Skip to main content

Snagging & Defects Liability Agreement (UAE)

Snagging & Defects Liability Agreement (UAE)

SNAGGING AND DEFECTS LIABILITY AGREEMENT

Dated: [Agreement Date]

EMPLOYER: [Employer Name], of [Employer Address] (the "Employer");

CONTRACTOR: [Contractor Name] (Trade Licence: [Contractor Licence]), of [Contractor Address] (the "Contractor").

THE EMPLOYER AND THE CONTRACTOR HAVE AGREED AS FOLLOWS:

1. BACKGROUND AND GOVERNING LAW

1.1 Project: [Project Name]. Main Contract Reference: [Main Contract Ref]. Taking-Over Certificate issued: [Taking-Over Date].

1.2 Following Taking-Over, the Employer and the Contractor conducted a joint snagging inspection and identified the defects and outstanding items listed in Schedule 1 (the "Snagging Items").

1.3 This Agreement records the parties' obligations for rectifying the Snagging Items and the consequences of failure to do so within the agreed period.

1.4 This Agreement is governed by the laws of the United Arab Emirates, in particular the UAE Civil Code (Federal Law No. 5 of 1985). Article 880 of the UAE Civil Code imposes non-excludable ten-year decennial liability on the Contractor for structural collapse or defects threatening structural stability, independently of this Agreement. The Commercial Transactions Law (Federal Decree-Law No. 50 of 2022) applies to commercial obligations between merchant parties.

2. SNAGGING ITEMS AND RECTIFICATION OBLIGATION

2.1 Snagging Items: [Snag List Description].

2.2 The Contractor shall rectify all Snagging Items in Schedule 1 within [Rectification Period].

2.3 The Contractor shall carry out all rectification works: (a) in a good and workmanlike manner, using materials matching the specification in the Main Contract; (b) without causing damage to other parts of the Works or the Employer's property; (c) at times reasonably requested by the Employer and with reasonable notice to occupants; (d) at no additional cost to the Employer, these being defects within the Contractor's obligations under the Main Contract and the UAE Civil Code (Federal Law No. 5 of 1985).

2.4 Joint sign-off inspection shall take place on [Snag Inspection Date]. The Employer and Contractor shall attend the sign-off inspection together. Items signed off as complete shall be deleted from Schedule 1.

3. RETENTION AND FINANCIAL CONSEQUENCES

3.1 The Employer currently withholds retention of [Retention Amount]. Retention shall be released upon: [Retention Release Conditions].

3.2 If the Contractor fails to rectify any Snagging Item within the Rectification Period, the following consequences apply: [Penalty For Delay].

3.3 All costs properly incurred by the Employer in engaging a third-party contractor to complete unrectified snagging items shall be deducted from the Retention Amount. Any shortfall shall be recoverable from the Contractor under Articles 282 and 389 of the UAE Civil Code (Federal Law No. 5 of 1985).

3.4 VAT at 5% under Federal Decree-Law No. 8 of 2017 applies to any additional payment made by the Employer for third-party rectification works. The third-party contractor's tax invoice must bear its Tax Registration Number (TRN) issued by the Federal Tax Authority (FTA).

4. DECENNIAL LIABILITY

4.1 Nothing in this Agreement limits or excludes the Contractor's non-excludable ten-year decennial liability under Art. 880 of the UAE Civil Code (Federal Law No. 5 of 1985) for total or partial collapse of the Works or for defects threatening the structural safety or stability of the structure. This Agreement governs non-structural snagging items only.

4.2 Any Snagging Item that, in the opinion of a qualified structural engineer, affects the structural safety or stability of the Works shall be treated as a matter of decennial liability under Art. 880, not merely as a Snagging Item under this Agreement, and shall be escalated to the Employer's structural engineer and the Engineer immediately for assessment.

5. DISPUTE RESOLUTION

5.1 The parties shall attempt to resolve any dispute by negotiation within 14 days of written notice. If unresolved, either party may refer the dispute to [Dispute Forum].

5.2 This Agreement is governed by the laws of the United Arab Emirates.

6. GENERAL

6.1 Schedule 1 (Snag List) is incorporated into and forms part of this Agreement.

6.2 This Agreement supplements the Main Contract and does not supersede or waive any right or obligation under the Main Contract.

6.3 Completion of all Snagging Items to the Employer's reasonable satisfaction is a condition precedent to the issue of the Performance Certificate under the Main Contract.

6.4 Electronic notices and communications are valid under the Electronic Transactions and Trust Services Law (Federal Decree-Law No. 46 of 2021).

