Performance Bond (Pakistan)
PERFORMANCE BOND
Under the Contract Act 1872 | Public Procurement Rules 2004 | State Bank of Pakistan Guidelines
Bond No.: _________________________
Bond Issue Date: [Bond Issue Date]
PRINCIPAL (Contractor):
[Principal Name], having its address at [Principal Address] ("Principal").
SURETY:
[Surety Name], SBP/SECP Registration No. [Surety Reg Number], having its address at [Surety Address] ("Surety").
BENEFICIARY (Project Owner / Obligee):
[Beneficiary Name], having its address at [Beneficiary Address] ("Beneficiary").
RECITALS
A. The Principal has entered into a contract with the Beneficiary under Contract Reference [Contract Reference] dated [Contract Date], for a total contract value of [Contract Value] ("Contract").
B. The Contract requires the Principal to furnish a Performance Bond as security for the Principal's due performance of all obligations under the Contract.
C. At the request of the Principal, the Surety has agreed to issue this Performance Bond in favour of the Beneficiary on the terms and conditions set out below.
1. SURETY'S UNDERTAKING
1.1 The Surety hereby unconditionally and irrevocably guarantees to the Beneficiary that, in the event of the Principal's failure to duly perform all its obligations under the Contract, the Surety shall, upon the Beneficiary's written demand, pay to the Beneficiary an amount not exceeding [Bond Amount] ("Bond Amount").
1.2 Bond Type: [Bond Type].
1.3 The Surety's liability under this Bond is in accordance with Section 126 and Section 128 of the Contract Act 1872. The Surety waives any right to require the Beneficiary to first exhaust remedies against the Principal before claiming under this Bond.
2. DEMAND PROCEDURE
2.1 The Beneficiary may make a demand under this Bond by delivering to the Surety a written demand stating that the Principal has failed to perform the Contract and specifying the amount claimed (not exceeding the Bond Amount).
2.2 The Surety shall pay the demanded amount to the Beneficiary within [Payment Period] of receiving a conforming written demand, without the right to delay payment pending resolution of any dispute between the Principal and the Beneficiary.
2.3 The Surety shall not be entitled to withhold payment on the basis of any dispute, set-off, or counterclaim asserted by the Principal against the Beneficiary.
3. VALIDITY AND EXTENSION
3.1 This Bond shall be valid from [Bond Issue Date] until [Bond Expiry Date], which date is calculated to cover the Contract completion date of [Contract Completion Date] plus the defect liability period of [Defect Liability Period].
3.2 If the Contract completion date is extended by variation order, force majeure, or any other reason, the Beneficiary may request the Surety to extend the validity of this Bond, and the Surety shall extend the Bond validity within 15 working days of such request.
3.3 This Bond shall be released and returned to the Principal upon the Beneficiary's written confirmation that the Principal has satisfactorily completed all obligations under the Contract including the defect liability period, or upon the Bond expiry date if no valid demand has been made.
4. GOVERNING LAW AND JURISDICTION
This Bond is governed by the laws of the Islamic Republic of Pakistan, including the Contract Act 1872 and the Public Procurement Rules 2004. Any dispute arising under this Bond shall be subject to the exclusive jurisdiction of the competent courts in [Governing City].
IN WITNESS WHEREOF
This Performance Bond is issued by the Surety on [Bond Issue Date].
SURETY: [Surety Name]
Authorised Signatory Name: _________________________
Designation: _________________________
Signature: _________________________
Official Bank / Company Stamp and Seal: _________________________
Date: _________________________
ACKNOWLEDGED BY PRINCIPAL: [Principal Name]
Authorised Signatory: _________________________ Date: _________________________
FOR RECORD BY BENEFICIARY: [Beneficiary Name]
Received by: _________________________ Date: _________________________
Surety (Bank / Insurance Company)
________________
Signature
Principal (Contractor)
________________
Signature
Beneficiary (Project Owner) — for acknowledgement
________________
Signature
What Is a Performance Bond (Pakistan)?
A Performance Bond in Pakistan records the guarantee under which the obligor undertakes to meet the secured obligation.
