Skip to main content

Project Completion Certificate (Pakistan)

Project Completion Certificate (Pakistan)

PROJECT COMPLETION CERTIFICATE

Issued under the Contract Act 1872 | Pakistan Engineering Council Act 1976

Certificate Date: [Certificate Date]

Contract / Project Reference: [Project Reference]

1. PROJECT DETAILS

Project Name: [Project Name]

Project Location: [Project Location]

Building Plan Approval No.: [Building Plan Approval No]

2. PARTIES

Employer / Owner: [Employer Name], of [Employer Address].

Main Contractor: [Contractor Name], PEC Licence No.: [Contractor Licence No].

3. CERTIFICATION OF PRACTICAL COMPLETION

I, [Certifier Name], [Certifier Designation], Registration No. [Certifier Reg No], hereby certify that the works described below have been practically completed in accordance with the contract documents, approved drawings, specifications, and applicable building regulations.

Contractual Completion Date: [Contractual Completion Date]

Date of Practical Completion: [Actual Completion Date]

Scope of Works Certified Complete: [Scope Certified]

4. OUTSTANDING / SNAGGING ITEMS

The following minor items remain outstanding and must be completed by the contractor within the specified period: [Outstanding Items]

These items do not affect practical completion or the occupancy of the building.

5. DEFECTS LIABILITY PERIOD AND RETENTION

5.1 The Defects Liability Period of [Defects Liability Period] commences from the Date of Practical Completion ([Actual Completion Date]) during which the contractor shall rectify any defects notified by the employer at no additional cost.

5.2 Contract Value: [Contract Value].

5.3 Retention Money Released (first moiety): [Retention To Release]. The remaining retention shall be released upon issue of the Defects Correction Certificate at the end of the Defects Liability Period.

6. COMPLIANCE DECLARATIONS

The certifying professional declares that the completed works comply with:

- The approved building plan and any approved variations.

- The applicable provincial building code (Punjab Building Code 2021 / Sindh Building Control Ordinance 1979 / CDA Building Regulations, as applicable).

- Environmental requirements under the Pakistan Environmental Protection Act 1997.

- Health and safety requirements under the Factories Act 1934 and the site safety plan.

CERTIFICATION

Certified by: [Certifier Name]

Designation: [Certifier Designation]

Registration No.: [Certifier Reg No]

Signature: _________________________

Date: [Certificate Date]

Official Stamp: _________________________

Acknowledged by Employer: [Employer Name]

Signature: _________________________ Date: _________________________

Acknowledged by Contractor: [Contractor Name]

Signature: _________________________ Date: _________________________

Certifying Engineer / Architect

________________

Signature

Employer / Owner

________________

Signature

Main Contractor

________________

Signature

Maintained by Vladislav Sergienko, Founder·Template last modified: ·Report an error

What Is a Project Completion Certificate (Pakistan)?

A Project Completion Certificate in Pakistan records the details required for the process it supports, providing a clear written account that can be relied on.

The Contract Act 1872 (Act No. IX of 1872) governs the obligations of the contractor and employer in a construction contract. Section 37 of the Contract Act 1872 provides that the parties to a contract must either perform or offer to perform their respective promises, unless such performance is dispensed with or excused under the provisions of the Contract Act 1872 or any other law. Practical completion — the state of completeness certified by the Project Completion Certificate — discharges the contractor's primary obligation to complete the works and simultaneously triggers the employer's obligation to release retention under Section 55 of the Contract Act 1872, which provides that time is the essence of a contract only where the parties have made it so.

In Pakistan, construction projects are additionally regulated by local building control authorities. In Punjab, the Punjab Building Code 2021 administered by the Punjab Building Department and the Lahore Development Authority (LDA) requires formal completion inspection before a building is certified as fit for occupation. In Sindh, the Sindh Building Control Authority (SBCA) under the Sindh Building Control Ordinance 1979 issues occupancy certificates following a completion inspection. In Islamabad Capital Territory, the Capital Development Authority (CDA) under the Capital Development Authority Ordinance 1960 performs completion inspections before issuing occupation certificates. In Khyber Pakhtunkhwa, the Building Control Act KPK applies. The Project Completion Certificate under the construction contract is distinct from the statutory Completion Certificate or Occupancy Certificate issued by these regulatory bodies, though the two are often required together.

For public sector projects, the Public Procurement Regulatory Authority (PPRA) Rules 2004 govern procurement and contract administration. PPRA Rule 46 requires that public sector construction contracts specify the procedure for completion certification and defects liability. Federal government projects are additionally subject to the Works and Services Department procedures for completion certification, which require certification by the project's designated Engineer-in-Charge before final payment is released.