SIGNED for and on behalf of the EMPLOYER: [Employer Name]

SIGNED for and on behalf of the CONTRACTOR: [Contractor Name]

Employer

________________

Signature

Contractor

________________

Signature

Maintained by Vladislav Sergienko, Founder·Template last modified: ·Report an error

What Is a Snagging & Defects Liability Agreement (UAE)?

A Snagging and Defects Liability Agreement in the United Arab Emirates is a formal document executed between an Employer and a Contractor at or after the issue of a Taking-Over Certificate (or practical completion certificate), recording the minor defects, incomplete items, and cosmetic imperfections identified during a joint inspection of the completed building — collectively known as the 'snagging list' — and setting out the Contractor's obligation to rectify those items within a defined period. The agreement is governed by the UAE Civil Code (Federal Law No. 5 of 1985), under which the Contractor's obligation to remedy defects during the Defects Liability Period (DLP) is a statutory and contractual duty under Arts 872-896 on muqawala (construction contracts), and Art. 880 imposes a separate, non-excludable ten-year decennial liability for structural defects threatening the safety of the building.

In UAE construction practice, the Taking-Over Certificate marks the point at which the Employer accepts that the Works are substantially complete and begins the DLP, typically 12 months. At Taking-Over, a snagging inspection is conducted jointly by the Employer's representative — the Client's project manager, the Engineer under a FIDIC-style contract, or a specialist snagging consultant — and the Contractor, resulting in a numbered snag list attaching to this Agreement as a Schedule. The snag list records each item with a unique reference, a location description, a defect description, and a priority classification. The Contractor is required to rectify all listed items within the rectification period stated in this Agreement, failing which the Employer may engage a third-party contractor and recover the cost from the retention withheld under the main contract.

Snagging is a critical stage in the UAE property handover process. The Dubai Land Department (DLD), RERA (Real Estate Regulatory Agency), and the Abu Dhabi Real Estate Centre (ADREC) all regulate the handover of residential properties to purchasers and require developers to address snagging complaints. The FIDIC-style main construction contract — whether Red Book (Design-Bid-Build) or Silver Book (EPC/Turnkey) — provides the framework for DLP obligations, but a standalone Snagging and Defects Liability Agreement provides clarity and enforceability for the specific items outstanding at Taking-Over, preventing the snagging process from devolving into an informal and unenforceable series of site meetings and email exchanges. The forms-legal.com UAE template provides a structured, legally sound framework for documenting and managing the snagging process across all types of UAE construction projects.

When Do You Need a Snagging & Defects Liability Agreement (UAE)?

A Snagging and Defects Liability Agreement in the United Arab Emirates is needed whenever a construction project reaches practical completion and a joint inspection identifies outstanding defects or incomplete works that must be rectified before the Contractor receives full payment and the final Performance Certificate.

Residential villa and apartment projects in Dubai, Abu Dhabi, and the Northern Emirates require a documented snagging process as part of the handover procedure required by the Dubai Land Department, RERA, and the Abu Dhabi Real Estate Centre. Off-plan purchasers are entitled to a snagging inspection before accepting the keys, and the developer's or contractor's obligations to rectify defects must be formally documented to be enforceable.

Commercial office towers, hotels, and mixed-use developments require a snagging agreement where the Employer's facilities management team or incoming tenant's fit-out contractor will take over the building and needs a clear record of which outstanding items the Contractor is responsible for, so that new defects arising during the fit-out period are not incorrectly attributed to the base-build contractor.

Government and infrastructure projects procured by Abu Dhabi government entities, the Abu Dhabi Department of Municipalities and Transport, and Dubai government departments require formal snagging documentation as part of their asset handover procedures. Without a signed snag list, the government asset register cannot accurately record the condition of the building at handover, and departmental auditors may flag incomplete handover procedures.

Project finance transactions require the bank or financier supervised by the Central Bank of the UAE to verify that the construction project has been handed over in a satisfactory condition before releasing the final construction loan drawdown. The snagging agreement and the retention release mechanism provide the lender with evidence that the Employer has accepted the Works subject only to documented minor defects, enabling the final drawdown to proceed.

Insurance renewals — particularly for the contractor's all-risks (CAR) policy transitioning to a building property insurance policy at Taking-Over — also require evidence of the handover condition, which the snagging agreement provides.

What to Include in Your Snagging & Defects Liability Agreement (UAE)

A UAE Snagging and Defects Liability Agreement that is enforceable before the Dubai Courts, the Abu Dhabi Judicial Department, and DIAC arbitration panels must contain the following key elements. The forms-legal.com UAE template addresses each component in a commercially sound and legally compliant structure.

