Snagging & Defects Liability Agreement (UAE)
SNAGGING AND DEFECTS LIABILITY AGREEMENT
Dated: [Agreement Date]
EMPLOYER: [Employer Name], of [Employer Address] (the "Employer");
CONTRACTOR: [Contractor Name] (Trade Licence: [Contractor Licence]), of [Contractor Address] (the "Contractor").
THE EMPLOYER AND THE CONTRACTOR HAVE AGREED AS FOLLOWS:
1. BACKGROUND AND GOVERNING LAW
1.1 Project: [Project Name]. Main Contract Reference: [Main Contract Ref]. Taking-Over Certificate issued: [Taking-Over Date].
1.2 Following Taking-Over, the Employer and the Contractor conducted a joint snagging inspection and identified the defects and outstanding items listed in Schedule 1 (the "Snagging Items").
1.3 This Agreement records the parties' obligations for rectifying the Snagging Items and the consequences of failure to do so within the agreed period.
1.4 This Agreement is governed by the laws of the United Arab Emirates, in particular the UAE Civil Code (Federal Law No. 5 of 1985). Article 880 of the UAE Civil Code imposes non-excludable ten-year decennial liability on the Contractor for structural collapse or defects threatening structural stability, independently of this Agreement. The Commercial Transactions Law (Federal Decree-Law No. 50 of 2022) applies to commercial obligations between merchant parties.
2. SNAGGING ITEMS AND RECTIFICATION OBLIGATION
2.1 Snagging Items: [Snag List Description].
2.2 The Contractor shall rectify all Snagging Items in Schedule 1 within [Rectification Period].
2.3 The Contractor shall carry out all rectification works: (a) in a good and workmanlike manner, using materials matching the specification in the Main Contract; (b) without causing damage to other parts of the Works or the Employer's property; (c) at times reasonably requested by the Employer and with reasonable notice to occupants; (d) at no additional cost to the Employer, these being defects within the Contractor's obligations under the Main Contract and the UAE Civil Code (Federal Law No. 5 of 1985).
2.4 Joint sign-off inspection shall take place on [Snag Inspection Date]. The Employer and Contractor shall attend the sign-off inspection together. Items signed off as complete shall be deleted from Schedule 1.
3. RETENTION AND FINANCIAL CONSEQUENCES
3.1 The Employer currently withholds retention of [Retention Amount]. Retention shall be released upon: [Retention Release Conditions].
3.2 If the Contractor fails to rectify any Snagging Item within the Rectification Period, the following consequences apply: [Penalty For Delay].
3.3 All costs properly incurred by the Employer in engaging a third-party contractor to complete unrectified snagging items shall be deducted from the Retention Amount. Any shortfall shall be recoverable from the Contractor under Articles 282 and 389 of the UAE Civil Code (Federal Law No. 5 of 1985).
3.4 VAT at 5% under Federal Decree-Law No. 8 of 2017 applies to any additional payment made by the Employer for third-party rectification works. The third-party contractor's tax invoice must bear its Tax Registration Number (TRN) issued by the Federal Tax Authority (FTA).
4. DECENNIAL LIABILITY
4.1 Nothing in this Agreement limits or excludes the Contractor's non-excludable ten-year decennial liability under Art. 880 of the UAE Civil Code (Federal Law No. 5 of 1985) for total or partial collapse of the Works or for defects threatening the structural safety or stability of the structure. This Agreement governs non-structural snagging items only.
4.2 Any Snagging Item that, in the opinion of a qualified structural engineer, affects the structural safety or stability of the Works shall be treated as a matter of decennial liability under Art. 880, not merely as a Snagging Item under this Agreement, and shall be escalated to the Employer's structural engineer and the Engineer immediately for assessment.
5. DISPUTE RESOLUTION
5.1 The parties shall attempt to resolve any dispute by negotiation within 14 days of written notice. If unresolved, either party may refer the dispute to [Dispute Forum].
5.2 This Agreement is governed by the laws of the United Arab Emirates.
6. GENERAL
6.1 Schedule 1 (Snag List) is incorporated into and forms part of this Agreement.
6.2 This Agreement supplements the Main Contract and does not supersede or waive any right or obligation under the Main Contract.
6.3 Completion of all Snagging Items to the Employer's reasonable satisfaction is a condition precedent to the issue of the Performance Certificate under the Main Contract.
