Skip to main content

Business

Bill of Quantities (Construction) (Ghana)

A Bill of Quantities for Ghana construction projects, itemising materials, labour, and works under the Contracts Act 1960 (Act 25) and Ghana Institute of Surveyors standards, for use in tendering and contract administration.

Key facts

GhanaGhanaEnglish (GH)FreePDF & Word
Legal basisContracts Act 1960 (Act 25) source Signature lines in this template: 2 partiesSource verified
Bill of Quantities (Construction)

Bill of Quantities (Construction)

PROJECT: [Project Name]

EMPLOYER: [Employer Name], [Employer Address]

CONTRACT / PPA REFERENCE: [Contract Reference]

QUANTITY SURVEYOR: [QS Name]

DATE OF ISSUE: [Issue Date]

Prepared in accordance with the Standard Method of Measurement for Building Works in Ghana (GhIS-SMM) under the Ghana Institute of Surveyors Act 1986 (PNDCL 193) and the Public Procurement Act 2003 (Act 663).

Section P: Preliminary and General Items

P.1

Preliminary and general items (including site establishment, insurance, performance bond of [Performance Bond Percent] of the contract sum, and health and safety provisions under the Factories, Offices and Shops Act 1970 (Act 328)): GHS [Preliminaries Amount]

Work Sections Summary

A

Site clearance and earthworks: GHS [Earthworks Amount]

B

Concrete works (measured in m³ per GhIS-SMM): GHS [Concrete Amount]

C

Masonry and blockwork (measured in m²): GHS [Masonry Amount]

D

Roofing: GHS [Roofing Amount]

E

Plastering, screeds, and finishes: GHS [Finishes Amount]

F

Carpentry, joinery, and ironmongery: GHS [Joinery Amount]

G

Plumbing and drainage: GHS [Plumbing Amount]

H

Electrical installation: GHS [Electrical Amount]

I

External works and drainage: GHS [External Works Amount]

PS

Provisional sums and prime cost items: GHS [Provisional Sums Amount]

Summary and Grand Total

S.1

Total Contract Sum (excluding VAT and levies): GHS [Total Contract Sum Ex VAT]

S.2

VAT (15%) + NHIL (2.5%) + GETFund (2.5%) = 20% under the Value Added Tax Act 2025 (Act 1151): GHS [VAT Amount]

S.3

TOTAL CONTRACT SUM (including all taxes and levies): GHS [Total Contract Sum Inc VAT] ([Contract Sum Words])

Certification

I, the undersigned GhIS-registered quantity surveyor, certify that this Bill of Quantities has been prepared in accordance with the Standard Method of Measurement for Building Works in Ghana (GhIS-SMM), the Ghana Institute of Surveyors Act 1986 (PNDCL 193), and the Public Procurement Act 2003 (Act 663), and that the quantities stated herein are a true and accurate reflection of the work shown on the drawings and specifications issued for the above project.

Tenderer's Certification

I/We, the undersigned tenderer, confirm that this Bill of Quantities has been fully priced and that the Total Contract Sum stated above represents the full and complete cost of executing the works described herein in accordance with the contract documents and the Contracts Act 1960 (Act 25). Signed and dated by the tenderer's authorised representative.

GhIS-Registered Quantity Surveyor

________________

Signature

Tenderer (Authorised Representative)

________________

Signature

What Is a Bill of Quantities (Construction) (Ghana)?

A Bill of Quantities (Construction) in Ghana documents the bill of quantities in a form the parties and authorities can rely on.

The Ghana Institute of Surveyors Act 1986 (PNDCL 193) regulates the registration and practice of quantity surveyors in Ghana. Only a registered quantity surveyor or a firm of quantity surveyors licensed by the GhIS is authorised to prepare and certify a Bill of Quantities for a construction project in Ghana. The GhIS prescribes the Standard Method of Measurement for Building Works in Ghana (GhIS-SMM), which specifies how each work item — earthworks, concrete, masonry, joinery, finishes, mechanical and electrical services — must be measured and described. Bills of Quantities prepared in accordance with GhIS-SMM provide a consistent basis for tendering, enabling fair comparison of tenders submitted under the Public Procurement Act 2003 (Act 663) and under private sector procurement.

The Public Procurement Authority (PPA) in Ghana requires Bills of Quantities to be prepared for construction projects procured by government entities under Act 663. Section 60 of Act 663 and the PPA Standard Bidding Documents for Procurement of Works prescribe the format in which Bills of Quantities must be presented in tender documents, including summary sheets, work sections, provisional sums, and prime cost items. The PPA and the Ministry of Finance's Public Financial Management framework use Bills of Quantities as the basis for contract budget approval, variation order assessment, and payment certificate preparation.