Party identification requires the full legal name, trade licence number, and address of both the Employer and the Contractor. The Employer's representative who conducted the snagging inspection should be identified, as this person may need to give evidence in any dispute about the condition of the Works at Taking-Over.

Project and main contract reference must identify the construction project by name and address, the main contract under which the Works were executed, and the date of the Taking-Over Certificate. This contextualises the snagging agreement within the main contract framework and confirms which DLP period governs the rectification obligation.

The Snagging List (Schedule 1) is the core of the document and must number each item sequentially, describe its location (floor and room reference), describe the defect, assign a priority classification (critical/standard/cosmetic), and state the agreed rectification deadline for each priority category. Photographs should be attached to the schedule to prevent later disputes about the condition of items at the time of inspection.

Rectification period must state the overall deadline for all items and the shorter deadline for critical items. The period typically starts from the date of this Agreement and runs in parallel with the Defects Liability Period under the main contract.

Joint inspection date for sign-off should be specified so that both parties are required to attend a formal review at a fixed date, preventing indefinite delays in signing off completed items.

Retention amount and release conditions must state the AED amount withheld and the precise conditions — satisfactory completion of all snagging items and issue of the Performance Certificate — that trigger release.

Third-party remedy rights must allow the Employer to engage a substitute contractor after notice and deduct costs from retention, consistent with Arts 282 and 389 of the UAE Civil Code (Federal Law No. 5 of 1985).

Decennial liability preservation clause must confirm that this Agreement does not limit Art. 880 rights for structural defects, and that structural items identified during snagging are escalated separately.

How to Fill Out Your Snagging & Defects Liability Agreement (UAE)

Completing a UAE Snagging and Defects Liability Agreement requires preparation of a detailed Snag List Schedule before execution, and careful review of the main contract's DLP and retention provisions.

Begin with the parties section. Enter the Employer's full legal name and address. For the Contractor, enter the full legal name, trade licence number from the relevant Department of Economic Development, and registered address. Confirm the identities of the representatives who conducted the snagging inspection, as their authority to bind their respective parties should be confirmed.

In the project and main contract section, enter the project name and full site address. Reference the main contract precisely — including the date and any contract reference number — and enter the date of the Taking-Over Certificate in DD/MM/YYYY format.

The Snagging Items section is the most important. Reference the Snag List Schedule (Schedule 1) clearly. The Schedule itself (which you prepare separately) should number each item, state the location, describe the defect, and classify it as critical, standard, or cosmetic. Attach photographs. In this template field, describe the Snag List generally — 'Schedule 1 comprising XX items as detailed therein' — and note the total number of items, any critical items requiring urgent attention, and any items that affect regulatory compliance (Civil Defence NOC, DEWA connection).

Enter the rectification period in clear terms: the overall deadline for all items, and the shorter deadline for critical items. Enter the joint sign-off inspection date in DD/MM/YYYY format — set this date at the end of the rectification period to allow time for completion.

Enter the retention amount in AED (e.g., the second half of retention under the main contract) and describe the conditions for release — completion of all snag items plus Performance Certificate.

In the financial consequence field, state the cost-recovery mechanism: the right to engage a third-party contractor after 14 days' written notice and deduct costs from retention. Specify a per-item financial consequence if useful.

Select the dispute resolution forum matching the project's emirate. Both parties sign through authorised representatives. Electronic signatures are valid under the Electronic Transactions and Trust Services Law (Federal Decree-Law No. 46 of 2021).

Common Mistakes to Avoid in Your Snagging & Defects Liability Agreement (UAE)

Snagging and defects liability management in the United Arab Emirates frequently suffers from documentation failures that lead to protracted disputes before the Dubai Courts and DIAC arbitration panels. The following mistakes recur across the construction and property sector.

1. No photographic evidence at inspection. A snag list without photographs is difficult to enforce. Contractors regularly dispute whether a snagging item existed at Taking-Over or arose subsequently through the Employer's use. Photographs with timestamps, taken jointly at the snagging inspection, provide the evidential record needed to support or defend a claim before the Dubai Courts.

2. Structural items mis-classified as snagging. Cracks that appear cosmetic may be indicative of structural movement within Art. 880 of the UAE Civil Code (Federal Law No. 5 of 1985). Snagging agreements that categorise structural-looking defects as cosmetic snagging items may inadvertently assist a Contractor in arguing that the Employer accepted the structural condition at Taking-Over. Any crack or defect with structural implications should be assessed by a structural engineer before being classified.