6.4 Electronic notices and communications are valid under the Electronic Transactions and Trust Services Law (Federal Decree-Law No. 46 of 2021).
SIGNED for and on behalf of the EMPLOYER: [Employer Name]
SIGNED for and on behalf of the CONTRACTOR: [Contractor Name]
Employer
________________
Signature
Contractor
________________
Signature
What Is a Snagging & Defects Liability Agreement (UAE)?
A Snagging and Defects Liability Agreement in the United Arab Emirates is a formal document executed between an Employer and a Contractor at or after the issue of a Taking-Over Certificate (or practical completion certificate), recording the minor defects, incomplete items, and cosmetic imperfections identified during a joint inspection of the completed building — collectively known as the 'snagging list' — and setting out the Contractor's obligation to rectify those items within a defined period. The agreement is governed by the UAE Civil Code (Federal Law No. 5 of 1985), under which the Contractor's obligation to remedy defects during the Defects Liability Period (DLP) is a statutory and contractual duty under Arts 872-896 on muqawala (construction contracts), and Art. 880 imposes a separate, non-excludable ten-year decennial liability for structural defects threatening the safety of the building.
In UAE construction practice, the Taking-Over Certificate marks the point at which the Employer accepts that the Works are substantially complete and begins the DLP, typically 12 months. At Taking-Over, a snagging inspection is conducted jointly by the Employer's representative — the Client's project manager, the Engineer under a FIDIC-style contract, or a specialist snagging consultant — and the Contractor, resulting in a numbered snag list attaching to this Agreement as a Schedule. The snag list records each item with a unique reference, a location description, a defect description, and a priority classification. The Contractor is required to rectify all listed items within the rectification period stated in this Agreement, failing which the Employer may engage a third-party contractor and recover the cost from the retention withheld under the main contract.
Snagging is a critical stage in the UAE property handover process. The Dubai Land Department (DLD), RERA (Real Estate Regulatory Agency), and the Abu Dhabi Real Estate Centre (ADREC) all regulate the handover of residential properties to purchasers and require developers to address snagging complaints. The FIDIC-style main construction contract — whether Red Book (Design-Bid-Build) or Silver Book (EPC/Turnkey) — provides the framework for DLP obligations, but a standalone Snagging and Defects Liability Agreement provides clarity and enforceability for the specific items outstanding at Taking-Over, preventing the snagging process from devolving into an informal and unenforceable series of site meetings and email exchanges. The forms-legal.com UAE template provides a structured, legally sound framework for documenting and managing the snagging process across all types of UAE construction projects.
When Do You Need a Snagging & Defects Liability Agreement (UAE)?
A Snagging and Defects Liability Agreement in the United Arab Emirates is needed whenever a construction project reaches practical completion and a joint inspection identifies outstanding defects or incomplete works that must be rectified before the Contractor receives full payment and the final Performance Certificate.
Residential villa and apartment projects in Dubai, Abu Dhabi, and the Northern Emirates require a documented snagging process as part of the handover procedure required by the Dubai Land Department, RERA, and the Abu Dhabi Real Estate Centre. Off-plan purchasers are entitled to a snagging inspection before accepting the keys, and the developer's or contractor's obligations to rectify defects must be formally documented to be enforceable.
Commercial office towers, hotels, and mixed-use developments require a snagging agreement where the Employer's facilities management team or incoming tenant's fit-out contractor will take over the building and needs a clear record of which outstanding items the Contractor is responsible for, so that new defects arising during the fit-out period are not incorrectly attributed to the base-build contractor.
Government and infrastructure projects procured by Abu Dhabi government entities, the Abu Dhabi Department of Municipalities and Transport, and Dubai government departments require formal snagging documentation as part of their asset handover procedures. Without a signed snag list, the government asset register cannot accurately record the condition of the building at handover, and departmental auditors may flag incomplete handover procedures.
Project finance transactions require the bank or financier supervised by the Central Bank of the UAE to verify that the construction project has been handed over in a satisfactory condition before releasing the final construction loan drawdown. The snagging agreement and the retention release mechanism provide the lender with evidence that the Employer has accepted the Works subject only to documented minor defects, enabling the final drawdown to proceed.
