Skip to main content

Construction Subcontract (UAE)

Construction Subcontract (UAE)

CONSTRUCTION SUBCONTRACT

Dated: [Agreement Date]

MAIN CONTRACTOR: [Main Contractor Name] (Trade Licence: [Main Contractor Licence]), of [Main Contractor Address] (the "Main Contractor");

SUBCONTRACTOR: [Subcontractor Name] (Trade Licence: [Subcontractor Licence]), of [Subcontractor Address] (the "Subcontractor").

THE MAIN CONTRACTOR AND THE SUBCONTRACTOR HAVE AGREED AS FOLLOWS:

1. RECITALS AND DEFINITIONS

1.1 The Main Contractor has entered into the main contract titled [Main Contract Title] with the Employer ([Employer Name]) for the [Project Name] (the "Main Contract").

1.2 The Main Contractor wishes to subcontract part of the Main Contract Works to the Subcontractor on back-to-back terms, subject to the modifications set out in this Subcontract.

1.3 This Subcontract is governed by the UAE Civil Code (Federal Law No. 5 of 1985), Arts 872-896 on muqawala, and the Commercial Transactions Law (Federal Decree-Law No. 50 of 2022).

2. SUBCONTRACT WORKS

2.1 The Subcontractor shall execute the Subcontract Works as follows: [Subcontract Works].

2.2 The Subcontract Documents are: [Subcontract Documents]. In the event of conflict, the order of precedence is: (a) this Subcontract; (b) Subcontract Specification; (c) Drawings; (d) Bills of Quantities.

2.3 The Subcontractor acknowledges that it has had the opportunity to review the Main Contract and that its obligations under this Subcontract include all obligations which the Main Contractor owes to the Employer in respect of the Subcontract Works.

3. TIME FOR COMPLETION

3.1 The Subcontractor shall commence the Subcontract Works on [Commencement Date] and complete them within [Completion Period], subject to extension in accordance with Clause 7 (Variations and Claims).

3.2 If the Subcontractor fails to complete on time, delay liquidated damages of [Delay Damages] become payable. The parties agree this is a genuine pre-estimate of the Main Contractor's loss, consistent with Art. 390 of the UAE Civil Code (Federal Law No. 5 of 1985).

3.3 The Subcontractor shall comply with the Main Contractor's master programme and any revised programme issued by the Main Contractor reflecting the requirements of the Engineer under the Main Contract.

4. PAYMENT

4.1 The Subcontract Price is [Subcontract Price] excluding VAT. VAT at 5% under Federal Decree-Law No. 8 of 2017 shall be added to each tax invoice.

4.2 Payment shall be made in accordance with: [Payment Terms].

4.3 The Main Contractor shall withhold retention of [Retention Percentage]. Retention is security for the Subcontractor's obligations and shall be released as specified above.

4.4 Each invoice must be a valid UAE VAT invoice bearing the Subcontractor's Tax Registration Number (TRN) issued by the Federal Tax Authority (FTA). The Main Contractor may withhold payment for non-compliant invoices.

5. BACK-TO-BACK OBLIGATIONS

5.1 The Subcontractor assumes toward the Main Contractor all rights, obligations, duties, and liabilities that the Main Contractor has assumed toward the Employer under the Main Contract in respect of the Subcontract Works. The Main Contractor assumes toward the Subcontractor those rights the Employer owes the Main Contractor in respect of the Subcontract Works.

5.2 If the Employer or the Engineer instructs any variation affecting the Subcontract Works, the Main Contractor shall promptly notify the Subcontractor and the value adjustment shall be applied back-to-back.

5.3 The Subcontractor shall not communicate directly with the Employer without the Main Contractor's prior written consent, except in an emergency affecting safety.

6. DEFECTS AND DECENNIAL LIABILITY

6.1 The Subcontractor shall remedy any defect in the Subcontract Works notified during the Defects Liability Period matching the Main Contract's Defects Notification Period.

