Skip to main content

Retention Money Bond (Pakistan)

Retention Money Bond (Pakistan)

RETENTION MONEY BOND

Bank Guarantee — Issued under the Contract Act 1872 (Sections 126–147) | Banking Companies Ordinance 1962

Bond No.: _________________________

Date of Issue: [Bond Date]

PRINCIPAL (CONTRACTOR):

[Contractor Name], SECP / CNIC: [Contractor SECP], NTN: [Contractor NTN]

Address: [Contractor Address]

GUARANTOR (BANK):

[Bank Name] — [Bank Branch]

Address: [Bank Address]

BENEFICIARY (EMPLOYER):

[Employer Name]

Address: [Employer Address]

RECITALS

A. By a construction contract titled '[Contract Title]', Contract No. [Contract Number], executed on [Contract Date] (the 'Construction Contract'), the Employer engaged the Contractor to carry out construction works at a contract price of PKR [Contract Value]/- (the 'Works').

B. Under the Construction Contract ([Contract Standard]), the Employer withholds [Retention Percentage] of each progress payment as retention money to secure the Contractor's defect rectification obligations during the Defects Liability Period.

C. The Contractor has requested the Employer to release the retention money ([Retention Moiety]) in exchange for this Retention Money Bond issued by the Bank on behalf of the Contractor.

D. In consideration of the Employer agreeing to release the said cash retention, the Bank hereby issues this Retention Money Bond in favour of the Employer on the following terms.

GUARANTEE UNDERTAKING

1. UNCONDITIONAL GUARANTEE: The Bank, [Bank Name] — [Bank Branch], hereby irrevocably and unconditionally undertakes to pay to the Employer, on first written demand, any sum or sums not exceeding in aggregate PKR [Bond Amount Figures]/- ([Bond Amount Words]) (the 'Bond Amount'), without proof or conditions and notwithstanding any objection by the Contractor, subject only to the Demand Conditions set out in Clause 3 below. This Bond is an on-demand guarantee under Sections 126–147 of the Contract Act 1872.

2. VALIDITY PERIOD: This Bond is valid from [Bond Validity Start] to [Bond Validity End] (inclusive). Any demand must be made and received by the Bank at the above address before the close of business on [Bond Validity End].

Defects Liability Period under the Construction Contract: [Defects Liability Period].

3. DEMAND CONDITIONS: To make a valid demand under this Bond, the Employer must submit to the Bank: [Demand Conditions]

4. PAYMENT: The Bank shall pay the demanded amount within five (5) banking days of receiving a valid demand, without requiring any further evidence of the Contractor's default or any prior recourse to the Contractor.

5. LIMIT OF LIABILITY: The Bank's total liability under this Bond shall not exceed PKR [Bond Amount Figures]/- ([Bond Amount Words]). This Bond shall reduce automatically upon each payment made hereunder by the amount so paid.

GENERAL TERMS

6. GOVERNING LAW: This Bond is governed by the laws of the Islamic Republic of Pakistan including the Contract Act 1872, the Banking Companies Ordinance 1962, and the State Bank of Pakistan's prudential regulations.

7. STAMP DUTY: Stamp duty under the Stamp Act 1899 applicable in [Stamp Duty Province] has been / shall be paid by the Contractor on this instrument. An unstamped bond is inadmissible under Section 35 of the Stamp Act 1899.

8. AUTHENTICITY: The Employer should verify the authenticity of this Bond directly with the issuing branch of [Bank Name] before releasing cash retention to the Contractor.

9. EXPIRY: This Bond shall automatically expire on [Bond Validity End] if no valid demand has been made. The Bank's obligations shall cease absolutely upon expiry.

IN WITNESS WHEREOF, the Bank has caused this Retention Money Bond to be executed by its duly authorised signatories on [Bond Date].

Bank Authorised Signatory 1

________________

Signature

Bank Authorised Signatory 2

________________

Signature

Contractor (Counter-Signed for Records)

________________

Signature

Maintained by Vladislav Sergienko, Founder·Template last modified: ·Report an error

What Is a Retention Money Bond (Pakistan)?

A Retention Money Bond in Pakistan binds the surety to answer for the obligation it guarantees if the principal fails to perform.

Under a standard construction contract in Pakistan governed by the Contract Act 1872, the employer withholds a percentage of each progress payment — typically 5% to 10% — as retention money (also called retention fund or security deposit). The purpose of cash retention is to create a financial incentive for the contractor to return and rectify defects discovered after practical completion of the works. The Retention Money Bond substitutes the bank's unconditional guarantee for the cash retention, enabling the contractor to recover their liquidity while the employer's security position remains intact.

