Project Completion Certificate (Ghana)
Contracts Act 1960 (Act 25)
PROJECT COMPLETION CERTIFICATE
Issued pursuant to the Contracts Act 1960 (Act 25) of Ghana
1. Project and Contract Particulars
Project: [Project Name]
Contract Reference: [Contract Reference]
Date of Construction Contract: [Contract Date]
Contract Sum: [Contract Sum]
2. Parties
Employer: [Employer Name], of [Employer Address].
Contractor: [Contractor Name], of [Contractor Address].
Supervising Architect / Engineer: [Supervising Professional].
3. Certification of Practical Completion
The undersigned hereby certifies that the works under the Contract reached practical completion on [Completion Date], being the date on which the works were found to be substantially complete and fit for their intended purpose under the Contracts Act 1960 (Act 25).
The originally contracted completion date was [Original Completion Date].
Outstanding snag items to be remedied by the Contractor: [Outstanding Items].
The works have been completed in accordance with the approved plans and specifications, the building permit issued by the relevant local assembly under the Local Governance Act 2016 (Act 936), and the applicable standards of the Ghana Standards Authority (GSA) under the Ghana Standards Authority Act 2011 (Act 820).
4. Defects Liability Period
The defects liability period commences on [Completion Date] and expires on [Defects Liability End].
During the defects liability period, the Contractor shall remedy any defects, shrinkages, or faults in the works notified in writing by the Employer, at the Contractor's own cost.
Retention to be released upon the issue of this certificate: [Retention Release Amount]. The balance of retention will be released upon the issue of the Final Completion Certificate at the end of the defects liability period.
Signatures
This Project Completion Certificate is issued on [Certificate Date].
Employer / Authorised Representative
________________
Signature
Supervising Architect / Engineer
________________
Signature
Contractor
________________
Signature
What Is a Project Completion Certificate (Ghana)?
A Project Completion Certificate in Ghana confirms the declared information and the maker's responsibility for its accuracy.
The issuance of a Project Completion Certificate has significant legal and financial consequences under the construction contract. Upon the issue of the certificate, the defects liability period commences — typically 12 months for building works and 24 months for civil engineering projects, during which the contractor remains obligated to remedy any defects that manifest in the works at the contractor's cost. The employer's right to call on the performance bond or retention bond is restricted during the defects liability period once the Completion Certificate has been issued, consistent with the conditions of the performance bond issued under standard practice by banks licensed by the Bank of Ghana (BoG).
The Public Procurement Act 2003 (Act 663), as amended by the Public Procurement (Amendment) Act 2016 (Act 914), governs procurement of works, services, and supplies by public entities in Ghana. The Public Procurement Authority (PPA) oversees compliance with Act 663. Under standard government construction contracts in Ghana — typically based on the FIDIC (Fédération Internationale des Ingénieurs-Conseils) Red Book or the Ghana government standard conditions — the issue of the Project Completion Certificate by the engineer or the employer's representative is a condition precedent to the release of the retention money held by the employer under the contract.
The Ghana Institution of Engineering (GhIE) and the Ghana Institution of Surveyors (GhIS) set professional standards for engineers and quantity surveyors in Ghana. The Ghana Institute of Architects (GIA) sets standards for architects. In building projects, the Project Completion Certificate is typically prepared by the architect or the quantity surveyor appointed under the construction contract, in accordance with the professional guidelines of the GIA or GhIS. An engineer registered with the Ghana Engineers Registration Board under the Ghana Engineering Council Act 2011 (Act 819) may also issue the certificate for civil or MEP (mechanical, electrical, plumbing) works.
The Environmental Protection Agency (EPA), established under the Environmental Protection Agency Act 1994 (Act 490), requires environmental impact assessments (EIAs) for certain categories of construction projects in Ghana. Where an EIA was required for the project, the Project Completion Certificate should confirm that the contractor has complied with the environmental conditions imposed by the EPA and has remediated any environmental damage caused during construction.