6.2 The Subcontractor acknowledges that Art. 880 of the UAE Civil Code (Federal Law No. 5 of 1985) imposes ten-year decennial liability for structural defects and that this liability flows through to the Subcontractor for its scope of works. This liability cannot be excluded by this Subcontract.

7. VARIATIONS AND CLAIMS

7.1 The Main Contractor may instruct Variations to the Subcontract Works. The Subcontractor shall proceed with all instructed Variations and submit its valuation within 14 days of the instruction. Failure to submit within 28 days of the event giving rise to a claim may bar the claim.

7.2 No Variation shall invalidate this Subcontract.

8. INSURANCE

8.1 The Subcontractor shall maintain the following insurances from the Commencement Date through the end of the Defects Liability Period: [Insurance Requirements]. All policies shall name the Main Contractor as an additional insured and be placed with an insurer licensed by the Insurance Authority of the UAE.

8.2 Evidence of insurance (certificates and endorsements) shall be provided to the Main Contractor before commencement. The Subcontractor shall also comply with Workmen's Compensation obligations under the Labour Law (Federal Decree-Law No. 33 of 2021) for its workers and subcontractors.

9. DISPUTE RESOLUTION

9.1 The parties shall attempt to resolve any dispute by negotiation within 21 days of written notice. If unresolved, either party may refer the dispute to [Dispute Forum].

9.2 This Subcontract is governed by the laws of the United Arab Emirates.

10. GENERAL

10.1 This Subcontract is the entire agreement between the parties on its subject matter. Amendments must be in writing.

10.2 The Subcontractor shall not further subcontract the Subcontract Works without the Main Contractor's prior written consent, which shall not be unreasonably withheld.

10.3 Electronic notices are valid under the Electronic Transactions and Trust Services Law (Federal Decree-Law No. 46 of 2021).

SIGNED for and on behalf of the MAIN CONTRACTOR: [Main Contractor Name]

SIGNED for and on behalf of the SUBCONTRACTOR: [Subcontractor Name]

Main Contractor

________________

Signature

Subcontractor

________________

Signature

Maintained by Vladislav Sergienko, Founder·Template last modified: ·Report an error

What Is a Construction Subcontract (UAE)?

A Construction Subcontract in the United Arab Emirates is a binding agreement between a Main Contractor and a Subcontractor under which the Subcontractor agrees to perform a defined portion of the construction works that the Main Contractor is obliged to deliver under its main contract with the Employer. The subcontract is governed by the UAE Civil Code (Federal Law No. 5 of 1985), specifically Arts 872-896 on muqawala (construction and works contracts), and by the Commercial Transactions Law (Federal Decree-Law No. 50 of 2022) where both parties are merchants acting in the course of trade.

Article 872 of the UAE Civil Code permits a contractor to subcontract work unless the main contract expressly prohibits subcontracting or the obligation was undertaken by reference to the Main Contractor's particular skills or identity. In practice, most UAE construction contracts and the standard FIDIC conditions (Red Book, Yellow Book, Silver Book) permit subcontracting subject to the Employer's or Engineer's prior written consent for specialist and named subcontractors. FIDIC subcontract practice in the UAE mirrors the main contract structure: the Subcontractor flows down the obligations of the Main Contractor to the Employer, and the Main Contractor flows up the rights of the Employer to the Subcontractor, on a back-to-back basis.

The subcontract is a separate legal instrument from the main contract, but it is drafted to be consistent with it. The Dubai Courts and the Abu Dhabi Judicial Department treat the subcontract as an independent contract giving rise to direct obligations between the Main Contractor and the Subcontractor, enforceable independently of the Employer's acts. Where the subcontract incorporates main contract provisions by reference, UAE courts give effect to those incorporated terms if they are clearly identified.