Insurance renewals — particularly for the contractor's all-risks (CAR) policy transitioning to a building property insurance policy at Taking-Over — also require evidence of the handover condition, which the snagging agreement provides.
What to Include in Your Snagging & Defects Liability Agreement (UAE)
A UAE Snagging and Defects Liability Agreement that is enforceable before the Dubai Courts, the Abu Dhabi Judicial Department, and DIAC arbitration panels must contain the following key elements. The forms-legal.com UAE template addresses each component in a commercially sound and legally compliant structure.
Party identification requires the full legal name, trade licence number, and address of both the Employer and the Contractor. The Employer's representative who conducted the snagging inspection should be identified, as this person may need to give evidence in any dispute about the condition of the Works at Taking-Over.
Project and main contract reference must identify the construction project by name and address, the main contract under which the Works were executed, and the date of the Taking-Over Certificate. This contextualises the snagging agreement within the main contract framework and confirms which DLP period governs the rectification obligation.
The Snagging List (Schedule 1) is the core of the document and must number each item sequentially, describe its location (floor and room reference), describe the defect, assign a priority classification (critical/standard/cosmetic), and state the agreed rectification deadline for each priority category. Photographs should be attached to the schedule to prevent later disputes about the condition of items at the time of inspection.
Rectification period must state the overall deadline for all items and the shorter deadline for critical items. The period typically starts from the date of this Agreement and runs in parallel with the Defects Liability Period under the main contract.
Joint inspection date for sign-off should be specified so that both parties are required to attend a formal review at a fixed date, preventing indefinite delays in signing off completed items.
Retention amount and release conditions must state the AED amount withheld and the precise conditions — satisfactory completion of all snagging items and issue of the Performance Certificate — that trigger release.
Third-party remedy rights must allow the Employer to engage a substitute contractor after notice and deduct costs from retention, consistent with Arts 282 and 389 of the UAE Civil Code (Federal Law No. 5 of 1985).
Decennial liability preservation clause must confirm that this Agreement does not limit Art. 880 rights for structural defects, and that structural items identified during snagging are escalated separately.
How to Fill Out Your Snagging & Defects Liability Agreement (UAE)
Completing a UAE Snagging and Defects Liability Agreement requires preparation of a detailed Snag List Schedule before execution, and careful review of the main contract's DLP and retention provisions.
Begin with the parties section. Enter the Employer's full legal name and address. For the Contractor, enter the full legal name, trade licence number from the relevant Department of Economic Development, and registered address. Confirm the identities of the representatives who conducted the snagging inspection, as their authority to bind their respective parties should be confirmed.
In the project and main contract section, enter the project name and full site address. Reference the main contract precisely — including the date and any contract reference number — and enter the date of the Taking-Over Certificate in DD/MM/YYYY format.
The Snagging Items section is the most important. Reference the Snag List Schedule (Schedule 1) clearly. The Schedule itself (which you prepare separately) should number each item, state the location, describe the defect, and classify it as critical, standard, or cosmetic. Attach photographs. In this template field, describe the Snag List generally — 'Schedule 1 comprising XX items as detailed therein' — and note the total number of items, any critical items requiring urgent attention, and any items that affect regulatory compliance (Civil Defence NOC, DEWA connection).
Enter the rectification period in clear terms: the overall deadline for all items, and the shorter deadline for critical items. Enter the joint sign-off inspection date in DD/MM/YYYY format — set this date at the end of the rectification period to allow time for completion.
Enter the retention amount in AED (e.g., the second half of retention under the main contract) and describe the conditions for release — completion of all snag items plus Performance Certificate.
In the financial consequence field, state the cost-recovery mechanism: the right to engage a third-party contractor after 14 days' written notice and deduct costs from retention. Specify a per-item financial consequence if useful.
Select the dispute resolution forum matching the project's emirate. Both parties sign through authorised representatives. Electronic signatures are valid under the Electronic Transactions and Trust Services Law (Federal Decree-Law No. 46 of 2021).
Legal Requirements for Snagging & Defects Liability Agreement (UAE)
A Snagging and Defects Liability Agreement in the United Arab Emirates is subject to the following statutory framework.
