CONTRATO DE INTERVENTORÍA

Celebrado conforme a la Ley 1474 de 2011 (Art. 83), Ley 400 de 1997 y Ley 80 de 1993

PRIMERA. — PARTES CONTRATANTES

EL CONTRATANTE:

Nombre / Razón Social: [Owner Name]

NIT / C.C.: [Owner NIT]

Domicilio: [Owner Address]

Representante Legal: [Owner Representative]

C.C. del Representante: [Owner Rep CC]

EL INTERVENTOR:

Nombre / Razón Social: [Interventor Name]

NIT / C.C.: [Interventor NIT]

Domicilio: [Interventor Address]

Representante Legal / Director: [Interventor Representative]

C.C. del Representante: [Interventor Rep CC]

Matrícula Profesional (COPNIA/CPNAA): [Interventor Matrícula]

Entre las partes arriba identificadas, quienes en adelante se denominarán EL CONTRATANTE y EL INTERVENTOR, respectivamente, se celebra el presente Contrato de Interventoría, regido por la Ley 1474 de 2011 (Artículo 83), la Ley 400 de 1997, la Ley 80 de 1993, el Decreto 926 de 2010 (NSR-10), y demás normas aplicables de la República de Colombia.

SEGUNDA. — CONTRATO DE OBRA SUPERVISADO

EL INTERVENTOR ejercerá la supervisión del siguiente contrato de obra:

Contratista de Obra: [Constructor Name]

Contrato de Obra No.: [Construction Contract No.]

Valor del Contrato de Obra: [Construction Contract Value]

Descripción del Proyecto: [Project Description]

Ubicación: [Project Address]

Licencia de Construcción No.: [License Number]

EL INTERVENTOR declara no tener vínculo contractual, societario ni de subordinación con el contratista de obra, conforme a la exigencia de independencia del Artículo 26 de la Ley 400 de 1997.

TERCERA. — OBJETO Y ALCANCE DE LA INTERVENTORÍA

EL INTERVENTOR se obliga a realizar la supervisión [Supervision Type] del proyecto de construcción descrito en la cláusula segunda, verificando el cumplimiento de los planos aprobados, las especificaciones técnicas, las Normas Colombianas de Diseño y Construcción Sismo Resistente (NSR-10 — Decreto 926 de 2010), y las obligaciones contractuales del contratista de obra.

Dedicación: [Supervision Schedule]

El alcance comprende: a) Verificación técnica del cumplimiento de NSR-10 en diseño estructural, materiales y procedimientos constructivos; b) Control de calidad de materiales mediante ensayos de laboratorio según normas NTC; c) Revisión y certificación de actas de obra para pagos parciales; d) Verificación del cumplimiento del cronograma de obra; e) Control del cumplimiento de las obligaciones laborales y de seguridad social del contratista; f) Verificación de la implementación del SG-SST conforme al Decreto 1072 de 2015; g) Elaboración de informes periódicos de interventoría; h) Mantenimiento de la bitácora de obra según NSR-10 Título I.

CUARTA. — EQUIPO DE INTERVENTORÍA

Director de Interventoría: [Director Name]

Residente de Interventoría: [Resident Name]

Cada profesional del equipo de interventoría debe contar con matrícula profesional vigente expedida por COPNIA (Ley 842 de 2003) o CPNAA (Ley 435 de 1998) según su disciplina. EL INTERVENTOR no podrá sustituir al personal clave sin autorización previa y escrita de EL CONTRATANTE, debiendo el reemplazo cumplir con calificaciones iguales o superiores.

QUINTA. — HONORARIOS Y FORMA DE PAGO

Honorarios Totales de Interventoría: [Interventoría Fee]

Equivalente a: [Fee Percentage]

Periodicidad de Pago: [Payment Frequency], previa presentación de informe de interventoría y factura o cuenta de cobro.

Retención en Garantía: [Retention %] de cada factura, que será liberada una vez se entregue el informe final de interventoría y el Acta de Recibo de Obra.