The Performance Bond in Pakistan is governed by the Contract Act 1872 (Act No. IX of 1872), which contains the law of contract including guarantee instruments under Chapter VIII (Sections 124-147). Section 126 of the Contract Act 1872 defines a guarantee as "a contract to perform the promise, or discharge the liability, of a third person in case of his default." Section 128 provides that the surety's liability is co-extensive with that of the principal debtor unless the contract of guarantee expressly provides otherwise — meaning the project owner can demand payment from the surety bank without first exhausting remedies against the contractor.
For public sector projects, the Public Procurement Regulatory Authority Ordinance 2002 (PPRA Ordinance) and the Public Procurement Rules 2004 issued thereunder regulate procurement by federal government ministries, departments, and autonomous bodies. Rule 40 of the Public Procurement Rules 2004 requires the successful bidder in a public tender to furnish a Performance Security (Performance Bond) before award — typically 5% to 10% of the contract value — to remain in force throughout the contract execution period and the defect liability period. The Pakistan Public Works Department (PWD) and the Federal Government's Central Public Works Organisation (CPWO) specify standard Performance Bond formats in their standard bidding documents.
Provincial governments also maintain procurement regulations: the Punjab Procurement Rules 2014, the Sindh Public Procurement Rules 2010, the Khyber Pakhtunkhwa Public Procurement of Goods, Works and Services Rules 2014, and the Balochistan Procurement Rules similarly require Performance Security from successful contractors. The National Highway Authority (NHA), the Water and Power Development Authority (WAPDA), and other federal autonomous bodies have their own standard forms of Performance Bond based on PPRA guidelines and international standards including the FIDIC (Fédération Internationale des Ingénieurs-Conseils) suite of contracts.
A Performance Bond must be distinguished from a Bid Bond (Tender Guarantee) — which secures the bidder's obligation to enter into the contract if awarded — and from an Advance Payment Guarantee, which secures the contractor's obligation to repay any advance payment received from the project owner if the contractor fails to perform. The Performance Bond becomes effective upon contract award and remains operative until the contractor fulfils all contractual obligations including the defect liability or warranty period, after which the bond is released by the project owner.
The legal framework governing the Performance Bond (Pakistan) in Pakistan draws on several key statutes and regulatory bodies. Under the Companies Act 2017, the Securities and Exchange Commission of Pakistan (SECP) maintains the register of Pakistani companies. Section 16 of the Companies Act 2017 governs company incorporation. The Contract Act 1872 governs general contractual obligations. The Federal Board of Revenue (FBR) administers corporate tax under the Income Tax Ordinance 2001. The High Courts (Lahore, Sindh, Peshawar, Balochistan, Islamabad) have original and appellate jurisdiction. Parties executing a Performance Bond (Pakistan) in Pakistan should confirm the document reflects current law, including any amendments enacted since the original drafting date. The Contract Act 1872 sets the foundational requirements.
When Do You Need a Performance Bond (Pakistan)?
A Performance Bond in Pakistan is required across a wide range of public procurement and private contracting situations where a project owner requires financial assurance of the contractor's performance.
A Performance Bond is needed when a contractor wins a public tender issued by a federal or provincial government department under the Public Procurement Rules 2004 or provincial equivalents. Rule 40 of the Public Procurement Rules 2004 requires submission of a Performance Security within the period specified in the bidding documents — failure to furnish the Performance Bond within the required time results in forfeiture of the Bid Bond and may lead to disqualification from future PPRA-registered procurement for a specified period.
A Performance Bond is required when a private sector project owner — such as a real estate developer registered with the Real Estate Regulatory Authority (RERA) or a housing scheme approved by the relevant Development Authority — engages a construction contractor for a residential or commercial development. Private project owners use Performance Bonds to protect themselves against contractor default, particularly for projects financed by banks under project finance facilities arranged by scheduled banks under SBP regulations.