The Contract Act 1872 (Act No. IX of 1872) governs the Retention Money Bond as a guarantee agreement between three parties: the contractor (principal), the bank (guarantor), and the employer (beneficiary). Sections 126 to 147 of the Contract Act 1872 govern contracts of guarantee — Section 126 defines a contract of guarantee as a contract to perform the promise or discharge the liability of a third person in case of their default. The Retention Money Bond is a demand guarantee — the employer may call upon it on demand, without first establishing that the contractor has defaulted, making it a stronger form of security than an ordinary suretyship.

Banks in Pakistan that issue Retention Money Bonds — including Habib Bank Limited (HBL), MCB Bank, United Bank Limited (UBL), Allied Bank, Bank Alfalah, and National Bank of Pakistan (NBP) — operate under the Banking Companies Ordinance 1962, the Financial Institutions (Recovery of Finances) Ordinance 2001, and the State Bank of Pakistan's prudential regulations. The bank assesses the contractor's creditworthiness before issuing the bond, and the contractor typically provides counter-security to the bank (cash collateral or a charge over assets).

Retention Money Bonds are widely used in Pakistan's public sector construction procurement — federal government projects procured under the Public Procurement Regulatory Authority (PPRA) Rules 2004, provincial government projects under provincial PPRA rules, and internationally funded projects (World Bank, Asian Development Bank, JICA) that specify FIDIC contract conditions. The FIDIC suite of contracts — the Red Book (construction works), the Yellow Book (plant and design-build), and the Silver Book (EPC/turnkey) — all contain provisions for retention money and the substitution of a retention money guarantee for cash retention.

The Pakistan Engineering Council (PEC) standard forms of contract, used for government engineering and construction projects in Pakistan, similarly provide for retention money and the substitution of a bank guarantee. The Retention Money Bond issued under these standard forms must comply with the bond format specified in the PEC standard conditions.

A Retention Money Bond in Pakistan operates within a broader legal framework that includes the Stamp Act 1899, which requires the bond instrument to be executed on appropriately stamped paper. Under Schedule I of the Stamp Act 1899, instruments of guarantee attract stamp duty at rates prescribed by the provincial government — typically in Punjab, Sindh, and Khyber Pakhtunkhwa. The Board of Revenue in each province administers stamp duty collection, and an unstamped or insufficiently stamped bond is inadmissible as evidence in court proceedings under Section 35 of the Stamp Act 1899.

The Securities and Exchange Commission of Pakistan (SECP) regulates contractor companies incorporated under the Companies Act 2017. Section 16 of the Companies Act 2017 governs company incorporation. Contractor companies issuing or receiving Retention Money Bonds must confirm their authorised signatories are properly designated by the board of directors, and that the company seal is affixed in accordance with the Companies Act 2017. The Federal Board of Revenue (FBR) administers withholding tax on construction contracts under Section 153 of the Income Tax Ordinance 2001, and the Retention Money Bond amount may influence the parties' tax withholding calculations.

The High Courts of Lahore, Sindh, Peshawar, Balochistan, and the Islamabad High Court have jurisdiction over disputes concerning Retention Money Bonds — including applications for injunctions restraining the employer from calling the bond, or applications for enforcement of the bond against the issuing bank. The Supreme Court of Pakistan is the final appellate authority. Courts apply the principle established in Edward Owen Engineering Ltd v Barclays Bank International [1978] (followed by Pakistani courts) that demand guarantees must be honoured on first demand absent fraud.

When Do You Need a Retention Money Bond (Pakistan)?

A Retention Money Bond in Pakistan is needed whenever a construction contractor wishes to recover cash retention withheld by an employer under a construction contract while ensuring the employer's security position for defect rectification is maintained.

A Retention Money Bond is required on government construction projects procured under the Public Procurement Regulatory Authority (PPRA) Rules 2004 — federal and provincial PPRA rules typically permit contractors to substitute a bank guarantee for cash retention held beyond the midpoint of the defects liability period. The contractor submits the bond to the employer's Ministry or department, and the employer releases the equivalent cash retention.

A Retention Money Bond is needed on large civil engineering and infrastructure projects — dams, roads, bridges, power plants, industrial plants — where the cumulative retention money held by the employer can amount to tens or hundreds of millions of Pakistani Rupees, creating significant cash flow pressure on the contractor throughout the project and defects liability period. Pakistan's National Highway Authority (NHA) procures major road projects where retention bonds are standard instruments.