A Bill of Quantities must be distinguished from a Schedule of Rates, which lists unit rates for construction activities without specifying quantities, and from a Priced Activity Schedule, which is used in design-and-build contracts where the contractor is responsible for measuring the works. A Bill of Quantities is most appropriate for traditionally procured construction contracts — such as the Joint Building Contracts Committee (JBCC) form adapted for Ghanaian use or the New Engineering Contract (NEC) adapted for Ghanaian public sector projects — where the employer provides the full design and the contractor prices the measured quantities.

The Ghana Revenue Authority (GRA) uses Bills of Quantities as supporting documents in the assessment of VAT on construction services under the Value Added Tax Act 2025 (Act 1151). Construction services supplied in Ghana attract the standard VAT rate of 15% plus the National Health Insurance Levy (NHIL) of 2.5%, the Ghana Education Trust Fund Levy (GETFund) of 2.5%, and the COVID-19 Health Recovery Levy of 1%, applied to the taxable value of construction services as measured in the Bill of Quantities.

When Do You Need a Bill of Quantities (Construction) (Ghana)?

A Bill of Quantities (Construction) in Ghana is required in the following circumstances under the Public Procurement Act 2003 (Act 663), the Contracts Act 1960 (Act 25), and Ghana Institute of Surveyors (GhIS) practice standards.

A Bill of Quantities is required for any construction project tendered through the public procurement process in Ghana where the procuring entity — a government ministry, district assembly, or state-owned enterprise — invites competitive tenders under Act 663. PPA Standard Bidding Documents for Procurement of Works require the employer's quantity surveyor to prepare a complete Bill of Quantities as part of the tender package, enabling tenderers to price each measured item rather than submit a lump-sum tender without breakdown.

A Bill of Quantities is needed for private sector construction projects in Ghana where the developer — an individual, a company incorporated under the Companies Act 2019 (Act 992), or a real estate developer licensed by the Ghana Real Estate Developers Association (GREDA) — invites competitive tenders from contractors registered with the Ghana National Contractors Association (GNCA). A priced Bill of Quantities forms the financial schedule to the construction contract, enabling the employer's quantity surveyor to assess monthly payment applications submitted by the contractor.

A Bill of Quantities is required when a contractor applies for a construction loan from a Bank of Ghana-licensed commercial bank to finance a construction project in Ghana. Banks typically require a priced Bill of Quantities approved by a GhIS-registered quantity surveyor as part of the loan appraisal documentation, to establish the project's estimated cost and the basis for drawdown of the loan in tranches linked to construction progress.

A Bill of Quantities is needed when a variation order is issued under a construction contract in Ghana. The Ghana National Construction Authority (NCA), which regulates contractors under the National Construction Authority Act 2011 (Act 820), requires that variation orders — additions to or omissions from the contracted works — be valued by reference to the rates and prices in the original Bill of Quantities, to prevent disputes over the cost of variations.

A Bill of Quantities is required for insurance valuation purposes when insuring a construction project under a Contractors All Risk (CAR) policy with a National Insurance Commission (NIC)-licensed insurer. The insurer uses the Bill of Quantities to establish the reinstatement value of the works for the purposes of the insured sum under the CAR policy.

A Bill of Quantities is needed for any construction project subject to the Environmental Protection Agency (EPA) Environmental Impact Assessment (EIA) process in Ghana, where the project cost — as established by the Bill of Quantities — determines the category of EIA required and the applicable permit fees under the Environmental Assessment Regulations 1999 (L.I. 1652).

What to Include in Your Bill of Quantities (Construction) (Ghana)

A valid Bill of Quantities (Construction) in Ghana under GhIS-SMM standards and the Public Procurement Act 2003 (Act 663) must contain the following essential elements.

Project Identification: Full name of the project, the employer's name and address, the contract reference number (for public sector projects, the PPA procurement reference), the name and GhIS registration number of the quantity surveyor who prepared the document, and the date of issue. GhIS-registered quantity surveyors must certify the Bill of Quantities with their registration number and professional seal.

Preliminary and General Items: A section covering the contractor's general obligations, site-establishment costs, insurance requirements under the construction contract, performance bond obligations under Section 44 of Act 663, health and safety provisions under the Factories, Offices and Shops Act 1970 (Act 328), and other preliminary costs that cannot be attributed to specific work sections. Preliminary costs in Ghanaian construction practice typically represent 8% to 15% of the contract sum.