The Lands Commission of Ghana, established under the Lands Commission Act 2008 (Act 767), is responsible for the management of government and stool land, and for the Land Title Registry. Where the completed project includes new buildings or structures on registered land, the employer must register the new structures with the Lands Commission after the issue of the Project Completion Certificate, in accordance with the Land Title Registration Act 1986 (PNDCL 152).
A Project Completion Certificate for a private sector construction project governed by the Contracts Act 1960 (Act 25) should be distinguished from a certificate of completion issued by a local assembly under the Local Governance Act 2016 (Act 936). Under Act 936, district, municipal, and metropolitan assemblies in Ghana issue building permits and occupation certificates for new buildings and major extensions. The employer should obtain both the contractual Project Completion Certificate and, separately, the occupation certificate or building completion certificate from the relevant local assembly before the completed building is occupied.
When Do You Need a Project Completion Certificate (Ghana)?
A Project Completion Certificate in Ghana is needed at the practical completion stage of any construction, infrastructure, or services project to formally document that the works have been substantially completed in accordance with the contract.
A Project Completion Certificate is required when a contractor engaged under a public sector construction contract governed by the Public Procurement Act 2003 (Act 663) and the Public Procurement (Amendment) Act 2016 (Act 914) completes the works, because the employer cannot release the retention money held under the contract until the Project Completion Certificate is issued by the engineer or the employer's representative.
A Project Completion Certificate is needed when a performance bond or advance payment bond issued by a bank licensed by the Bank of Ghana (BoG) provides that the bond automatically reduces or expires upon the issue of the Project Completion Certificate. The contractor needs the certificate to request the partial release of the performance bond and to trigger the defects liability period.
A Project Completion Certificate is required when the employer needs to register completed buildings or structures with the relevant local assembly under the Local Governance Act 2016 (Act 936) to obtain an occupation certificate, because the local assembly typically requires evidence of the completion of the contracted works before issuing the occupation certificate.
A Project Completion Certificate is needed when a contractor has completed works for a company registered with the Ghana Free Zones Authority under the Ghana Free Zones Authority Act 1995 (Act 504), and the employer must demonstrate to the Ghana Free Zones Authority that the free zone infrastructure has been completed in accordance with the approved development plan.
A Project Completion Certificate is required when a development finance institution — such as a bank regulated by the Bank of Ghana (BoG) or the Ghana Infrastructure Investment Fund (GIIF) — has disbursed a construction loan and requires confirmation of practical completion as a condition for releasing the final tranche of the loan or for converting the construction facility to a term loan.
A Project Completion Certificate is needed when a contractor engaged under an engineering, procurement, and construction (EPC) contract for an energy project regulated by the Energy Commission of Ghana under the Energy Commission Act 1997 (Act 541) has completed the construction phase and needs to trigger the commencement of the operations and maintenance phase.
A Project Completion Certificate is required when the contractor needs to commence the defects liability period under the contract, so that the clock starts running on the period within which the employer may give notice of defects for the contractor to remedy at the contractor's cost.
What to Include in Your Project Completion Certificate (Ghana)
A legally effective Project Completion Certificate for use in Ghana under the Contracts Act 1960 (Act 25) must contain the following essential elements.
Project Identification: The full name and description of the project — for example, "Construction of a Three-Storey Office Building at Airport Hills, Accra, Greater Accra Region, Ghana" — and the contract reference number. Where the project was procured under the Public Procurement Act 2003 (Act 663), the Public Procurement Authority (PPA) tender reference number should be included.
Parties: The full legal names and addresses of the employer (the client) and the contractor. Where the employer is a public entity under Act 663, the name of the relevant government ministry, department, or agency should be stated. Where the contractor is a company registered under the Companies Act 2019 (Act 992), the company registration number issued by the Office of the Registrar of Companies (ORC) should be included.
Contract Details: The date of the construction contract, the contract sum (in Ghana cedis — GHS), and any approved variations to the contract sum. The contract sum should be stated inclusive of VAT and other levies under the Value Added Tax Act 2013 (Act 870) where the contractor is VAT-registered.
Date of Practical Completion: The date on which the works reached practical completion — the date the employer or the contract administrator formally accepted the works as substantially complete. This date determines when the defects liability period begins.