The Ministry of Human Resources and Emiratisation (MOHRE) regulates the employment of workers engaged by the Subcontractor, and the Wage Protection System requires wage payment through UAE-licensed financial institutions. The Federal Tax Authority (FTA) requires the Subcontractor to issue compliant VAT invoices under Federal Decree-Law No. 8 of 2017 for each taxable supply of subcontract services. The Insurance Authority of the UAE requires subcontractors carrying structural risk to hold appropriate insurance, and the Central Bank of the UAE supervises the banks that issue performance guarantees securing the Subcontractor's obligations.

When Do You Need a Construction Subcontract (UAE)?

A Construction Subcontract in the United Arab Emirates is needed whenever a Main Contractor delegates part of the construction works to a specialist trade contractor, and both parties require a written, legally compliant agreement that establishes their respective rights and obligations clearly enough to be enforced before the Dubai Courts, the Abu Dhabi Judicial Department, or a DIAC arbitration panel.

Structural and specialist works — piling, structural steelwork, concrete frame, curtain wall, and MEP installations — are routinely subcontracted in UAE projects because the Main Contractor may lack the specific plant, workforce, or expertise for those trades. The Abu Dhabi Department of Municipalities and Transport and the Dubai Building Permit Authority require specialist trade contractors to hold appropriate category licences from the relevant Department of Economic Development, so the subcontract must identify the Subcontractor's licensed activity and confirm it covers the subcontracted scope.

Main contractors tendering for government and semi-government projects under Abu Dhabi government procurement rules or the Dubai Supply Chain Policy must list their intended subcontractors and confirm subcontract compliance with the main contract, making a formal subcontract document a procurement requirement. Financiers — UAE-licensed banks supervised by the Central Bank of the UAE — reviewing project finance transactions also require subcontract documentation as part of their due diligence on the construction programme.

Insurance requirements make a formal subcontract essential: the Subcontractor's public liability and workmen's compensation policies must name the Main Contractor as an additional insured, and the Insurance Authority of the UAE requires policy endorsements to be supported by a formal contractual basis. Where the Subcontractor performs design and build work — for example, designing and installing a prefabricated staircase or a mechanical ventilation system — the subcontract must also allocate decennial liability under Art. 880 of the UAE Civil Code (Federal Law No. 5 of 1985) and professional indemnity insurance obligations clearly.

Wage Protection System (WPS) compliance, administered by the Ministry of Human Resources and Emiratisation (MOHRE) under the Labour Law (Federal Decree-Law No. 33 of 2021) and Cabinet Resolution No. 1 of 2022, is a mandatory obligation for the Subcontractor's workforce. Main Contractors operating under government procurement frameworks or FIDIC-style contracts increasingly require subcontracts to include explicit WPS compliance obligations, because a Subcontractor's WPS default can result in MOHRE visa suspension affecting the entire project's labour supply. A formal written subcontract allows the Main Contractor to deduct WPS-related costs directly from the Subcontract Price if the Subcontractor defaults, providing financial protection that an informal arrangement does not afford.

What to Include in Your Construction Subcontract (UAE)

A UAE Construction Subcontract that is enforceable before the Dubai Courts, the Abu Dhabi Judicial Department, and DIAC arbitration panels must contain the following key elements. The forms-legal.com subcontract template incorporates each component in a commercially sound structure.

Party identification requires the full legal name, trade licence number, and registered address of both the Main Contractor and the Subcontractor. The trade licence must confirm that each party's licensed activity covers the relevant construction operations, as required by the relevant Department of Economic Development.

Reference to the main contract is essential for an effective back-to-back subcontract. The main contract title, date, and parties must be identified, and the subcontract must specify which main contract obligations and rights are incorporated by flow-down. Ambiguous incorporation by reference without specifying which provisions flow through is a frequent source of UAE construction disputes.

Scope of Subcontract Works must describe the works with sufficient precision to avoid disputes about what is in scope. Reference drawings, specifications, and bills of quantities by revision date and document number.

Time for Completion and programme obligations must align with the main contract programme. The Subcontractor must be given the Main Contractor's construction programme and must comply with milestones affecting the Main Contractor's own completion obligations to the Employer.