A Retention Money Bond is required on internationally funded projects in Pakistan — World Bank-funded projects under the National Highway Authority (NHA), Asian Development Bank (ADB)-funded urban infrastructure projects, and JICA-funded development projects — where the contract conditions (typically FIDIC-based) specify that the contractor may substitute a retention guarantee for cash retention.

A Retention Money Bond is needed on private sector commercial construction projects — office towers, shopping malls, industrial facilities, housing schemes — where the employer insists on retention money as security for defects but the contractor's banker or surety company can provide an equivalent guarantee. Developers of large housing schemes in Lahore, Karachi, and Islamabad — particularly those regulated under provincial housing authority rules — routinely deal in retention bonds.

A Retention Money Bond is required when a subcontractor on a major construction project wishes to recover retention withheld by the main contractor. The main contractor-subcontractor relationship mirrors the employer-contractor relationship in terms of retention money mechanics, and the same bond mechanism can be applied at the subcontract level.

A Retention Money Bond is needed at the end of a defects liability period when the employer's release of the remaining retention is delayed or disputed — the bond provides the contractor with evidence that adequate security exists while they negotiate the final account settlement with the employer under the contract.

A Retention Money Bond is required when a contractor is working on a multi-phase construction project where different phases reach practical completion at different times, and the employer releases retention on a phase-by-phase basis. A separate retention bond for each phase — or a consolidated bond with reducing provisions — enables the contractor to recover retention progressively as each phase is completed and accepted by the employer.

A Retention Money Bond is needed in joint venture construction contracts — where two or more contractors form a joint venture (JV) to execute a government or private project — because each JV member's share of the retention security must be provided through their respective banks, and the Retention Money Bond mechanism allows each member to manage their own bank's exposure while the employer retains consolidated security from all JV members. The JV agreement should specify how the Retention Money Bond obligations are allocated among the JV members in proportion to their participation shares.

What to Include in Your Retention Money Bond (Pakistan)

A valid Retention Money Bond in Pakistan under the Contract Act 1872 and banking practice must contain the following essential elements to be effective as security for the employer and to enable the contractor to obtain release of cash retention.

Parties: The full legal names and addresses of the three parties to the bond — (1) the Principal (contractor — the entity whose performance obligation the bond secures), (2) the Guarantor (the issuing bank — a commercial bank regulated by the State Bank of Pakistan, such as HBL, MCB, UBL, Allied Bank, or NBP), and (3) the Beneficiary (the employer — the entity in whose favour the guarantee runs and who may call upon it). The SECP company registration numbers, NTN numbers from FBR, and bank account details should be included.

Construction Contract Reference: A clear reference to the underlying construction contract — contract title, contract number, date of execution, the works described, and the total contract price in Pakistani Rupees (PKR). The Retention Money Bond is a secondary instrument ancillary to the primary construction contract — its terms must align with the retention provisions of the construction contract.

Bond Amount: The maximum aggregate amount payable under the bond in Pakistani Rupees (PKR), stated in both figures and words — this amount must equal or exceed the total cash retention withheld and to be released by the employer in exchange for the bond. The bond amount typically corresponds to the total retention percentage (e.g., 5% of the contract price, or 10% of the contract price split between a first moiety released at practical completion and a second moiety held through the defects liability period).

Unconditional Demand Guarantee: The bank's unconditional and irrevocable commitment to pay the bond amount (or the portion demanded) to the employer on first written demand, without requiring proof of the contractor's default or any prior recourse to the contractor. The demand guarantee nature of the bond — as distinct from a conditional performance bond or a suretyship — must be clearly stated. An on-demand guarantee is more valuable to the employer because payment is not conditional on establishing a breach.

Validity Period: The period during which the bond remains in force and the employer may make a call on it — typically from the date of issue until the end of the defects liability period plus a buffer (e.g., 30 days after the expiry of the defects liability period). The validity period must be clearly stated with calendar dates.

Demand Requirements: The formal requirements that the employer must satisfy to make a valid call on the bond — typically a written demand signed by authorised signatories of the employer, stating the amount claimed and the reason for the call. Some bonds also require the employer's written certification that the contractor has failed to rectify defects within the specified notice period.

Reduction Mechanism: Where the bond covers both tranches of retention (first moiety and second moiety), the bond must provide for automatic or notified reduction of the bond amount as the first moiety is released or as work milestones are reached — this prevents the employer from calling the full bond amount after partial releases.