Outstanding Items: A schedule of any minor outstanding works or snag items that the contractor is required to remedy within a stated period, confirming that these items do not prevent the works from being used for their intended purpose.
Defects Liability Period: The start and end dates of the defects liability period — typically 12 months for building works from the date of practical completion, or such other period as specified in the contract. During this period, the contractor must rectify any defects notified by the employer at the contractor's own cost.
Retention Release: The conditions under which the retention money held by the employer will be released — for example, 50% of the retention released upon the issue of the Project Completion Certificate and the balance upon the issue of the Final Completion Certificate at the end of the defects liability period.
Compliance Statements: Confirmation that the works were completed in accordance with: the approved building plans and specifications; the building permit issued by the relevant local assembly under the Local Governance Act 2016 (Act 936); any environmental conditions imposed by the Environmental Protection Agency (EPA) under the Environmental Protection Agency Act 1994 (Act 490); and applicable Ghana Standards Authority (GSA) standards under the Ghana Standards Authority Act 2011 (Act 820).
Authorised Signatories: The certificate must be signed by the authorised representative of the employer, and — for supervised contracts — by the supervising architect, engineer, or quantity surveyor. Engineers must be registered with the Ghana Engineers Registration Board under the Ghana Engineering Council Act 2011 (Act 819); architects must be registered with the Architects Registration Board under the Architects Registration Board Act 2001 (Act 591).
Forms-legal.com provides this Project Completion Certificate template as a starting point for employers and contractors in Ghana. For public sector projects, the certificate must comply with the standard conditions prescribed by the Public Procurement Authority (PPA) under the Public Procurement Act 2003 (Act 663).
Cite this page
Reference this free template in an article, syllabus, or research note:
Forms Legal. (2026). Project Completion Certificate (Ghana) (Ghana) [Legal document template]. Forms Legal. https://forms-legal.com/ghana/business/construction/project-completion-certificate-ghana
"Project Completion Certificate (Ghana) (Ghana)." Forms Legal, 2026, https://forms-legal.com/ghana/business/construction/project-completion-certificate-ghana.
@misc{formslegal-project-completion-certificate-ghana,
author = {{Forms Legal}},
title = {Project Completion Certificate (Ghana) (Ghana)},
year = {2026},
howpublished = {\url{https://forms-legal.com/ghana/business/construction/project-completion-certificate-ghana}},
note = {Free legal document template}
}Also available for these jurisdictions:
Frequently Asked Questions
Practical completion in Ghana construction law is the stage at which the works under a construction contract are substantially complete and fit for their intended purpose, even if minor snag items or outstanding works remain. The concept of practical completion is recognised by the courts of Ghana — including the High Court (Commercial Division) in Accra — under the general principles of contract performance in the Contracts Act 1960 (Act 25). In standard construction contracts based on the FIDIC Red Book or the Ghana government standard conditions of contract, practical completion is certified by the engineer or the employer's representative, not merely declared by the contractor. The issue of the Project Completion Certificate triggers several important contractual consequences: the defects liability period commences; the employer's right to deduct liquidated damages for delay ceases; the risk of damage to the works passes from the contractor to the employer; and a portion of the retention money becomes due for release to the contractor.
The authority to issue a Project Completion Certificate depends on the terms of the construction contract and the nature of the project. For building projects, the supervising architect registered with the Architects Registration Board under the Architects Registration Board Act 2001 (Act 591), or the quantity surveyor registered with the Ghana Institution of Surveyors (GhIS), typically issues the certificate on behalf of the employer. For civil and infrastructure projects, the supervising engineer registered with the Ghana Engineers Registration Board under the Ghana Engineering Council Act 2011 (Act 819) issues the certificate. For public sector projects under the Public Procurement Act 2003 (Act 663), the employer's representative — typically a government technical officer — issues the certificate in accordance with the standard conditions of contract approved by the Public Procurement Authority (PPA). Where no professional consultant is appointed, the employer may issue the certificate directly, provided the contract permits this.