Payment terms, including the advance payment, progress payment timing, retention percentage and release milestones, must be stated. VAT at 5% under Federal Decree-Law No. 8 of 2017 applies to all subcontract services, and every payment must be supported by a compliant tax invoice issued to the Federal Tax Authority (FTA) standard.

Delay liquidated damages must be fixed as a genuine pre-estimate of the Main Contractor's loss attributable to the Subcontractor's delay, capped at a maximum percentage, consistent with Art. 390 of the UAE Civil Code (Federal Law No. 5 of 1985).

Decennial liability acknowledgement must confirm that Art. 880 applies to structural works performed by the Subcontractor and that this liability cannot be limited by the subcontract.

Dispute resolution must identify the forum — Dubai Courts, Abu Dhabi Judicial Department, or DIAC arbitration under the Federal Arbitration Law (Federal Law No. 6 of 2018) — and the governing law as UAE law.

How to Fill Out Your Construction Subcontract (UAE)

Completing a UAE Construction Subcontract requires careful coordination between the Main Contractor's commercial team and the Subcontractor's management, ideally before the Subcontractor starts work on site.

Begin with the parties section. Enter the Main Contractor's full legal name as it appears on its trade licence, the trade licence number, and the registered office address. Repeat for the Subcontractor. Confirm that both parties hold trade licences from the relevant Department of Economic Development covering the construction activity being subcontracted — the Dubai DED, Abu Dhabi DED, Sharjah DED, or the relevant free-zone registrar.

In the main contract details section, enter the full title and reference of the main contract — including the date, the parties' names, and the project name. Enter the Employer's full legal name. This information enables the back-to-back flow-down to be read in the context of the specific main contract, so precision matters.

Describe the Subcontract Works precisely. Reference the drawings and specification sections by revision date and document reference number. List the Bills of Quantities reference. The scope description should leave no reasonable doubt about what is included and what is excluded from the subcontracted package.

Enter the Commencement Date in DD/MM/YYYY format. State the completion period clearly — calendar days from the Commencement Date, or cross-reference to the Main Contractor's programme milestone. Set the delay liquidated damages rate in AED per calendar day, with a cap.

Set the Subcontract Price in AED excluding VAT. State the payment terms, including the timing of monthly valuations, the payment period after the Main Contractor receives Employer payment, and the retention percentage. Note that VAT at 5% under Federal Decree-Law No. 8 of 2017 must be added to each tax invoice.

List the insurance requirements, including minimum sums insured, and confirm that the Insurance Authority of the UAE licences all insurers. Select the dispute resolution forum — the Dubai Courts for Dubai projects, Abu Dhabi Judicial Department for Abu Dhabi projects, or DIAC arbitration for major subcontracts.

Both parties should sign through authorised representatives. Electronic signatures are valid under the Electronic Transactions and Trust Services Law (Federal Decree-Law No. 46 of 2021). Retain originals with both parties' commercial managers and file copies with the project document control system.

Common Mistakes to Avoid in Your Construction Subcontract (UAE)

UAE construction subcontracts are frequently drafted with errors that create expensive disputes. The following mistakes recur in DIAC arbitration proceedings and before the Dubai Courts and Abu Dhabi Judicial Department.

1. Vague scope description. A subcontract that describes the works as 'all structural works' without identifying drawings, specification sections, and bill of quantities references creates scope boundary disputes. Every scope boundary must be specified by reference to numbered documents with revision dates.

2. Incomplete back-to-back incorporation. Stating that the subcontract is 'on back-to-back terms with the main contract' without listing which specific main contract clauses are incorporated means the courts must interpret the incorporation, often in the Main Contractor's favour at the Subcontractor's expense. List every incorporated provision explicitly.

3. Missing time bar for claims. The Subcontractor must serve written notice of a claim for additional time or money within the contractual period — typically 28 days. Failure to track notice deadlines has caused many Subcontractors to lose valid claims before DIAC and the Dubai Courts.