3. No time limits for individual items. A snagging agreement that gives the Contractor 60 days for all items, without prioritising critical items affecting safety or habitability, allows life-safety defects — fire system gaps, electrical faults, HVAC failures in UAE summer heat — to remain unremedied for the full period. Critical items must have a separate, shorter deadline of 7-14 days.

4. No joint sign-off procedure. Without a contractual requirement for both parties to attend a joint sign-off inspection at a fixed date, the Contractor may complete some items informally and claim they are done, while the Employer disputes completion. A fixed joint inspection date with a sign-off sheet removes this ambiguity.

5. Releasing retention before Performance Certificate. Releasing full retention on the basis of an informal email exchange rather than waiting for the formal Performance Certificate from the Engineer leaves the Employer without financial leverage for any defects discovered in the final weeks of the DLP.

6. Not preserving Art. 880 decennial rights. Snagging agreements that purport to constitute a full and final settlement of all defects may inadvertently waive structural claims. Every UAE snagging agreement must expressly preserve the Employer's Art. 880 rights for the full ten-year period.

Cite this page

Reference this free template in an article, syllabus, or research note:

APA

Forms Legal. (2026). Snagging & Defects Liability Agreement (UAE) (United Arab Emirates) [Legal document template]. Forms Legal. https://forms-legal.com/uae/business/contracts/snagging-defects-liability-agreement-uae

MLA

"Snagging & Defects Liability Agreement (UAE) (United Arab Emirates)." Forms Legal, 2026, https://forms-legal.com/uae/business/contracts/snagging-defects-liability-agreement-uae.

BibTeX
@misc{formslegal-snagging-defects-liability-agreement-uae,
  author       = {{Forms Legal}},
  title        = {Snagging & Defects Liability Agreement (UAE) (United Arab Emirates)},
  year         = {2026},
  howpublished = {\url{https://forms-legal.com/uae/business/contracts/snagging-defects-liability-agreement-uae}},
  note         = {Free legal document template. Based on UAE Civil Code (Federal Law No. 5 of 1985), Arts 872-896 (muqawala) and Art. 880 (decennial liability)}
}

Frequently Asked Questions

Based on UAE Civil Code (Federal Law No. 5 of 1985), Arts 872-896 (muqawala) and Art. 880 (decennial liability) — Template last modified June 2026

This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer

Found an error? Let us know

Related Documents

You may also find these documents useful:

Construction Contract (FIDIC-Style) (UAE)

A FIDIC-style lump-sum construction contract for UAE projects, incorporating muqawala provisions under Arts 872-896 of the UAE Civil Code (Federal Law No. 5 of 1985), Art. 880 decennial liability, VAT under Federal Decree-Law No. 8 of 2017, and DIAC arbitration. Covers Employer, Contractor, Engineer, performance security, defects, and variations.

Completion Certificate (Construction) (UAE)

A UAE Taking-Over / Completion Certificate issued by the Engineer under a FIDIC-style or bespoke construction contract, certifying practical completion, commencing the Defects Notification Period, triggering first-half retention release, and recording regulatory approvals (Dubai Municipality, Civil Defence, DEWA/ADDC). Governed by the UAE Civil Code (Federal Law No. 5 of 1985) Arts 872-896 and Art. 880.

Variation Order (Construction) (UAE)

A UAE construction Variation Order (VO) instructed by the Engineer under Art. 887 of the UAE Civil Code (Federal Law No. 5 of 1985) for lump-sum contract changes, recording scope, valuation (Bill of Quantities rates or Engineer's determination), Extension of Time, adjusted Contract Price, and VAT under Federal Decree-Law No. 8 of 2017.

Construction Subcontract (UAE)

A back-to-back construction subcontract for UAE projects, flowing down obligations from the main contract under the UAE Civil Code (Federal Law No. 5 of 1985), Arts 872-896 muqawala. Covers scope, payment, retention, delay damages, decennial liability under Art. 880, and dispute resolution through DIAC or UAE courts.

MEP Works Contract (UAE)

A UAE MEP works contract for mechanical, electrical, and plumbing installation projects, covering design (where applicable), supply, testing, commissioning, and handover. Governed by the UAE Civil Code (Federal Law No. 5 of 1985) Arts 872-896, with Art. 880 decennial liability, DEWA/ADDC commissioning requirements, UAE Civil Defence NOC, and VAT under Federal Decree-Law No. 8 of 2017.