The UAE Civil Code (Federal Law No. 5 of 1985) is the primary source. Articles 872-896 govern muqawala contracts, including the Contractor's obligations during the DLP. Article 880 imposes mandatory ten-year decennial liability for structural collapse or defects threatening structural safety — this cannot be excluded or limited by the snagging agreement. Article 246 requires good faith performance of the rectification obligation. Article 247 provides the exception of non-performance, permitting the Employer to withhold retention for unremedied snags. Articles 282 and 389 provide the basis for compensation claims for third-party rectification costs. Article 390 governs liquidated damages for delay in rectification.
The Commercial Transactions Law (Federal Decree-Law No. 50 of 2022) applies to commercial obligations between merchant parties, governing late-payment interest under Art. 76 at the Central Bank of the UAE rate.
The Commercial Companies Law (Federal Decree-Law No. 32 of 2021) requires each signatory to hold authority to bind the entity.
Federal Decree-Law No. 8 of 2017 on VAT requires 5% VAT on any third-party rectification services procured by the Employer and deducted from retention.
Property-specific regulations: Dubai Law No. 13 of 2008 (as amended) and RERA regulations govern off-plan property handover and the developer's snagging obligations to purchasers. Abu Dhabi Real Estate Centre (ADREC) regulations apply to Abu Dhabi off-plan properties.
The Federal Arbitration Law (Federal Law No. 6 of 2018) governs arbitration clauses. The Electronic Transactions and Trust Services Law (Federal Decree-Law No. 46 of 2021) validates electronic communications and digital snag-list platforms.
Common Mistakes to Avoid in Your Snagging & Defects Liability Agreement (UAE)
Snagging and defects liability management in the United Arab Emirates frequently suffers from documentation failures that lead to protracted disputes before the Dubai Courts and DIAC arbitration panels. The following mistakes recur across the construction and property sector.
1. No photographic evidence at inspection. A snag list without photographs is difficult to enforce. Contractors regularly dispute whether a snagging item existed at Taking-Over or arose subsequently through the Employer's use. Photographs with timestamps, taken jointly at the snagging inspection, provide the evidential record needed to support or defend a claim before the Dubai Courts.
2. Structural items mis-classified as snagging. Cracks that appear cosmetic may be indicative of structural movement within Art. 880 of the UAE Civil Code (Federal Law No. 5 of 1985). Snagging agreements that categorise structural-looking defects as cosmetic snagging items may inadvertently assist a Contractor in arguing that the Employer accepted the structural condition at Taking-Over. Any crack or defect with structural implications should be assessed by a structural engineer before being classified.
3. No time limits for individual items. A snagging agreement that gives the Contractor 60 days for all items, without prioritising critical items affecting safety or habitability, allows life-safety defects — fire system gaps, electrical faults, HVAC failures in UAE summer heat — to remain unremedied for the full period. Critical items must have a separate, shorter deadline of 7-14 days.
4. No joint sign-off procedure. Without a contractual requirement for both parties to attend a joint sign-off inspection at a fixed date, the Contractor may complete some items informally and claim they are done, while the Employer disputes completion. A fixed joint inspection date with a sign-off sheet removes this ambiguity.
5. Releasing retention before Performance Certificate. Releasing full retention on the basis of an informal email exchange rather than waiting for the formal Performance Certificate from the Engineer leaves the Employer without financial leverage for any defects discovered in the final weeks of the DLP.
6. Not preserving Art. 880 decennial rights. Snagging agreements that purport to constitute a full and final settlement of all defects may inadvertently waive structural claims. Every UAE snagging agreement must expressly preserve the Employer's Art. 880 rights for the full ten-year period.
Cite this page
Reference this free template in an article, syllabus, or research note:
Forms Legal. (2026). Snagging & Defects Liability Agreement (UAE) (United Arab Emirates) [Legal document template]. Forms Legal. https://forms-legal.com/uae/business/contracts/snagging-defects-liability-agreement-uae
"Snagging & Defects Liability Agreement (UAE) (United Arab Emirates)." Forms Legal, 2026, https://forms-legal.com/uae/business/contracts/snagging-defects-liability-agreement-uae.