4. No compliant VAT invoice procedure. The Federal Tax Authority (FTA) requires every interim payment to be supported by a valid tax invoice with the Subcontractor's Tax Registration Number (TRN). Failure to issue compliant invoices delays payment and may attract FTA penalties against the Subcontractor.

5. Ignoring MOHRE WPS requirements. Subcontractors who fail to pay workers through the Wage Protection System face MOHRE fines and visa suspension, which can halt works on site and trigger liquidated damages claims from the Main Contractor.

6. Failure to maintain contemporaneous site records. DIAC arbitration panels and UAE courts require documentary evidence of delay causes, additional work performed, and instructions received. Subcontractors who do not keep daily site records, labour allocation sheets, and written instruction logs frequently fail to recover legitimate Variation claims.

Cite this page

Reference this free template in an article, syllabus, or research note:

APA

Forms Legal. (2026). Construction Subcontract (UAE) (United Arab Emirates) [Legal document template]. Forms Legal. https://forms-legal.com/uae/business/contracts/construction-subcontract-uae

MLA

"Construction Subcontract (UAE) (United Arab Emirates)." Forms Legal, 2026, https://forms-legal.com/uae/business/contracts/construction-subcontract-uae.

BibTeX
@misc{formslegal-construction-subcontract-uae,
  author       = {{Forms Legal}},
  title        = {Construction Subcontract (UAE) (United Arab Emirates)},
  year         = {2026},
  howpublished = {\url{https://forms-legal.com/uae/business/contracts/construction-subcontract-uae}},
  note         = {Free legal document template. Based on UAE Civil Code (Federal Law No. 5 of 1985), Arts 872-896 (muqawala) and Art. 880 (decennial liability)}
}

Frequently Asked Questions

Based on UAE Civil Code (Federal Law No. 5 of 1985), Arts 872-896 (muqawala) and Art. 880 (decennial liability) — Template last modified June 2026

This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer

Found an error? Let us know

Related Documents

You may also find these documents useful:

Construction Contract (FIDIC-Style) (UAE)

A FIDIC-style lump-sum construction contract for UAE projects, incorporating muqawala provisions under Arts 872-896 of the UAE Civil Code (Federal Law No. 5 of 1985), Art. 880 decennial liability, VAT under Federal Decree-Law No. 8 of 2017, and DIAC arbitration. Covers Employer, Contractor, Engineer, performance security, defects, and variations.

Variation Order (Construction) (UAE)

A UAE construction Variation Order (VO) instructed by the Engineer under Art. 887 of the UAE Civil Code (Federal Law No. 5 of 1985) for lump-sum contract changes, recording scope, valuation (Bill of Quantities rates or Engineer's determination), Extension of Time, adjusted Contract Price, and VAT under Federal Decree-Law No. 8 of 2017.

MEP Works Contract (UAE)

A UAE MEP works contract for mechanical, electrical, and plumbing installation projects, covering design (where applicable), supply, testing, commissioning, and handover. Governed by the UAE Civil Code (Federal Law No. 5 of 1985) Arts 872-896, with Art. 880 decennial liability, DEWA/ADDC commissioning requirements, UAE Civil Defence NOC, and VAT under Federal Decree-Law No. 8 of 2017.

Completion Certificate (Construction) (UAE)

A UAE Taking-Over / Completion Certificate issued by the Engineer under a FIDIC-style or bespoke construction contract, certifying practical completion, commencing the Defects Notification Period, triggering first-half retention release, and recording regulatory approvals (Dubai Municipality, Civil Defence, DEWA/ADDC). Governed by the UAE Civil Code (Federal Law No. 5 of 1985) Arts 872-896 and Art. 880.

Snagging & Defects Liability Agreement (UAE)

A UAE snagging and defects liability agreement executed after Taking-Over, documenting outstanding items and the Contractor's rectification obligations under the UAE Civil Code (Federal Law No. 5 of 1985). Covers the snag register, rectification period, retention release, third-party remedy rights, and Art. 880 decennial liability preservation.