Bid Bond (Pakistan)
BID BOND / BID SECURITY
Under the Contract Act 1872 | Public Procurement Rules 2004 (PPRA)
1. PARTIES
BIDDER (Principal): [Bidder Name], [Bidder Address], NTN/CNIC: [Bidder NTN].
SURETY / ISSUING BANK: [Surety Name], [Surety Branch].
BENEFICIARY (Procuring Entity): [Procuring Entity].
2. PROCUREMENT REFERENCE
Tender Reference: [Tender Reference]
Description: [Procurement Description]
3. GUARANTEE
The Bidder and Surety, jointly and severally, hereby bind themselves to the Procuring Entity in the amount of [Bid Security Amount] (the 'Bid Security Amount') as bid security for the above procurement, in accordance with Rule 27 of the Public Procurement Rules 2004 and Sections 124–147 of the Contract Act 1872.
This Bond is valid from [Issue Date] to [Bond Expiry Date], covering the bid validity period of [Bid Validity Period].
4. CALLABLE EVENTS
The Procuring Entity may demand payment of the Bid Security Amount if the Bidder:
(a) withdraws or modifies its bid after the bid submission deadline and during the bid validity period;
(b) having been selected as successful bidder, fails to sign the contract within the period specified in the Letter of Acceptance; or
(c) fails to furnish the required performance security after contract award.
Payment shall be made within seven (7) banking days of a written demand from the Procuring Entity, without the Procuring Entity needing to prove the Bidder's default.
5. GOVERNING LAW AND JURISDICTION
This Bid Bond is governed by the laws of Pakistan, including the Contract Act 1872 and the Public Procurement Rules 2004. Disputes are subject to the jurisdiction of the courts at the location of the Procuring Entity.
Issued at __________ on [Issue Date].
For and on behalf of BIDDER:
Authorised Signatory: _________________________
Name / Title: _________________________
Company Seal: _________________________
For and on behalf of SURETY / ISSUING BANK:
[Surety Name], [Surety Branch]
Authorised Signatory 1: _________________________
Authorised Signatory 2: _________________________
Bank Seal: _________________________
Bidder (Principal)
________________
Signature
Surety / Issuing Bank
________________
Signature
What Is a Bid Bond (Pakistan)?
A Bid Bond in Pakistan binds the surety to answer for the obligation it guarantees if the principal fails to perform.
The Public Procurement Regulatory Authority (PPRA), established under the Public Procurement Regulatory Authority Ordinance 2002, regulates public procurement in Pakistan through the Public Procurement Rules 2004 (PPR 2004). Rule 27 of the PPR 2004 authorises procuring agencies to require bid security — the regulatory term for a bid bond — as a condition of bid submission. The standard bid security under PPR 2004 typically ranges from 1% to 5% of the estimated contract value, and may be submitted in the form of a pay order, demand draft, or bank guarantee issued by a scheduled bank. The PPRA Standard Bidding Documents (SBDs) published by PPRA contain prescribed formats for bid security that are widely adopted by federal and provincial government procuring agencies.
Provincial procurement frameworks mirror the federal structure. The Punjab Procurement Rules 2014 issued by the Punjab Finance Department under the Punjab Procurement Regulatory Authority Act 2009, the Sindh Public Procurement Rules 2010, the Khyber Pakhtunkhwa Public Procurement of Goods, Works and Services Act 2012, and the Balochistan Public Procurement Rules 2014 each contain equivalent bid security requirements, reflecting PPRA's model rules.
For private sector procurement, Bid Bonds are governed entirely by the Contract Act 1872. Sections 124 to 147 of the Contract Act 1872 govern contracts of guarantee, establishing that the surety's liability is co-extensive with the principal debtor's liability unless limited by the contract. A bank-issued Bid Bond constitutes an independent guarantee under Pakistani banking practice — the issuing bank's liability to pay on a valid call is primary and does not depend on establishing the bidder's underlying default.