@misc{formslegal-snagging-defects-liability-agreement-uae,
author = {{Forms Legal}},
title = {Snagging & Defects Liability Agreement (UAE) (United Arab Emirates)},
year = {2026},
howpublished = {\url{https://forms-legal.com/uae/business/contracts/snagging-defects-liability-agreement-uae}},
note = {Free legal document template. Based on UAE Civil Code (Federal Law No. 5 of 1985), Arts 872-896 (muqawala) and Art. 880 (decennial liability)}
}Frequently Asked Questions
A snagging list in United Arab Emirates construction practice is a register of minor defects, outstanding works, and incomplete finishes identified during a joint inspection by the Employer (or the Employer's representative) and the Contractor at or shortly after practical completion — typically coinciding with the Taking-Over Certificate under FIDIC-style contracts or the equivalent handover milestone in other contract forms.
Common snagging items on UAE residential and commercial projects include: paint finish blemishes or colour inconsistencies; tiling gaps or lippage; door and window alignment or sealing issues; fitting and fixture installation defects; HVAC grille positioning; minor electrical switch and socket plate misalignments; and plumbing leak-test failures.
The snagging list is typically prepared jointly by the Employer's technical representative — the Client's project manager, the Employer's Representative under FIDIC, or a specialist snagging consultant — and the Contractor's site manager. Each item is assigned a unique reference number, a location description (floor, room, or grid reference), a brief description of the defect, and a priority classification (critical, standard, or cosmetic). Critical items — affecting safety, weatherproofing, or habitability — are given a shorter rectification deadline than cosmetic items.
In the UAE, snagging inspections are commonly required as part of the handover process by the Dubai Land Department (DLD) for residential properties sold under the Jointly Owned Property Law (Law No. 27 of 2007), and by the Abu Dhabi Real Estate Centre (ADREC) for Abu Dhabi residential developments. Property developers registered with the Real Estate Regulatory Agency (RERA) must address snagging complaints from purchasers within defined timelines under the RERA developer regulations.
Snagging and decennial liability are distinct legal concepts in the United Arab Emirates that operate at different scales and over different time periods.
Snagging refers to minor defects, incomplete works, and cosmetic imperfections identified at or shortly after practical completion of the building. Snagging items are typically non-structural: paint blemishes, tiling gaps, door alignment issues, and fixture installation defects. The Contractor's obligation to rectify snagging items runs during the Defects Liability Period (DLP) — typically 12 months from Taking-Over — and is a contractual obligation under the main contract and this Snagging and Defects Liability Agreement.
Decennial liability under Art. 880 of the UAE Civil Code (Federal Law No. 5 of 1985) is a statutory, non-contractual obligation that applies to structural defects — total or partial collapse of the completed building, or defects threatening the structural safety or stability of the structure. Decennial liability lasts for ten years from the date of handover and applies regardless of whether the main contract has expired, whether the DLP has ended, or whether the snagging process is complete. It cannot be excluded or limited by contract.
The practical difference is significant: a cracked tile is a snagging item, remedied under the DLP; a cracking foundation or a collapsing balcony is a decennial liability issue, giving rise to statutory claims against the Contractor and the structural Engineer/Architect for the full ten years from handover. The Employer has three years from the date it discovers a structural defect to bring a claim under Art. 883 of the UAE Civil Code.
This Snagging and Defects Liability Agreement expressly preserves the Employer's Art. 880 rights and does not limit them, ensuring that completion of the snagging process does not inadvertently waive the Employer's statutory decennial liability claims.
An Employer in the United Arab Emirates is generally entitled to withhold retention under the construction contract until the conditions for retention release are satisfied, which typically include completion of snagging items and issue of the Performance Certificate. However, the Employer must exercise this right in good faith under Art. 246 of the UAE Civil Code (Federal Law No. 5 of 1985) and cannot use the snagging process as a pretext to withhold retention for items that have been satisfactorily remedied.
The standard FIDIC approach in the UAE splits retention release into two tranches: the first half is released when the Engineer issues the Taking-Over Certificate for the whole works; the second half is released when the Defects Notification Period expires and the Engineer issues the Performance Certificate confirming all defects have been remedied. The snag list bridges the gap between Taking-Over and Performance Certificate.
UAE courts, including the Dubai Courts and the Abu Dhabi Judicial Department, have held that the Contractor is entitled to the second retention tranche once it has completed all required remedial work, regardless of whether the Employer has formally issued a Performance Certificate. Where the Employer withholds the Performance Certificate without legitimate reason after defects have been remedied, the Contractor may apply to the court for an order releasing the retention, relying on Art. 272 of the UAE Civil Code (allowing rescission with compensation) or a direct payment order.