Los pagos se realizarán dentro de los quince (15) días hábiles siguientes a la radicación de la factura con el informe de interventoría aprobado por EL CONTRATANTE.

SEXTA. — PLAZO DEL CONTRATO

Fecha de Inicio: [Start Date]

Fecha de Terminación: [End Date]

El plazo del contrato de interventoría cubrirá la totalidad de la fase de ejecución de la obra más el período de liquidación del contrato de obra, conforme al Artículo 2.2.1.2.1.5.3 del Decreto 1082 de 2015. Las prórrogas derivadas de extensiones del contrato de obra se formalizarán mediante otrosí al presente contrato.

SÉPTIMA. — OBLIGACIONES DEL INTERVENTOR

EL INTERVENTOR se obliga a:

a) Verificar que la obra se ejecute conforme a los planos aprobados, las especificaciones técnicas y las normas NSR-10 (Decreto 926 de 2010).

b) Mantener la bitácora de obra actualizada con registros diarios de actividades, observaciones e instrucciones al constructor.

c) Certificar las actas de obra (cortes de obra) para autorizar los pagos parciales al contratista de obra.

d) Presentar informes mensuales de interventoría con avance físico, financiero, fotográfico y de cumplimiento normativo.

e) Verificar el cumplimiento de las obligaciones laborales y de seguridad social del contratista conforme a la Ley 100 de 1993 y el CST.

f) Verificar la implementación del SG-SST en el sitio de obra conforme al Decreto 1072 de 2015 y la Resolución 0312 de 2019.

g) Ordenar la suspensión de actividades cuando se identifiquen condiciones que comprometan la seguridad estructural o la integridad de los trabajadores.

h) Coordinar los ensayos de laboratorio de materiales según las normas NTC aplicables.

i) Participar en la suscripción del Acta de Inicio, Actas de Recibo Parcial y el Acta de Recibo de Obra.

OCTAVA. — OBLIGACIONES DEL CONTRATANTE

EL CONTRATANTE se obliga a:

a) Suministrar al INTERVENTOR copia completa del contrato de obra, los planos aprobados, los estudios técnicos y la Licencia de Construcción.

b) Facilitar el acceso del equipo de interventoría al sitio de obra en todo momento.

c) Realizar los pagos de honorarios conforme a los plazos y condiciones establecidos en la cláusula quinta.

d) Atender oportunamente las recomendaciones y alertas emitidas por EL INTERVENTOR.

NOVENA. — RESPONSABILIDAD PROFESIONAL

EL INTERVENTOR responderá civil, disciplinaria y penalmente por los daños derivados de la supervisión negligente o deficiente conforme al Artículo 52 de la Ley 400 de 1997, el Artículo 2341 del Código Civil y el régimen disciplinario de la Ley 842 de 2003. EL INTERVENTOR deberá constituir una póliza de responsabilidad civil profesional que cubra errores y omisiones en el ejercicio de la interventoría.

PARÁGRAFO. — La responsabilidad del INTERVENTOR no excluye ni sustituye la responsabilidad del contratista de obra por la correcta ejecución de los trabajos ni la garantía decenal de estabilidad establecida en el Artículo 51 de la Ley 400 de 1997.

DÉCIMA. — LEY APLICABLE Y RESOLUCIÓN DE CONTROVERSIAS

El presente contrato se rige por la Ley 1474 de 2011, la Ley 400 de 1997, la Ley 80 de 1993, el Decreto 926 de 2010 (NSR-10), la Ley 842 de 2003, la Ley 435 de 1998, y el Código Civil de Colombia. Las controversias serán resueltas por los Juzgados Civiles del Circuito competentes del lugar de ubicación del proyecto, previa conciliación ante un centro de conciliación autorizado conforme a la Ley 640 de 2001.

FIRMAS

En [Contract City], a los [Contract Date].

