghana) used in Ghana include: Under the Companies Act 2019 (Act 992), the Registrar General's Department (RGD) maintains the register of Ghanaian companies. Section 7 of the Companies Act 2019 governs company incorporation. The Ghana Revenue Authority (GRA) administers corporate tax under the Income Tax Act 2015 (Act 896). The Commercial Division of the High Court in Accra adjudicates business disputes. The Ghana Investment Promotion Centre (GIPC) regulates foreign investment under the GIPC Act 2013 (Act 865). Forms-legal.com provides this template as a starting point for Ghana-compliant documentation.
Cite this page
Reference this free template in an article, syllabus, or research note:
Forms Legal. (2026). Construction Contract (Ghana) (Ghana) [Legal document template]. Forms Legal. https://forms-legal.com/ghana/business/construction/construction-contract-ghana
"Construction Contract (Ghana) (Ghana)." Forms Legal, 2026, https://forms-legal.com/ghana/business/construction/construction-contract-ghana.
@misc{formslegal-construction-contract-ghana,
author = {{Forms Legal}},
title = {Construction Contract (Ghana) (Ghana)},
year = {2026},
howpublished = {\url{https://forms-legal.com/ghana/business/construction/construction-contract-ghana}},
note = {Free legal document template}
}Also available for these jurisdictions:
Frequently Asked Questions
The Contracts Act 1960 (Act 25) does not specifically mandate that construction contracts be in writing, as oral contracts are technically valid under Ghanaian common law. However, the Public Procurement Act 2003 (Act 663) requires public sector entities in Ghana to execute written contracts for all procurement of works above prescribed thresholds set by the Public Procurement Authority (PPA). For private sector projects, the High Court (Commercial Division) in Accra and the Ghana Arbitration Centre (GAC) strongly favour written agreements when resolving construction disputes, as oral evidence about scope, price, and programme is inherently unreliable. Any construction project requiring a Building Permit from the Accra Metropolitan Assembly (AMA) or another District Assembly will also require written documentation as part of the permit application process. In practice, any construction project with a value above GHS 20,000 should be governed by a written contract.
Construction contracts in Ghana are taxable supplies for Value Added Tax (VAT) purposes under the Value Added Tax Act 2013 (Act 870). VAT-registered contractors charge VAT at the standard rate of 15%, the National Health Insurance Levy (NHIL) at 2.5%, and the Ghana Education Trust Fund Levy (GETFund Levy) at 2.5% — giving an effective tax rate of 20% on the contract price. Contractors must be registered with the Ghana Revenue Authority (GRA) and hold a valid VAT registration certificate before issuing tax invoices on construction contracts. For public sector projects, the government entity — acting as the withholding agent — must withhold Withholding Tax (WHT) of 5% on payments to resident contractors and 15% on payments to non-resident contractors under the Income Tax Act 2015 (Act 896), and remit the withheld amount to the GRA.
Construction disputes in Ghana are resolved through several mechanisms under the Alternative Dispute Resolution Act 2010 (Act 798) and the High Court (Civil Procedure) Rules 2004 (C.I. 47). The most common route for large commercial construction disputes is arbitration before the Ghana Arbitration Centre (GAC) in Accra, which administers arbitrations under its own rules based on UNCITRAL principles. GAC arbitration awards are final, binding, and enforceable through the High Court of Ghana. Adjudication — a faster interim dispute resolution mechanism common in UK construction law — is not yet codified in Ghanaian statute but can be incorporated contractually. For smaller disputes, the District Courts and the High Court (Commercial Division) in Accra have jurisdiction. The Alternative Dispute Resolution Act 2010 (Act 798) also enables parties to refer disputes to a mediator or other ADR practitioner before resorting to arbitration or litigation.
The defects liability period (DLP) in a Ghana construction contract is a period — typically 12 months from the date of practical completion — during which the contractor is contractually obliged to return to site and remedy, at the contractor's own cost, any defects that arise from defective workmanship, materials, or non-compliance with the contract specification. The DLP is not specified in a single statute in Ghana but is a standard provision in contracts published by the Ghana Institution of Engineering (GhIE), the Ghana Institute of Architects (GIA), and the FIDIC standard forms used for internationally financed projects. During the DLP, the owner retains a portion of the contract price — typically 5% — as a retention sum. The retention is released in two tranches: 50% on practical completion and the balance at the end of the defects liability period, once the contractor has rectified all notified defects. After expiry of the DLP, the owner's claims for latent defects are governed by the Limitation Act 1972 (NRCD 54), which prescribes a six-year limitation period for claims in contract.
A Construction Contract in Ghana may be terminated before practical completion by either the owner or the contractor, subject to the contractual termination provisions and the general principles of the Contracts Act 1960 (Act 25). The owner may terminate for contractor default — including insolvency, persistent failure to proceed with diligence, or substantial departure from the contract specification — provided that written notice of default is given and the contractor fails to remedy the default within the agreed cure period. The contractor may terminate if the owner fails to make payments when due, obstructs the works, or becomes insolvent. Upon termination, the parties must account for works executed to date and materials on site, with payment due for the fair value of work done. Disputes arising from termination are referred to the Ghana Arbitration Centre (GAC) or the High Court (Commercial Division) in Accra, depending on the dispute resolution clause in the contract. Under the Contracts Act 1960 (Act 25), a party who wrongfully terminates a construction contract is liable to pay damages for the innocent party's loss of profit and additional costs.
This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer
Found an error? Let us knowRelated Documents
You may also find these documents useful:
Employment Contract (Ghana)
A formal Employment Contract for Ghana setting out terms of employment under the Labour Act 2003 (Act 651), covering duties, remuneration, SSNIT contributions, leave, and termination.
Independent Contractor Agreement (Ghana)
An Independent Contractor Agreement for Ghana distinguishing the contractor from an employee under the Labour Act 2003 (Act 651), with GRA withholding tax obligations and IP assignment clauses.
Non-Disclosure Agreement — Disclosure (Ghana)
A binding Non-Disclosure Agreement for Ghana protecting confidential business information under the Contract Act 1960 (Act 25) and equitable principles of confidence recognised by Ghanaian courts.
Consulting Agreement (Ghana)
A formal Consulting Agreement for Ghana governing an independent consultant's services under the Labour Act 2003 (Act 651) s.175, covering scope of services, fees, intellectual property, confidentiality, and termination.
Service Agreement (Ghana)
A general-purpose Service Agreement for Ghana governing the provision of professional or business services between a service provider and a client under the Contracts Act 1960 (Act 25).