Governing Law and Jurisdiction: The Contract Act 1872 and the Banking Companies Ordinance 1962 as governing law; jurisdiction of the courts of the city where the project is located or the bank's branch city (Lahore, Karachi, Islamabad) for disputes about the validity or enforcement of the bond. The Arbitration Act 1940 may be referenced if the parties wish to resolve disputes through arbitration rather than litigation.

Bank's Liability Limitations: The bank's liability is limited to the bond amount — the bank is not responsible for disputes about the quality of the works, defects, or contractual breaches between the employer and contractor. The bank pays on demand and leaves it to the contractor to recover from the employer if the demand was fraudulent or unfounded.

Counter-Indemnity Reference: A reference to the counter-indemnity or counter-security provided by the contractor to the bank (though the counter-security arrangements between the contractor and bank are a separate agreement not disclosed to the employer).

Stamp Duty Compliance: Under Section 3 of the Stamp Act 1899, the bond instrument must be stamped at the rate applicable in the relevant province. In Punjab, the Board of Revenue prescribes the stamp duty schedule. An unstamped bond is inadmissible as evidence under Section 35 of the Stamp Act 1899. The parties should confirm the applicable stamp duty rate with a licensed stamp vendor before execution.

Authentication: The bond must be signed by authorised bank signatories — typically two signatories from the issuing bank — and bear the bank's official stamp. The employer should verify the authenticity of the bond directly with the issuing bank before releasing cash retention under the construction contract.

PPRA Compliance: For bonds issued in connection with federal government projects under the PPRA Rules 2004, the bank must be a scheduled bank listed by the State Bank of Pakistan, and the bond format must conform to the standard format prescribed in the government's standard bidding documents. Non-conforming bonds may be rejected by the procuring agency's procurement committee.

Forms-legal.com provides this Retention Money Bond (Pakistan) template as a reference framework. Banks issuing retention money bonds will typically use their own standard bond format, which should be reviewed and accepted by the employer's legal counsel before being substituted for cash retention under the construction contract. Contractors and employers dealing with bonds of significant value should engage an Advocate experienced in banking and construction law, enrolled at the relevant provincial Bar Council.

Cite this page

Reference this free template in an article, syllabus, or research note:

APA

Forms Legal. (2026). Retention Money Bond (Pakistan) (Pakistan) [Legal document template]. Forms Legal. https://forms-legal.com/pakistan/business/construction/retention-money-bond-pakistan

MLA

"Retention Money Bond (Pakistan) (Pakistan)." Forms Legal, 2026, https://forms-legal.com/pakistan/business/construction/retention-money-bond-pakistan.

BibTeX
@misc{formslegal-retention-money-bond-pakistan,
  author       = {{Forms Legal}},
  title        = {Retention Money Bond (Pakistan) (Pakistan)},
  year         = {2026},
  howpublished = {\url{https://forms-legal.com/pakistan/business/construction/retention-money-bond-pakistan}},
  note         = {Free legal document template}
}

Frequently Asked Questions

Statute-referenced template — Template last modified June 2026

This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer

Found an error? Let us know

Related Documents

You may also find these documents useful:

Renovation Contract (Pakistan)

A Renovation Contract for Pakistan — a binding agreement between a property owner and a contractor for renovation, refurbishment, or remodelling works, governed by the Contract Act 1872 and the Building Control Authority regulations of the relevant province.

Construction Contract (Pakistan)

A Construction Contract for Pakistan — a comprehensive agreement between a property owner and contractor governing the construction of a building or civil works project, compliant with the Contract Act 1872, and incorporating project scope, timelines, payment terms, and defect liability provisions applicable under Pakistani construction law.

Bid Bond (Pakistan)

A Bid Bond for Pakistan — a guarantee issued by a bidder or their bank to a procuring agency confirming the bidder's commitment to enter into a contract if selected, governed by the Contract Act 1872, the Public Procurement Regulatory Authority Rules 2004, and State Bank of Pakistan bank guarantee regulations.

Bank Guarantee Application (Pakistan)

A Bank Guarantee Application for Pakistan — a formal request by a customer to their bank for the issuance of a bank guarantee in favour of a beneficiary, governed by the Contract Act 1872 and State Bank of Pakistan regulations, detailing the guarantee type, amount, purpose, and security offered.

Indemnity Bond (Pakistan)

An Indemnity Bond for Pakistan — a unilateral instrument executed on stamp paper by which the obligor undertakes to indemnify a bank, government authority, or institution against loss arising from a specific act or event, governed by Sections 124-125 of the Contract Act 1872 and the Stamp Act 1899.