The State Bank of Pakistan regulates bank guarantees issued by scheduled banks. SBP's Prudential Regulations and Foreign Exchange Manual govern the issuance of guarantees — particularly guarantees issued in foreign currency for international procurement under PPRA's alternative procurement modalities or World Bank-financed projects in Pakistan where the World Bank's Procurement Regulations for Borrowers apply alongside PPRA rules.
A Bid Bond in Pakistan is distinct from a Performance Bond (submitted after contract award as security for due performance) and from an Advance Payment Guarantee (issued when an advance mobilisation payment is made to the contractor). The Bid Bond secures the period between bid submission and contract signing — typically 60 to 180 days — and is returned to unsuccessful bidders after contract award and to the successful bidder upon submission of the performance security.
When Do You Need a Bid Bond (Pakistan)?
A Bid Bond in Pakistan is required in a wide range of public and private procurement situations involving competitive bidding.
A Bid Bond is required when a contractor, supplier, or service provider submits a bid for a government procurement contract under the Public Procurement Rules 2004. Federal ministries and departments, autonomous bodies, and state-owned enterprises regulated by the Ministry of Finance require bid security from all qualifying bidders. The National Highway Authority (NHA), the Water and Power Development Authority (WAPDA), the Pakistan Railways, the Civil Aviation Authority (CAA), and the Pakistan Public Works Department (PPWD) are among the major procuring agencies that consistently require bank-issued bid bonds for infrastructure and supply contracts.
A Bid Bond is needed when a contractor participates in provincial government tenders under the Punjab Procurement Rules 2014, Sindh Public Procurement Rules 2010, KPK Procurement Act 2012, or Balochistan Procurement Rules 2014. Provincial departments for roads, housing, irrigation, and health routinely require bid security in their standard bidding documents.
A Bid Bond is required when a supplier or contractor bids for World Bank, Asian Development Bank (ADB), or Asian Infrastructure Investment Bank (AIIB) financed projects in Pakistan. These multilateral development bank financed projects use their own Standard Bidding Documents which include a prescribed Bid Security Form that must be issued by a reputable bank and conform to the required text.
A Bid Bond is needed when a Pakistani company participates in an international tender for an overseas contract and the foreign procuring entity requires a bid bond from a Pakistani bank or from an international bank confirming through a counter-guarantee issued by a Pakistani scheduled bank.
A Bid Bond is required by large private sector companies — oil and gas companies such as Pakistan Petroleum Limited (PPL), Oil and Gas Development Company (OGDC), and Pakistan State Oil (PSO) — when conducting competitive procurement for exploration or supply contracts under their internal procurement policies modelled on PPRA rules.
A Bid Bond is needed when a construction company bids for private real estate development contracts where the developer requires bid security to confirm serious participation and deter non-serious bidders from tying up the procurement process.
What to Include in Your Bid Bond (Pakistan)
A valid Bid Bond in Pakistan under the Contract Act 1872 and the PPRA Rules 2004 must contain the following essential elements to be accepted by procuring entities and banks.
Parties: Full legal names and addresses of the bidder (principal), the issuing bank (surety) if bank-issued, and the procuring entity (beneficiary). For bank-issued bid bonds, the issuing bank's name, branch address, and SBP-assigned bank code must be stated.
Procurement Reference: The tender or bid reference number, date of issue of the bidding documents, and a description of the procurement — including the name of the project or goods being procured. This cross-reference is critical to limiting the guarantee to the specific procurement and preventing the bond from being called in relation to unrelated transactions.
Guarantee Amount: The amount of the bid security expressed in Pakistani Rupees (PKR) or, for international procurement, in the specified foreign currency. The amount must match the bid security requirement stated in the Instructions to Bidders section of the procuring entity's bidding documents — typically 1% to 5% of the estimated contract value.
Validity Period: The period during which the bid bond remains valid and callable — typically matching the bid validity period stated in the bidding documents, plus a safety margin of 28 to 30 days. The PPRA Standard Bidding Documents require bid bonds to remain valid at least 28 days beyond the bid validity period. After expiry, the bond is automatically discharged and the surety has no further liability.