EL CONTRATANTE:

[Owner Name]

NIT / C.C.: [Owner NIT]

Representante Legal: [Owner Representative]

C.C.: [Owner Rep CC]

Firma: _________________________

EL INTERVENTOR:

[Interventor Name]

NIT / C.C.: [Interventor NIT]

Representante Legal: [Interventor Representative]

C.C.: [Interventor Rep CC]

Matrícula Profesional: [Interventor Matrícula]

Firma: _________________________

Contracting Party / Property Owner (Contratante)

________________

Signature

Interventor / Supervisor (Interventor)

________________

Signature

Maintained by Vladislav Sergienko, Founder·Template last modified: ·Report an error

What Is a Construction Supervision Contract Colombia (Contrato de Interventoría)?

A Construction Supervision Contract Colombia (Contrato de Interventoría) is a professional services agreement governed by Ley 1474 de 2011 Article 83 and Ley 80 de 1993 Article 32, through which a property owner or contracting entity engages an independent professional or firm (interventor) to perform technical, administrative, financial, and legal supervision of a construction project. The interventor acts as the owner's representative on the construction site, verifying that the contractor (contratista) executes the work in accordance with approved plans, specifications, applicable construction standards, and contractual obligations.

Ley 400 de 1997 Article 18 establishes the mandatory requirement for professional supervision (supervisión técnica) of all structural construction projects in Colombia. The supervisión técnica must be performed by a licensed professional engineer or architect who is independent from the constructor — the same professional or firm cannot act as both constructor and supervisor on the same project under Article 26 of Ley 400 de 1997. The supervisor must hold a valid matrícula profesional issued by the Consejo Profesional Nacional de Ingeniería (COPNIA) under Ley 842 de 2003 or by the Consejo Profesional Nacional de Arquitectura y sus Profesiones Auxiliares (CPNAA) under Ley 435 de 1998.

For public construction contracts, Ley 1474 de 2011 (Estatuto Anticorrupción) Article 83 strengthened the interventoría framework by requiring that all State construction contracts above the menor cuantía threshold have mandatory external interventoría. Article 83 defines interventoría as the technical supervision and control exercised by a natural or juridical person contracted for that purpose, distinguishing it from the internal supervisión that State entities may exercise through their own personnel. Ley 80 de 1993 Article 32 numeral 2 classifies the contrato de interventoría as a separate contract type within the framework of State contracting.

The Decreto Único Reglamentario del Sector de Planeación Nacional — Decreto 1082 de 2015 — consolidates the regulatory framework for interventoría in public contracts, establishing requirements for the selection process, professional qualifications, contract duration, and reporting obligations. Article 2.2.1.2.1.5.3 of Decreto 1082 de 2015 requires that the interventoría contract term must extend for the duration of the construction contract plus the liquidation period.

In private construction projects, the interventoría obligation derives from Ley 400 de 1997 and the Reglamento Colombiano de Construcción Sismo Resistente (NSR-10), adopted through Decreto 926 de 2010. NSR-10 Título I establishes the supervisión técnica requirements, mandating that the supervisor verify compliance with structural design, materials quality, construction procedures, and geotechnical recommendations throughout the construction process. The supervisor must maintain a bitácora de obra (construction logbook) recording daily observations, instructions to the constructor, and any deviations from approved plans.

The interventor bears professional liability under multiple Colombian statutes. Ley 400 de 1997 Article 52 establishes civil and criminal liability for professionals who certify non-compliant structures. Ley 842 de 2003 Articles 30 through 35 establish the disciplinary regime for engineers, with sanctions ranging from written reprimand (amonestación) to cancellation of the matrícula profesional for serious professional misconduct. Under Código Civil Article 2341, the interventor is liable for damages caused by negligent supervision — the Corte Suprema de Justicia Sala de Casación Civil has held that supervisors who fail to identify and report construction defects bear joint liability with the constructor.

The Ministerio de Vivienda, Ciudad y Territorio (MVCT) oversees the implementation of construction standards through the Comisión Asesora Permanente para el Régimen de Construcciones Sismo Resistentes established by Ley 400 de 1997 Article 39. The Curadurías Urbanas verify that construction projects comply with NSR-10 and the applicable Plan de Ordenamiento Territorial (POT) during the licensing phase, while the interventor verifies compliance during the execution phase.