International construction contracts in Pakistan — particularly those funded by development finance institutions such as the World Bank, Asian Development Bank (ADB), or China-Pakistan Economic Corridor (CPEC) infrastructure projects financed by the China Development Bank — frequently adopt FIDIC (Fédération Internationale des Ingénieurs-Conseils) conditions of contract. The FIDIC Red Book (Construction Contract) and Yellow Book (Plant and Design-Build) both prescribe specific procedures for the Taking-Over Certificate (equivalent to the Project Completion Certificate) under FIDIC Sub-Clause 10.1, which requires the contractor to apply for a Taking-Over Certificate when the works are substantially complete and the employer issues it within 28 days of the application if satisfied.

The Project Completion Certificate is distinct from an Interim Payment Certificate (which certifies progress payments during construction), a Defects Correction Certificate (issued at the end of the defects liability period), and a No-Objection Certificate (NOC) issued by regulatory authorities. The Project Completion Certificate marks the point of practical completion and is the basis for calculating the defects liability period, which under most Pakistani construction contracts runs for 6 to 12 months after the date of the certificate.

When Do You Need a Project Completion Certificate (Pakistan)?

A Project Completion Certificate in Pakistan is required at the conclusion of every construction project or significant works contract to formally record that the contractor has fulfilled contractual obligations and to trigger the downstream legal and financial consequences specified in the construction contract.

A Project Completion Certificate is needed upon completion of a residential building in Lahore, Karachi, Islamabad, or any other city where the contractor has constructed the building in accordance with the approved plan sanctioned by the Lahore Development Authority (LDA), Karachi Development Authority (KDA), Capital Development Authority (CDA), or relevant municipal authority. The certificate documents that the building matches the approved drawings and specifications, enabling the employer to proceed with the occupancy certificate application.

A Project Completion Certificate is required at the end of a government infrastructure project — road construction, bridge works, irrigation works under the Pakistan Water and Power Development Authority (WAPDA), or building works under the Public Works Department (PWD) — to authorise final payment to the contractor and to commence the defects liability period during which the contractor remains responsible for rectifying defects at no additional cost.

A Project Completion Certificate is needed in commercial construction projects — factory buildings, office complexes, warehouses, and industrial facilities — to release the retention money typically withheld at 5% to 10% of each progress payment under the construction contract. Release of retention is conditional on the Project Completion Certificate under standard Pakistani construction contract terms, and the contractor cannot demand payment of retention without presenting the signed certificate.

A Project Completion Certificate is required for infrastructure projects financed by the Asian Development Bank (ADB), World Bank, or other multilateral development banks operating in Pakistan, where the Project Completion Certificate or Taking-Over Certificate under FIDIC Sub-Clause 10.1 is a prerequisite for the disbursement of the final tranche of project financing and for the submission of the project completion report to the lending institution.

A Project Completion Certificate is needed in engineering, procurement, and construction (EPC) contracts for power generation projects — particularly renewable energy projects under the Alternative Energy Development Board (AEDB) framework and the National Electric Power Regulatory Authority (NEPRA) licensing regime — where the certificate marks the date from which the power purchase agreement (PPA) commercial operation date (COD) is calculated and power sales commence.

What to Include in Your Project Completion Certificate (Pakistan)

A valid Project Completion Certificate in Pakistan under the Contract Act 1872 and applicable construction regulations must include the following essential elements to be legally effective and accepted by employers, contractors, financial institutions, and regulatory authorities.

Project Identification: The full name and description of the project, the project number or reference, the location (address, plot number, survey number, or GPS coordinates), the building plan approval number issued by the relevant building authority (LDA, KDA, CDA, SBCA, or relevant authority), and the contract reference number. Clear project identification prevents the certificate from being applied to a different project or phase.

Parties to the Contract: Full legal names and addresses of the employer (owner or client), the main contractor, and (where applicable) the nominated sub-contractors whose works form part of the completion. For government contracts, the designation of the Engineer-in-Charge appointed under the Public Works Department or PPRA Rules 2004 should be stated.

Certifying Authority: Name, professional designation, and registration number of the certifying engineer or architect. In Pakistan, engineers should be registered with the Pakistan Engineering Council (PEC) under the Pakistan Engineering Council Act 1976, and architects with the Pakistan Council of Architects and Town Planners (PCATP) under the Pakistan Council of Architects and Town Planners Act 1983. Certification by an unregistered professional may be challenged in court.

Scope of Works Certified: A description of the specific works being certified as complete — structural works, finishing works, mechanical, electrical, and plumbing (MEP) systems, external works, and site clearance. Where only a portion or phase of the project is complete, the certificate must clearly state the scope of the partial completion.