Work Sections: Separate sections for each major trade or work category — site clearance and earthworks, concrete works (measured in cubic metres), masonry (measured in square metres), carpentry and joinery (measured in linear metres or square metres), roofing, plastering and finishes, plumbing and drainage, electrical installation, and external works. Each item must state the work description, the unit of measurement, the quantity, and a rate and extended amount column for the tenderer to complete.

Provisional Sums and Prime Cost Items: A schedule of provisional sums for work whose scope cannot be fully defined at tender stage — such as specialist subcontract packages or contingency allowances — and prime cost (PC) sums for work to be executed by nominated subcontractors or suppliers. PPA Standard Bidding Documents for Procurement of Works require provisional sums and PC sums to be clearly labelled and excluded from the contractor's profit and overhead calculation.

Summary and Grand Total: A summary sheet collecting the totals from all work sections, adding provisional sums and PC items, and producing the total contract sum excluding VAT. The tenderer signs and dates the summary sheet to confirm that the Bill of Quantities has been priced in full. The VAT-exclusive contract sum is the basis for calculating the 15% VAT, the NHIL and the GETFund levy under the Value Added Tax Act 2025 (Act 1151).

Daywork Schedule: A schedule of daywork rates for labour, plant, and materials for use in valuing minor variations that cannot be measured under the standard method. The Bill of Quantities template for Ghana includes pre-formatted work sections for common Ghanaian construction types, consistent with GhIS-SMM and NCA contractor classification requirements under Act 820, and aligns with PPA Standard Bidding Documents for Procurement of Works.

Sources & Citations

Statutory citations link to the official government text where one is available, otherwise to a free law library named next to the link.

  1. Public Procurement Act 2003 (Act 663)GH official
  2. Value Added Tax Act 2025 (Act 1151)GH official
  3. Companies Act 2019 (Act 992)GH official
  4. Contracts Act 1960 (Act 25)GH official

Cite this page

CC BY 4.0 · free to cite

Reference this free template in an article, syllabus, or research note:

APA
Forms Legal. (2026). Bill of Quantities (Construction) (Ghana) [Legal document template]. Forms Legal. https://forms-legal.com/ghana/business/construction/bill-of-quantities-construction-ghana
MLA
"Bill of Quantities (Construction) (Ghana)." Forms Legal, 2026, https://forms-legal.com/ghana/business/construction/bill-of-quantities-construction-ghana.
Chicago
Forms Legal. "Bill of Quantities (Construction) (Ghana)." Forms Legal, 2026. https://forms-legal.com/ghana/business/construction/bill-of-quantities-construction-ghana.
BibTeX
@misc{formslegal-bill-of-quantities-construction-ghana,
  author       = {{Forms Legal}},
  title        = {Bill of Quantities (Construction) (Ghana)},
  year         = {2026},
  howpublished = {\url{https://forms-legal.com/ghana/business/construction/bill-of-quantities-construction-ghana}},
  note         = {Free legal document template. Based on Contracts Act 1960 (Act 25)}
}
Wikipedia
{{cite web |title=Bill of Quantities (Construction) (Ghana) |website=Forms Legal |publisher=Forms Legal |date=2026 |url=https://forms-legal.com/ghana/business/construction/bill-of-quantities-construction-ghana}}
RIS
TY  - ELEC
T1  - Bill of Quantities (Construction) (Ghana)
T2  - Forms Legal
PB  - Forms Legal
PY  - 2026
UR  - https://forms-legal.com/ghana/business/construction/bill-of-quantities-construction-ghana
ER  - 
Forms Legal

Also available for these jurisdictions:

Frequently Asked Questions

Who is qualified to prepare a Bill of Quantities in Ghana?

Under the Ghana Institute of Surveyors Act 1986 (PNDCL 193), only a quantity surveyor registered with the Ghana Institute of Surveyors (GhIS) is authorised to prepare and certify a Bill of Quantities for construction projects in Ghana. GhIS maintains a register of licensed quantity surveying firms and individual practitioners. For public sector projects tendered under the Public Procurement Act 2003 (Act 663), the PPA requires that the employer's quantity surveyor be a GhIS-registered professional to ensure the Bill of Quantities complies with the Standard Method of Measurement for Building Works in Ghana (GhIS-SMM). For private sector projects, Ghanaian developers may engage either a GhIS-registered quantity surveyor or a firm with a recognised international qualification — such as a Chartered Quantity Surveyor registered with the Royal Institution of Chartered Surveyors (RICS) — provided the Bill of Quantities is prepared in accordance with GhIS-SMM. Contractors registered with the Ghana National Construction Authority (NCA) at D1 or D2 contractor classification level are required to maintain an in-house or consultancy quantity surveying capacity.