Under Ley 1796 de 2016 (Ley de Vivienda Segura), residential construction projects require the constructor to obtain a póliza decenal de estabilidad — a ten-year structural warranty insurance policy. The interventor's compliance certifications during construction directly affect the insurer's risk assessment and willingness to maintain coverage. Insurance companies supervised by the Superintendencia Financiera de Colombia may deny claims or seek subrogation against the interventor who certified non-compliant work, reinforcing the practical importance of a well-defined interventoría contract.

Disputes arising from interventoría contracts in the private sector are resolved by the Juzgados Civiles del Circuito, with appeals to the Sala Civil of the Tribunal Superior de Distrito Judicial. For public interventoría contracts, the Jurisdicción de lo Contencioso Administrativo — specifically the Juzgados Administrativos and the Sección Tercera of the Consejo de Estado — has exclusive jurisdiction under the Código de Procedimiento Administrativo y de lo Contencioso Administrativo (Ley 1437 de 2011).

When Do You Need a Construction Supervision Contract Colombia (Contrato de Interventoría)?

A Construction Supervision Contract Colombia is required whenever a construction project in Colombian territory needs independent professional oversight to verify compliance with approved plans, technical standards, and contractual obligations. Ley 400 de 1997 Article 18 mandates supervisión técnica for all structural construction projects, and Ley 1474 de 2011 Article 83 requires formal interventoría for all public construction contracts exceeding the menor cuantía threshold.

A Contrato de Interventoría is needed when a property owner (propietario) or developer (promotor inmobiliario) commissions a construction project and requires an independent professional to supervise the contractor's work, verify construction quality, certify progress payments, and protect the owner's technical and financial interests. Under Ley 400 de 1997 Article 26, the interventor must be a different professional or firm from the constructor — this independence requirement is a fundamental principle of Colombian construction law designed to prevent conflicts of interest.

The contract is required for residential construction projects where units will be sold to end buyers under the régimen de propiedad horizontal established by Ley 675 de 2001. Ley 1796 de 2016 (Ley de Vivienda Segura) strengthened buyer protection by requiring constructors to obtain the póliza decenal de estabilidad (ten-year structural warranty insurance), and the interventor's compliance certification is a prerequisite for the insurance company's risk assessment.

A Contrato de Interventoría is needed when construction financing requires independent progress verification. Colombian financial institutions supervised by the Superintendencia Financiera de Colombia typically require interventoría reports as a condition for disbursing construction loan tranches (desembolsos). The interventor certifies the percentage of physical progress (avance físico) and financial progress (avance financiero) before each disbursement.

The contract is required for projects involving complex technical systems where specialized supervision is needed — structural reinforcement (reforzamiento estructural under NSR-10 Título A.10), seismic retrofitting, deep foundations, or specialized installations governed by RETIE (Reglamento Técnico de Instalaciones Eléctricas) or RAS 2000 (Reglamento de Agua Potable y Saneamiento Básico). The interventor must have specific expertise in the relevant technical discipline.

A written interventoría contract formalizes the scope, duration, fees, and liability allocation before the Acta de Inicio de Obra is signed. Under Decreto 1082 de 2015, the interventoría contract must be in place before construction begins, and the interventor must participate in the pre-construction meeting (reunión de preconstrucción) where the construction schedule, quality control procedures, and communication protocols are established.

A Contrato de Interventoría is needed when the construction project involves environmental management obligations under Ley 99 de 1993. Projects with a Licencia Ambiental issued by the Autoridad Nacional de Licencias Ambientales (ANLA) or the regional Corporación Autónoma Regional (CAR) require the interventor to verify compliance with the Plan de Manejo Ambiental — monitoring waste disposal, noise levels, dust control, water resource protection, and reforestation commitments throughout the construction phase.