DIAC arbitration panels similarly take a practical view: retention withheld for more than a reasonable period after completion of all snagging items is treated as an unjustified withholding entitling the Contractor to interest on the overdue amount under Art. 76 of the Commercial Transactions Law (Federal Decree-Law No. 50 of 2022) at the Central Bank of the UAE rate.
If a Contractor in the United Arab Emirates refuses or fails to remedy snagging items within the agreed rectification period, the Employer has several legal and practical remedies under UAE law and the terms of the Snagging and Defects Liability Agreement.
The most practical remedy is the right to engage a third-party contractor to complete the unrectified snags and to deduct the cost from the retention withheld under the main contract. This self-help remedy must be exercised in good faith — the Employer must give the Contractor at least 14 days' written notice of its intention to use a third-party contractor, and must allow the Contractor a reasonable opportunity to attend and supervise the remedial works. UAE courts and DIAC panels have consistently held that a unilateral step-in without prior notice is unreasonable and may reduce the Employer's entitlement to recovery.
Where the retention is insufficient to cover the third-party remedial costs, the Employer may bring a claim for compensation under Articles 282 and 389 of the UAE Civil Code (Federal Law No. 5 of 1985), requiring the Contractor to compensate for the loss actually suffered as a natural result of the failure to remedy. The Employer must prove the breach, the loss, and the causal link between them.
The Employer may also call any performance security or bank guarantee issued by the Contractor, on an on-demand basis, where the guarantee terms permit. On-demand guarantees issued by Central Bank of the UAE licensed banks are autonomous instruments, and UAE courts give effect to demand calls without requiring proof of the underlying breach at the time of demand.
For structural defects, the separate Art. 880 regime applies — the Employer may sue for the full cost of structural remediation, whether or not retention has been released, for ten years from Taking-Over.
Off-plan property purchasers in the United Arab Emirates have specific rights regarding defects and snagging that are governed by real estate regulations in addition to the general construction law framework.
In Dubai, off-plan purchasers are protected under Law No. 13 of 2008 on Interim Real Property Register (amended by Law No. 9 of 2009 and Law No. 21 of 2013) and by the Real Estate Regulatory Agency (RERA) under the Real Estate Regulatory Authority. Developers registered with RERA must address structural defects for ten years and must remedy unit-level defects for one year from delivery, mirroring the Art. 880 decennial liability framework. The Dubai Land Department (DLD) and RERA provide dispute resolution mechanisms specifically for off-plan purchaser complaints about snagging.
In Abu Dhabi, the Abu Dhabi Real Estate Centre (ADREC) regulates off-plan property sales, and developers must address unit defects within one year of handover and structural defects for the full ten-year decennial period. Purchasers may file complaints with ADREC if the developer fails to respond to snagging requests within the mandatory timeframe.
A formal snagging agreement is useful for off-plan purchasers to document agreed snags at the time of handover, creating a clear record of what defects were acknowledged by the developer/contractor and what rectification was promised. Without a documented snag list, disputes about which items were identified at handover versus which defects arose subsequently become evidential rather than legal disputes, which the Dubai Courts and Abu Dhabi Judicial Department resolve on the balance of probabilities from whatever documentary evidence is available. A signed, itemised snag schedule significantly strengthens the purchaser's position.
Effective snagging management in the United Arab Emirates requires a systematic classification system that prioritises safety-critical and habitability issues over cosmetic defects and assigns realistic rectification timelines to each category.
Critical items are defects that affect the safety, weatherproofing, or habitability of the building. In UAE practice, these include: active water leaks; fire suppression system deficiencies requiring UAE Civil Defence Authority re-inspection; electrical faults creating shock or fire risk; structural cracking that may be indicative of Art. 880 decennial liability issues; HVAC system failures preventing habitation in UAE climate conditions; and lift defects requiring Lift Authority (part of Abu Dhabi Department of Municipalities and Transport or Dubai Municipality) re-inspection. Critical items should be targeted for rectification within 7 to 14 days under most UAE snagging agreements.
Standard items are functional defects that impair normal use but do not endanger safety: door and window sealing failures, plumbing fitting leaks, incomplete tiling, light fitting failures, and BMS control issues. Standard items are typically targeted for rectification within 30 days.