The defects liability period in Ghana is the period following practical completion during which the contractor remains obligated to remedy any defects, shrinkages, or other faults that appear in the works. The defects liability period is set by the construction contract — under standard FIDIC-based contracts used in Ghana, the period is typically 12 months for building works and up to 24 months for civil engineering or mechanical and electrical works. The defects liability period begins on the date certified in the Project Completion Certificate. During this period, the employer may give written notice to the contractor specifying defects to be remedied, and the contractor must attend to those defects within a reasonable time and at the contractor's own cost, under the principles of the Contracts Act 1960 (Act 25). At the end of the defects liability period, the employer issues a Final Completion Certificate confirming that all notified defects have been remedied and releasing the balance of the retention money.
A performance bond is a financial guarantee issued by a commercial bank licensed by the Bank of Ghana (BoG) or an insurance company licensed by the National Insurance Commission (NIC), guaranteeing that the contractor will perform the construction contract. Standard performance bonds in Ghana provide that upon the issue of the Project Completion Certificate, the bond amount reduces — typically from 10% to 5% of the contract sum — reflecting the reduced risk to the employer after practical completion. The remaining 5% bond then provides security during the defects liability period and is released upon the issue of the Final Completion Certificate at the end of that period. Where the contractor fails to complete the works by the agreed completion date, the employer may be entitled to call on the performance bond for liquidated damages, subject to the terms of the bond and the construction contract. The contractor should therefore act promptly to obtain the Project Completion Certificate upon practical completion to trigger the bond reduction.
No. A Project Completion Certificate and an occupation certificate are two separate documents issued by different authorities in Ghana. A Project Completion Certificate is a contractual document issued by the employer, the supervising architect or engineer, confirming that the construction works have reached practical completion under the construction contract and the Contracts Act 1960 (Act 25). An occupation certificate, by contrast, is an administrative certificate issued by the relevant metropolitan, municipal, or district assembly (MMDA) under the Local Governance Act 2016 (Act 936), confirming that a completed building complies with the approved building plans, the building permit conditions, and applicable building regulations, and is safe for occupation. Both documents are required before a completed building can lawfully be occupied in Ghana. The employer must obtain the Project Completion Certificate from the contractor's supervising professional and the occupation certificate from the local assembly independently — one does not substitute for the other.
The issue of a Project Completion Certificate in Ghana has specific implications for VAT under the Value Added Tax Act 2013 (Act 870) and for the release of retention money under the construction contract. On VAT: the final progress payment due upon practical completion constitutes a taxable supply under Act 870, and the contractor who is VAT-registered must issue a valid tax invoice under Section 41 of Act 870 showing the VAT registration number, the taxable value of the final payment, and the VAT, NHIL, and GETFund levies applicable. The employer (if VAT-registered) may claim an input VAT credit on the final payment upon receipt of the valid tax invoice. On retention: standard construction contracts in Ghana typically provide for the release of 50% of the accumulated retention upon the issue of the Project Completion Certificate, with the remaining 50% released upon the issue of the Final Completion Certificate at the end of the defects liability period. The Ghana Revenue Authority (GRA) may require stamp duty on the release of retention, depending on the form of the release documentation.
This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer
Found an error? Let us knowRelated Documents
You may also find these documents useful:
Construction Contract (Ghana)
A formal Construction Contract for Ghana setting out obligations of the owner and contractor under the Contracts Act 1960 (Act 25), covering scope of works, payment schedule, variations, defects liability, and dispute resolution.
Subcontractor Agreement (Ghana)
A binding Subcontractor Agreement for Ghana governing the engagement of subcontractors in construction and commercial projects under the Contracts Act 1960 (Act 25) and the Public Procurement Act 2003 (Act 663).
Performance Bond Agreement (Ghana)
A binding Performance Bond Agreement for Ghana guaranteeing contractual performance under the Contracts Act 1960 (Act 25) and the Public Procurement Act 2003 (Act 663), enforceable before the High Court (Commercial Division) in Accra.
Payment Plan Agreement (Ghana)
A legally binding Payment Plan Agreement for Ghana under the Contracts Act 1960 (Act 25) s.1, allowing a creditor and debtor to agree on structured instalment payments to satisfy an outstanding debt or financial obligation.