A Performance Bond is needed when a supplier or manufacturer in a supply contract for industrial equipment, pharmaceutical products, or consumer goods requires the buyer to accept delivery guarantees backed by a bank guarantee. The buyer requests a Performance Bond from the supplier's bank to secure timely delivery and specification compliance under the sale contract governed by the Contract Act 1872 and the Sale of Goods Act 1930.
A Performance Bond is required when an international contractor operating in Pakistan through a joint venture or a local subsidiary submits a bid for a large infrastructure project — road construction under the National Highway Authority (NHA), power generation under WAPDA or NEPRA-licensed projects, or water supply under a provincial public health engineering department — and the project owner's standard bidding document (based on FIDIC or World Bank standard forms) requires a bank guarantee from a Pakistani scheduled bank or an internationally rated bank with a branch in Pakistan.
A Performance Bond is needed when a government-to-government (G2G) agreement or an agreement signed under the China-Pakistan Economic Corridor (CPEC) framework requires Pakistani and Chinese contractors to provide cross-guarantees for their respective contractual obligations, and the guarantees must be issued by a bank acceptable to both parties and to the relevant financing institutions.
Under the Companies Act 2017, the Securities and Exchange Commission of Pakistan (SECP) maintains the register of Pakistani companies. Section 16 of the Companies Act 2017 governs company incorporation. The Contract Act 1872 governs general contractual obligations. The Federal Board of Revenue (FBR) administers corporate tax under the Income Tax Ordinance 2001. The High Courts (Lahore, Sindh, Peshawar, Balochistan, Islamabad) have original and appellate jurisdiction.
What to Include in Your Performance Bond (Pakistan)
A valid Performance Bond in Pakistan under the Contract Act 1872 and the Public Procurement Rules 2004 must contain the following essential elements to be enforceable by the beneficiary (project owner) against the surety (bank or insurance company).
Parties: Full legal name of the principal (contractor), the surety (issuing bank or insurance company with their SBP or SECP registration number), and the beneficiary (project owner). For government beneficiaries, the ministry, department, or autonomous body's full official name and address must be stated.
Underlying Contract Reference: The name, number, date, and subject matter of the contract secured by the Performance Bond — for example, "Contract No. NHA/2024/001 dated [date] for Construction of [Road/Project Name]." The contract value and the completion date must be referenced.
Bond Amount and Currency: The guaranteed amount expressed as a fixed sum (typically 5-10% of the contract value for PPRA contracts, or as specified in the contract). The currency — Pakistani Rupees (PKR) or, for international contracts, the agreed foreign currency — and the exchange rate mechanism if applicable.
Unconditional Demand Feature: Whether the bond is a conditional or unconditional (on-demand) guarantee. Most PPRA and FIDIC-based contracts require an unconditional (first-demand) Performance Bond under which the surety must pay upon the beneficiary's first written demand without requiring proof of the contractor's default. This is more favourable to the project owner than a conditional bond requiring proof of breach.
Validity Period: The bond must remain in force from the contract commencement date until the expiry of the defect liability period (typically 12 to 24 months after practical completion). The bond must include an automatic extension clause if the contract completion date is extended by variation order or force majeure, or the surety must agree to extend the bond validity upon the project owner's written request.
Demand Mechanism: The procedure for the beneficiary to make a claim — typically a written demand to the surety at the surety's specified address, stating that the principal has failed to perform the contract and the amount claimed. The surety must pay within a specified number of business days (typically 5-15 working days) of receiving a conforming demand.
Governing Law and Jurisdiction: Pakistani law as the governing law, and the jurisdiction of the courts in Islamabad, Lahore, Karachi, or the city of the project — or arbitration under the Arbitration Act 1940 if the underlying contract specifies arbitration.
Release Conditions: The circumstances in which the bond is released and returned to the contractor — typically upon the project owner's written confirmation of satisfactory completion of all contractual obligations including the defect liability period, or upon the bond's expiry date without a valid demand.
Forms-legal.com provides this Performance Bond (Pakistan) template as a practical starting point compliant with the Contract Act 1872, the Public Procurement Rules 2004, and State Bank of Pakistan guidelines for bank guarantees. Project owners and contractors engaged in high-value infrastructure projects should work with their legal advisors and banking relationship managers to customise the bond terms to the specific project requirements and financing arrangements.