The contract is also required for projects under the régimen de propiedad horizontal (Ley 675 de 2001) where constructed units will be sold to individual buyers. The interventor's certification of construction quality and regulatory compliance supports the developer's obligations under Ley 1796 de 2016 (Ley de Vivienda Segura) and the consumer protection framework of Ley 1480 de 2011. Financial institutions, homebuyer associations (asociaciones de compradores), and the Superintendencia de Industria y Comercio (SIC) may require access to the interventor's reports as evidence of construction compliance in claims related to structural defects or construction quality deficiencies.

What to Include in Your Construction Supervision Contract Colombia (Contrato de Interventoría)

A valid Construction Supervision Contract Colombia under Ley 1474 de 2011 Article 83 and Ley 400 de 1997 must contain the following elements to define the scope of supervision, allocate professional liability, and meet the technical oversight requirements of Colombian construction law.

Identification of Parties: Full legal name, cédula de ciudadanía or NIT (Número de Identificación Tributaria assigned by the DIAN), and domicile of both the contratante (property owner or contracting entity) and the interventor (supervisor). The interventor must provide proof of valid matrícula profesional issued by COPNIA (for engineers under Ley 842 de 2003) or CPNAA (for architects under Ley 435 de 1998). Where the interventor is a firm (persona jurídica), the NIT, Cámara de Comercio registration, and credentials of the director de interventoría and key technical staff must be included.

Reference to the Construction Contract: Identification of the construction contract being supervised, including the constructor's identity, the contract number, date, scope, value, and duration. Under Ley 400 de 1997 Article 26, the interventor must be independent from the constructor — the contract should contain an explicit declaration of no conflict of interest. The interventoría contract duration must cover the construction period plus the liquidation period per Decreto 1082 de 2015 Article 2.2.1.2.1.5.3.

Scope of Supervision: Detailed description of the interventor's technical, administrative, financial, and legal supervision responsibilities. Technical supervision under NSR-10 Título I (Decreto 926 de 2010) includes verification of structural compliance, materials testing per NTC standards (NTC 673 for concrete, NTC 2289 for steel), geotechnical monitoring, and construction procedure oversight. Administrative supervision covers schedule monitoring, workforce verification, and permit compliance. Financial supervision includes verification of quantities, unit prices, progress billing, and advance payment amortization.

Project Identification: Reference to the construction project including the Licencia de Construcción number issued by the Curaduría Urbana under Ley 388 de 1997, the project address, matrícula inmobiliaria, and applicable NSR-10 seismic zone classification. The interventor's supervision scope must align with the parameters authorized in the construction license.

Intervention Team: Identification of the key professionals who will perform the supervision, their matrícula profesional numbers, and their specific roles — director de interventoría, residente de interventoría, and specialized reviewers (structural, electrical, plumbing, geotechnical). Under Ley 842 de 2003 Article 12, each professional performing engineering functions must hold individual professional credentials.

Supervision Fee and Payment: The total interventoría fee in Colombian Pesos (COP), typically calculated as a percentage of the construction contract value — standard market rates range from 3% to 8% depending on project complexity. Payment is usually structured in monthly instalments tied to the construction duration, with retention provisions similar to the construction contract.

Reporting Obligations: The interventor must submit periodic supervision reports (informes de interventoría) — typically monthly — documenting construction progress, quality observations, non-conformities, contractor compliance, and recommendations. The report format should include photographic records, laboratory test results, progress measurements, and financial tracking. Under Ley 400 de 1997 Article 18, the supervisor must maintain a bitácora de obra recording all site observations and instructions.

Certification Authority: The interventor's authority to approve or reject work, certify progress payments through actas de obra (work certificates), issue instructions to the constructor through the bitácora de obra, and recommend suspension of work when safety or quality concerns arise. The interventor certifies the Acta de Recibo Parcial de Obra for progress payments and the Acta de Recibo de Obra for final acceptance.