Date of Practical Completion: The date on which the works were inspected and found practically complete. This date is critical as it starts the defects liability period, triggers retention release obligations, and marks the commencement of the building's insurance cover in the employer's name.

Outstanding Works and Defects (Snagging List): Any minor works, snagging items, or outstanding obligations that are excluded from the certificate and that the contractor must complete within a specified period. The certificate must distinguish between works that are practically complete (allowing the certificate to issue) and works that remain genuinely outstanding (which must be listed and time-bound).

Defects Liability Period: The duration of the defects liability period commencing from the date of the certificate — typically 6 or 12 months under Pakistani construction contracts. During this period, the contractor must rectify any defects notified by the employer at no additional cost under the Contract Act 1872's implied warranty of fitness and the express provisions of the construction contract.

Retention Release: A statement confirming that the certificate triggers the release of half the retention money (the first moiety) to the contractor, with the remaining retention released at the end of the defects liability period upon issue of the Defects Correction Certificate. Retention release provisions must comply with the construction contract and may be subject to audit under PPRA Rules 2004 for public sector contracts.

Compliance Declarations: Confirmation that the works have been carried out in compliance with the approved building plan, the Punjab Building Code 2021 or applicable provincial building code, all applicable environmental requirements under the Pakistan Environmental Protection Act 1997, and health and safety requirements under the Factories Act 1934 and any site-specific safety plan.

Forms-legal.com provides this Project Completion Certificate (Pakistan) template as a practical starting point for construction project administration. Project owners, contractors, and certifying engineers should obtain advice from Pakistan Engineering Council (PEC)-registered engineers and qualified Advocates enrolled at the relevant provincial bar for complex infrastructure projects, government contracts, and FIDIC-based international construction agreements.

Under the Companies Act 2017, the Securities and Exchange Commission of Pakistan (SECP) maintains the register of Pakistani companies. Section 16 of the Companies Act 2017 governs company incorporation. The Contract Act 1872 governs general contractual obligations. The Federal Board of Revenue (FBR) administers corporate tax under the Income Tax Ordinance 2001. The High Courts (Lahore, Sindh, Peshawar, Balochistan, Islamabad) have original and appellate jurisdiction.

Cite this page

Reference this free template in an article, syllabus, or research note:

APA

Forms Legal. (2026). Project Completion Certificate (Pakistan) (Pakistan) [Legal document template]. Forms Legal. https://forms-legal.com/pakistan/business/construction/project-completion-certificate-pakistan

MLA

"Project Completion Certificate (Pakistan) (Pakistan)." Forms Legal, 2026, https://forms-legal.com/pakistan/business/construction/project-completion-certificate-pakistan.

BibTeX
@misc{formslegal-project-completion-certificate-pakistan,
  author       = {{Forms Legal}},
  title        = {Project Completion Certificate (Pakistan) (Pakistan)},
  year         = {2026},
  howpublished = {\url{https://forms-legal.com/pakistan/business/construction/project-completion-certificate-pakistan}},
  note         = {Free legal document template}
}

Also available for these jurisdictions:

Frequently Asked Questions

Statute-referenced template — Template last modified June 2026

This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer

Found an error? Let us know

Related Documents

You may also find these documents useful:

Construction Contract (Pakistan)

A Construction Contract for Pakistan — a comprehensive agreement between a property owner and contractor governing the construction of a building or civil works project, compliant with the Contract Act 1872, and incorporating project scope, timelines, payment terms, and defect liability provisions applicable under Pakistani construction law.

Building Contract (Pakistan)

A Building Contract for Pakistan — a comprehensive construction agreement between an owner and a contractor for the design and build or build-only construction of a structure, governed by the Contract Act 1872, applicable building bylaws, and the Pakistan Engineering Council's professional standards.

Variation Order — Construction (Pakistan)

A Variation Order for construction projects in Pakistan — a formal written instruction from an employer or engineer to a contractor authorising a change in scope, design, or specification under an existing construction contract governed by the Contract Act 1872.

Performance Bond (Pakistan)

A Performance Bond for Pakistan — a guarantee instrument issued by a surety (bank or insurance company) to a project owner, securing the contractor's contractual obligations under the Contract Act 1872, the Public Procurement Regulatory Authority Ordinance 2002, and State Bank of Pakistan prudential regulations.

Building Plan Approval Application (Pakistan)

A Building Plan Approval Application for Pakistan — a formal submission to the Building Control Authority or Municipal Committee for sanction of construction drawings under the Building Control Authority Ordinance, Punjab Local Government Act 2013, and applicable municipal bye-laws.