Can a contractor alter a Bill of Quantities after the contract is signed in Ghana?

A contractor in Ghana cannot unilaterally alter a priced Bill of Quantities that forms part of a signed construction contract, as the priced Bill of Quantities is a binding contractual document under the Contracts Act 1960 (Act 25). Changes to the scope or price of the works must be effected through a formal variation order issued by the employer or the employer's contract administrator — typically a GhIS-registered quantity surveyor or a Ghana Institution of Engineers (GhIE)-registered engineer. Variation orders are valued by reference to the rates and prices in the original Bill of Quantities under the standard forms of construction contract used in Ghana. Where the original Bill of Quantities rates are not applicable to a particular variation, the employer's quantity surveyor and the contractor negotiate a fair rate under the contract's valuation rules. Disputes about variation valuations may be referred to adjudication or arbitration under the construction contract's dispute resolution clause, administered by the Ghana Arbitration Centre (GAC) in Accra.

Is VAT included in a Bill of Quantities for construction in Ghana?

A Bill of Quantities for construction in Ghana is typically presented on a VAT-exclusive basis, with VAT and associated levies added separately to the total contract sum at the summary sheet stage. Under the Value Added Tax Act 2025 (Act 1151), construction services supplied in Ghana attract a combined effective rate of 20%: standard VAT of 15%, the National Health Insurance Levy (NHIL) of 2.5%, and the Ghana Education Trust Fund Levy (GETFund) of 2.5%. The COVID-19 Health Recovery Levy no longer applies from 1 January 2026. The contractor is required to register for VAT with the Ghana Revenue Authority (GRA) if their annual taxable turnover exceeds the registration threshold set by the Act, and to charge VAT on interim payment certificates and the final account. For public sector contracts under Act 663, the procuring entity withholds VAT Withholding Tax at source — GRA has implemented a VAT withholding mechanism for government contractors — and remits the withheld amount directly to the GRA. Private sector employers should confirm with their tax advisers whether the VAT Withholding Tax mechanism applies to their project.

What is the difference between a Bill of Quantities and a Schedule of Rates in Ghana?

A Bill of Quantities and a Schedule of Rates are both pricing documents used in Ghanaian construction contracting, but they serve different functions. A Bill of Quantities — prepared in accordance with GhIS-SMM — contains fully measured quantities of all work items derived from the architect's or engineer's drawings, and the tenderer prices a rate against each quantity to produce a contract sum. A Schedule of Rates contains unit rates for construction activities without specifying the total quantity of each item; it is used in term contracts, maintenance contracts, and design-and-build projects where the full scope of works cannot be defined before the contract is awarded. Under the Public Procurement Act 2003 (Act 663), the PPA uses Bills of Quantities for works contracts where the design is complete at tender stage, and Schedules of Rates for framework contracts and maintenance contracts where work orders are issued against pre-agreed rates during the contract term. For dispute resolution purposes before the Ghana Arbitration Centre (GAC), a priced Bill of Quantities carries greater evidentiary weight than a Schedule of Rates because the quantities are verified by the employer's quantity surveyor.

Do I need a lawyer to use a Bill of Quantities in Ghana?

A lawyer enrolled with the Ghana Bar Association is not required to prepare or use a Bill of Quantities in Ghana — the document is a quantity surveying instrument, not a legal instrument, and is prepared by a GhIS-registered quantity surveyor. However, legal advice is recommended when incorporating a Bill of Quantities into a formal construction contract, particularly for high-value projects where the construction contract — whether a JBCC-adapted form, an NEC3/NEC4 contract adapted for Ghanaian use, or a bespoke agreement — allocates risk between the employer and the contractor by reference to the priced Bill of Quantities. A Ghanaian lawyer with construction law experience can advise on the enforceability of contract terms, the validity of variation order procedures, the operation of the dispute resolution clause under the Ghana Arbitration Centre (GAC) rules, and compliance with the National Construction Authority Act 2011 (Act 820) contractor registration requirements. For public sector projects, compliance with PPA Standard Bidding Documents for Procurement of Works is mandatory and reduces but does not eliminate the need for tailored legal review.

Based on Contracts Act 1960 (Act 25) — text last edited November 2026Verify the source →

This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer

Found an error? Let us know