Professional Liability: Clear allocation of the interventor's liability under Ley 400 de 1997 Article 52, CC Article 2341, and the disciplinary regime of Ley 842 de 2003. The interventor must carry a póliza de responsabilidad civil profesional (professional liability insurance) covering errors and omissions in the supervision process. The contract should specify liability limits and the relationship to the constructor's ten-year structural warranty under Ley 400 de 1997 Article 51.

Governing Law and Jurisdiction: Statement that the contract is governed by Ley 1474 de 2011, Ley 400 de 1997, Decreto 926 de 2010 (NSR-10), Ley 842 de 2003, and the Código Civil. Private interventoría disputes are resolved by the Juzgados Civiles del Circuito; public interventoría disputes by the Jurisdicción de lo Contencioso Administrativo under Ley 1437 de 2011.

Forms-legal.com provides this Construction Supervision Contract Colombia template as a starting point for formalizing the interventoría relationship. Every interventoría contract should be reviewed by a licensed abogado with experience in derecho de la construcción to confirm compliance with the applicable project's technical requirements, the Licencia de Construcción conditions, and the professional liability framework established by COPNIA and CPNAA.

Cite this page

Reference this free template in an article, syllabus, or research note:

APA

Forms Legal. (2026). Construction Supervision Contract Colombia (Contrato de Interventoría) (Colombia) [Legal document template]. Forms Legal. https://forms-legal.com/colombia/business/construction/construction-supervision-contract-colombia

MLA

"Construction Supervision Contract Colombia (Contrato de Interventoría) (Colombia)." Forms Legal, 2026, https://forms-legal.com/colombia/business/construction/construction-supervision-contract-colombia.

BibTeX
@misc{formslegal-construction-supervision-contract-colombia,
  author       = {{Forms Legal}},
  title        = {Construction Supervision Contract Colombia (Contrato de Interventoría) (Colombia)},
  year         = {2026},
  howpublished = {\url{https://forms-legal.com/colombia/business/construction/construction-supervision-contract-colombia}},
  note         = {Free legal document template}
}

Also available for these jurisdictions:

Frequently Asked Questions

Statute-referenced template — Template last modified June 2026

This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer

Found an error? Let us know

Related Documents

You may also find these documents useful:

Contrato de Obra de Construcción Colombia

Contrato de Obra de Construcción para Colombia conforme al Artículo 1602 del Código Civil y la Ley 400 de 1997, que establece las condiciones para la ejecución de obras civiles, incluyendo alcance, cronograma, materiales, hitos de pago, garantías y cumplimiento de las normas NSR-10 y la Licencia de Construcción.

Contrato de Diseño Arquitectónico Colombia

Contrato de Diseño Arquitectónico para Colombia regido por la Ley 435 de 1998 y el Código Civil artículo 1602, que establece los términos para servicios profesionales de diseño arquitectónico, incluyendo diseño esquemático, planos detallados, documentos de construcción, radicación ante la Curaduría Urbana y cumplimiento del NSR-10 y el POT.

Acta de Inicio de Obra Colombia

Acta de Inicio de Obra para Colombia conforme a la Ley 400 de 1997 y el Decreto 1077 de 2015, que documenta formalmente el inicio de un proyecto de construccion con identificacion del contratista, datos de la licencia de construccion, condiciones del sitio, plazo de ejecucion y cumplimiento de la Norma Sismo Resistente NSR-10.

Acta de Recibo Final de Obra Colombia

Acta de Recibo Final de Obra para Colombia conforme a la Ley 400 de 1997 y el Articulo 2060 del Codigo Civil, que documenta formalmente la aceptacion final de un proyecto de construccion terminado por el propietario o la entidad contratante, certificando el cumplimiento de los diseños aprobados, la Norma NSR-10 y las especificaciones contractuales.

Acta de Recibo Parcial de Obra Colombia

Acta de Recibo Parcial de Obra para Colombia conforme a la Ley 400 de 1997 y el Código Civil Artículo 2060, que documenta formalmente la aceptación de una fase o hito de construcción completado, autoriza pagos parciales y registra el porcentaje de ejecución del contrato frente al cronograma de construcción aprobado.