Callable Events: A clear statement of the events that entitle the beneficiary to call the bond — typically: (a) the bidder withdraws or modifies its bid during the bid validity period contrary to the Instructions to Bidders; (b) the bidder, having been selected as the successful bidder, fails to sign the contract within the specified period; or (c) the bidder fails to furnish the required performance security after contract award. The callable events must be precisely drafted to avoid disputes — under the Contract Act 1872, the surety's liability is co-extensive with the terms of the guarantee.
Payment Terms: A statement that the surety will pay the guaranteed amount within a specified number of days — typically five to seven banking days — upon receipt of a written demand from the beneficiary, without the beneficiary needing to prove the bidder's default or initiate legal proceedings. Bank-issued bid bonds in Pakistan operate as demand guarantees — independent of the underlying contract dispute.
Governing Law and Jurisdiction: A statement that the bid bond is governed by the laws of Pakistan, including the Contract Act 1872, and that disputes are subject to the jurisdiction of the courts at the location of the procuring entity or the issuing bank.
Bank Seal and Authorised Signatories: For bank-issued bid bonds, the instrument must bear the official seal of the issuing bank and be signed by at least two authorised bank officials — typically the branch manager and a senior officer — whose signatures have been registered with the SBP and are verifiable by the beneficiary bank.
Forms-legal.com provides this Bid Bond (Pakistan) template as a starting point for corporate bidders preparing their own bid security instruments. Most procuring entities and banks have prescribed formats — bidders should confirm the required format with the procuring entity's bidding documents and obtain the bid bond from a scheduled bank licensed by the SBP, as bank-issued bonds carry greater commercial credibility than corporate-issued bid bonds.
Under the Companies Act 2017, the Securities and Exchange Commission of Pakistan (SECP) maintains the register of Pakistani companies. Section 16 of the Companies Act 2017 governs company incorporation. The Contract Act 1872 governs general contractual obligations. The Federal Board of Revenue (FBR) administers corporate tax under the Income Tax Ordinance 2001. The High Courts (Lahore, Sindh, Peshawar, Balochistan, Islamabad) have original and appellate jurisdiction.
Cite this page
Reference this free template in an article, syllabus, or research note:
Forms Legal. (2026). Bid Bond (Pakistan) (Pakistan) [Legal document template]. Forms Legal. https://forms-legal.com/pakistan/business/contracts/bid-bond-pakistan
"Bid Bond (Pakistan) (Pakistan)." Forms Legal, 2026, https://forms-legal.com/pakistan/business/contracts/bid-bond-pakistan.
@misc{formslegal-bid-bond-pakistan,
author = {{Forms Legal}},
title = {Bid Bond (Pakistan) (Pakistan)},
year = {2026},
howpublished = {\url{https://forms-legal.com/pakistan/business/contracts/bid-bond-pakistan}},
note = {Free legal document template}
}Also available for these jurisdictions:
Frequently Asked Questions
Under Rule 27 of the Public Procurement Rules 2004 (PPR 2004) issued by the Public Procurement Regulatory Authority (PPRA), the bid security (bid bond) for public procurement in Pakistan is typically set between 1% and 5% of the estimated contract value, as stated in the procuring agency's bidding documents. The exact percentage is determined by the procuring entity based on the nature of the procurement — construction and infrastructure contracts tend to require higher bid security (3% to 5%) than goods supply contracts (1% to 2%). The PPRA Standard Bidding Documents (SBDs) for works, goods, and services each contain a corresponding bid security requirement that procuring agencies may adapt within the PPRA-prescribed range. Provincial procurement frameworks — the Punjab Procurement Rules 2014, Sindh Public Procurement Rules 2010, KPK Procurement Act 2012, and Balochistan Procurement Rules 2014 — generally follow the same percentage range. For World Bank, ADB, and AIIB financed projects in Pakistan, the bid security percentage follows the relevant multilateral development bank's standard bidding document requirements, which may differ from PPRA's domestic framework.