Cosmetic items are aesthetic imperfections that do not affect function or safety: paint finish touch-ups, minor floor scratching, grouting colour irregularities, and furniture scuff marks. Cosmetic items are typically targeted within 60 days.
The Snag List should number each item sequentially, record the location (floor and room reference), describe the defect, assign the category (critical/standard/cosmetic), note the agreed deadline, and provide a sign-off column for the Employer's and Contractor's representatives to initial when each item is completed. Digital snagging platforms commonly used on UAE projects — Snagr, PlanGrid, and Aconex — generate timestamped photographic records of each item, which are admissible as evidence before the Dubai Courts and in DIAC arbitration.
The Defects Liability Period (DLP) for UAE construction projects is the contractual period following Taking-Over during which the Contractor is obliged to remedy defects, shrinkages, and other faults at its own cost. The DLP under standard FIDIC conditions is typically 12 months from the date of the Taking-Over Certificate, and this is the market standard across residential, commercial, and infrastructure projects in Dubai, Abu Dhabi, and the Northern Emirates.
Some UAE project types use longer DLPs: infrastructure projects often specify an 18-month to 24-month DLP to cover seasonal performance cycles; complex MEP installations may carry a 24-month DLP to assess performance over more than one cooling season, which is relevant in the UAE climate where chilled water and HVAC systems face year-round stress.
At the end of the DLP, the Engineer issues a Performance Certificate confirming that the Contractor has fulfilled all its obligations under the contract, including rectification of all notified defects. The Performance Certificate triggers the release of the second half of retention under the standard FIDIC structure. If the Contractor fails to remedy defects by the end of the DLP, the Employer may engage a third party and deduct the cost from retention, and the Engineer may extend the DLP for unremedied items.
The DLP is a contractual construct and is distinct from the statutory ten-year decennial liability period under Art. 880 of the UAE Civil Code (Federal Law No. 5 of 1985), which runs independently regardless of the DLP duration. Completion of the DLP and issue of the Performance Certificate does not waive the Employer's right to bring a decennial liability claim within ten years of Taking-Over for structural defects discovered after the Performance Certificate is issued.
This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer
Found an error? Let us knowRelated Documents
You may also find these documents useful:
Construction Contract (FIDIC-Style) (UAE)
A FIDIC-style lump-sum construction contract for UAE projects, incorporating muqawala provisions under Arts 872-896 of the UAE Civil Code (Federal Law No. 5 of 1985), Art. 880 decennial liability, VAT under Federal Decree-Law No. 8 of 2017, and DIAC arbitration. Covers Employer, Contractor, Engineer, performance security, defects, and variations.
Completion Certificate (Construction) (UAE)
A UAE Taking-Over / Completion Certificate issued by the Engineer under a FIDIC-style or bespoke construction contract, certifying practical completion, commencing the Defects Notification Period, triggering first-half retention release, and recording regulatory approvals (Dubai Municipality, Civil Defence, DEWA/ADDC). Governed by the UAE Civil Code (Federal Law No. 5 of 1985) Arts 872-896 and Art. 880.
Variation Order (Construction) (UAE)
A UAE construction Variation Order (VO) instructed by the Engineer under Art. 887 of the UAE Civil Code (Federal Law No. 5 of 1985) for lump-sum contract changes, recording scope, valuation (Bill of Quantities rates or Engineer's determination), Extension of Time, adjusted Contract Price, and VAT under Federal Decree-Law No. 8 of 2017.
Construction Subcontract (UAE)
A back-to-back construction subcontract for UAE projects, flowing down obligations from the main contract under the UAE Civil Code (Federal Law No. 5 of 1985), Arts 872-896 muqawala. Covers scope, payment, retention, delay damages, decennial liability under Art. 880, and dispute resolution through DIAC or UAE courts.
MEP Works Contract (UAE)
A UAE MEP works contract for mechanical, electrical, and plumbing installation projects, covering design (where applicable), supply, testing, commissioning, and handover. Governed by the UAE Civil Code (Federal Law No. 5 of 1985) Arts 872-896, with Art. 880 decennial liability, DEWA/ADDC commissioning requirements, UAE Civil Defence NOC, and VAT under Federal Decree-Law No. 8 of 2017.