Additional compliance elements for a Performance Bond (Pakistan) used in Pakistan include: Under the Companies Act 2017, the Securities and Exchange Commission of Pakistan (SECP) maintains the register of Pakistani companies. Section 16 of the Companies Act 2017 governs company incorporation. The Contract Act 1872 governs general contractual obligations. The Federal Board of Revenue (FBR) administers corporate tax under the Income Tax Ordinance 2001. The High Courts (Lahore, Sindh, Peshawar, Balochistan, Islamabad) have original and appellate jurisdiction. Forms-legal.com provides this template as a starting point for Pakistan-compliant documentation.
Cite this page
Reference this free template in an article, syllabus, or research note:
Forms Legal. (2026). Performance Bond (Pakistan) (Pakistan) [Legal document template]. Forms Legal. https://forms-legal.com/pakistan/business/contracts/performance-bond-pakistan
"Performance Bond (Pakistan) (Pakistan)." Forms Legal, 2026, https://forms-legal.com/pakistan/business/contracts/performance-bond-pakistan.
@misc{formslegal-performance-bond-pakistan,
author = {{Forms Legal}},
title = {Performance Bond (Pakistan) (Pakistan)},
year = {2026},
howpublished = {\url{https://forms-legal.com/pakistan/business/contracts/performance-bond-pakistan}},
note = {Free legal document template}
}Frequently Asked Questions
Under Rule 40 of the Public Procurement Rules 2004 issued by the Public Procurement Regulatory Authority (PPRA), the Performance Security for public sector contracts in Pakistan is typically between 5% and 10% of the contract value, as specified in the bidding documents. The exact percentage depends on the risk profile of the contract — larger, more complex contracts or contracts with higher risk of contractor default may attract a higher Performance Security requirement. Private sector contracts have no fixed statutory percentage — the project owner and contractor negotiate the bond amount based on the contract value, the contractor's financial standing, and market practice. For FIDIC-based contracts (widely used in Pakistan for infrastructure and EPC projects), the Performance Security is typically 10% of the accepted contract amount. The bond amount must be sufficient to cover the cost of engaging an alternative contractor to complete the works in the event of the original contractor's default, which may exceed the stated bond percentage if the replacement contractor charges a premium.
A contractor in Pakistan whose Performance Bond has been wrongfully called by a project owner can seek an injunction from the relevant High Court (Lahore High Court, Sindh High Court, Peshawar High Court, Balochistan High Court, or Islamabad High Court) restraining the surety bank from making payment. Under Pakistani law, courts have granted injunctions restraining payment on bank guarantees where there is clear evidence of fraud by the beneficiary — the so-called 'fraud exception' to the autonomy principle of bank guarantees recognised in landmark Supreme Court of Pakistan judgments. However, the contractor must act swiftly — typically within days of the demand — and demonstrate a strong prima facie case of fraud or unconscionable conduct. Mere breach of contract by the project owner or a bona fide dispute over performance standards is generally insufficient to restrain payment. The contractor's primary remedy for a wrongful call is a damages claim against the project owner under Section 73 of the Contract Act 1872 for any loss suffered as a result of the improper demand.
In Pakistani commercial practice, the terms 'Performance Bond' and 'bank guarantee' are often used interchangeably, but there is a technical distinction. A Performance Bond is traditionally a three-party instrument (principal, surety, and beneficiary) where the surety's obligation is secondary to the principal's — the surety pays only if the principal fails to perform. A bank guarantee issued by a scheduled bank regulated by the State Bank of Pakistan is typically an independent, unconditional (on-demand) obligation of the bank — the bank is a primary obligor who pays on first demand without requiring proof of the contractor's default. Most PPRA and private sector project documents in Pakistan use the term 'Performance Security' or 'Performance Guarantee' to refer to an unconditional bank guarantee rather than a traditional conditional Performance Bond. The State Bank of Pakistan's prudential regulations and foreign exchange guidelines govern the issuance of bank guarantees by scheduled banks, including guarantees denominated in foreign currency for international contracts.
A Performance Bond in Pakistan must remain valid for the entire period during which the project owner can claim against the contractor for failure to perform — which includes both the construction or delivery period and the defect liability (warranty) period following practical completion. For PPRA public sector contracts, the Performance Security typically remains in force until 14 to 28 days after the expiry of the defect liability period, to allow the project owner time to inspect and confirm satisfactory performance. For FIDIC-based contracts, the defect notification period is typically 12 months after the taking-over date, meaning the Performance Security must remain valid for at least 12 months post-completion plus the notice period. Where the contract completion is delayed by extension of time, the Performance Bond validity must be extended accordingly — most bond documents include a clause requiring the surety to extend validity upon the project owner's written request. A Performance Bond that expires before contractual obligations are completed leaves the project owner without security for the remaining period.
In Pakistan, Performance Bonds can be issued by both scheduled banks regulated by the State Bank of Pakistan and by insurance companies licensed by the Securities and Exchange Commission of Pakistan (SECP) under the Insurance Ordinance 2000. Bonds issued by insurance companies are known as surety bonds and are typically issued by non-life insurance companies with a surety bond product line. The Insurance Ordinance 2000 governs the licensing of non-life insurers in Pakistan, and SECP regulates their solvency requirements and product approvals. For PPRA public sector contracts, the bidding documents typically specify that the Performance Security must be in the form of a bank guarantee from a scheduled bank — some government departments do not accept insurance company surety bonds because banks are perceived as more creditworthy guarantors. Private sector project owners and international clients are more likely to accept surety bonds from SECP-licensed insurance companies. Contractors should confirm the acceptability of insurance surety bonds with the project owner before arranging coverage.
When a construction contract in Pakistan is novated (transferring all rights and obligations to a new contractor) or assigned (transferring rights only), the original Performance Bond issued in favour of the project owner does not automatically extend to cover the new contractor's obligations. The project owner must obtain a fresh Performance Bond from the new contractor or ensure that the original surety bank expressly extends the bond to cover the novated arrangement. Under the Contract Act 1872, a novation extinguishes the original contract and creates a new contract — the original contractor's obligations (and the bond securing them) are discharged upon novation unless the surety expressly consents to remain bound. For partial assignment, the bond may continue to secure the original contractor's retained obligations. Project owners should address the Performance Bond implications in the novation or assignment agreement itself, requiring the incoming contractor to provide replacement security before releasing the original contractor from their obligations under the bond.
This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer
Found an error? Let us knowRelated Documents
You may also find these documents useful:
Construction Contract (Pakistan)
A Construction Contract for Pakistan — a comprehensive agreement between a property owner and contractor governing the construction of a building or civil works project, compliant with the Contract Act 1872, and incorporating project scope, timelines, payment terms, and defect liability provisions applicable under Pakistani construction law.
Bid Bond (Pakistan)
A Bid Bond for Pakistan — a guarantee issued by a bidder or their bank to a procuring agency confirming the bidder's commitment to enter into a contract if selected, governed by the Contract Act 1872, the Public Procurement Regulatory Authority Rules 2004, and State Bank of Pakistan bank guarantee regulations.
Guarantee Agreement (Pakistan)
A Guarantee Agreement for Pakistan — a legally binding contract under the Contract Act 1872 whereby a guarantor undertakes to perform the obligation or discharge the liability of a principal debtor if the debtor fails to perform, governed by Sections 126 to 147 of the Contract Act 1872.
Indemnity Bond (Pakistan)
An Indemnity Bond for Pakistan — a unilateral instrument executed on stamp paper by which the obligor undertakes to indemnify a bank, government authority, or institution against loss arising from a specific act or event, governed by Sections 124-125 of the Contract Act 1872 and the Stamp Act 1899.
Advance Payment Guarantee (Pakistan)
An Advance Payment Guarantee for Pakistan — a bank or corporate guarantee securing repayment of an advance payment made to a contractor or supplier, governed by the Contract Act 1872 and State Bank of Pakistan banking regulations.