A procuring agency in Pakistan may call (encash) a bid bond when the bidder commits any of the default events specified in the bid bond instrument — which typically align with the default events prescribed in the PPRA Standard Bidding Documents. The standard callable events are: first, the bidder withdraws or modifies their bid after the deadline for submission and during the bid validity period stated in the Instructions to Bidders — withdrawal before the deadline does not generally trigger the bid bond. Second, the bidder is selected as the successful bidder but fails to sign the contract within the period specified in the Letter of Acceptance — typically 28 days. Third, the successful bidder fails to submit the required performance security within the period specified after the Letter of Acceptance. In each case, the procuring entity must make a written demand on the bid bond before its expiry date. Under the Contract Act 1872, the surety (bank) is entitled to contest a call only if it can establish that the demand is fraudulent — not merely that the underlying facts are disputed. The PPRA's Procurement Policy Board has authority to review procurement disputes, including disputed bid bond calls, under PPRA's dispute resolution framework.
Yes. Under Rule 27 of the Public Procurement Rules 2004, bid security in Pakistan may be submitted in acceptable forms specified by the procuring entity, which typically include: a pay order issued by a scheduled bank in favour of the procuring agency; a demand draft drawn on a scheduled bank; a bank guarantee issued by a scheduled bank; or, for smaller contracts, cash deposited with the procuring agency's accounts office. The procuring entity specifies the acceptable forms of bid security in the Instructions to Bidders section of the bidding documents — not all forms are accepted for all procurement types. For high-value construction contracts — such as those tendered by the National Highway Authority (NHA) or WAPDA — a bank guarantee from a scheduled bank is typically the only acceptable form. For smaller goods procurement by district-level departments, a pay order or demand draft is usually acceptable. A personal cheque, property bond, or any security from a non-scheduled bank is generally not accepted under PPRA rules. The pay order or demand draft must be drawn in favour of the specific procuring agency and be valid for the full bid validity period plus the required margin.
After contract award in a PPRA-regulated procurement in Pakistan, the bid bond is treated as follows: For unsuccessful bidders, the bid bond is returned promptly — the PPRA Standard Bidding Documents require bid security to be returned to unsuccessful bidders within 28 days of the date of signing of the contract with the successful bidder, or after the bid validity period expires, whichever comes first. For the successful bidder, the bid bond is returned after the successful bidder: (a) signs the contract with the procuring agency; and (b) furnishes the required performance security — typically a bank guarantee for 5% to 10% of the contract value, as specified in the contract conditions. The return of the bid bond to the successful bidder is conditional on submission of the performance security — if the successful bidder fails to submit the performance security, the procuring agency is entitled to call the bid bond before returning it. For international competitive bidding under World Bank, ADB, or AIIB financed projects in Pakistan, the bid bond return timeline follows the specific multilateral development bank's standard bidding document requirements, which are generally aligned with PPRA's domestic framework but may have additional conditions.
No. A bid bond and a performance bond are distinct guarantee instruments used at different stages of the procurement cycle in Pakistan, though both are species of guarantee governed by Sections 124 to 147 of the Contract Act 1872. A bid bond — referred to as bid security under the PPRA Rules 2004 — is provided at the time of bid submission, before contract award. Its purpose is to guarantee that the bidder will not withdraw its bid during the bid validity period and will sign the contract and furnish performance security if selected. The bid bond amount is typically 1% to 5% of the estimated contract value and is valid only during the bid evaluation and award period. A performance bond — referred to as performance security under the PPRA Standard Bidding Documents — is submitted by the successful bidder after contract award, as a condition of contract commencement. Its purpose is to guarantee the contractor's due and faithful performance of the contract obligations. The performance bond amount is typically 5% to 10% of the contract price and remains valid until the defects liability period expires after practical completion of the works or delivery of goods. The two instruments are legally independent — encashment of the bid bond does not preclude separate recourse against the performance bond, and vice versa.
This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer
Found an error? Let us knowRelated Documents
You may also find these documents useful: