Completion Certificate (Construction) (UAE)
COMPLETION CERTIFICATE (TAKING-OVER CERTIFICATE)
Certificate Reference: [Engineer Ref]
Issued by: [Engineer Name]
Date: [Certificate Date]
Project: [Project Name]
Employer: [Employer Name]
Contractor: [Contractor Name]
Main Contract Reference: [Main Contract Ref]
1. CERTIFICATION OF COMPLETION
1.1 I, [Engineer Name], acting as Engineer / Contract Administrator under the Main Contract, certify that the Contractor, [Contractor Name], has completed the Works identified below to the standard required by the Main Contract, and that the Employer, [Employer Name], may take over the Works with effect from [Actual Completion Date] (the "Date of Taking-Over").
1.2 Works certified as complete: [Works Completed].
1.3 Contractual Time for Completion: [Contractual Completion Date]. Actual Date of Taking-Over: [Actual Completion Date].
1.4 This Completion Certificate is issued in accordance with the Main Contract and the UAE Civil Code (Federal Law No. 5 of 1985), Arts 872-896 on muqawala contracts, which govern the Employer's obligation to accept the completed Works and the Contractor's right to receive payment upon completion.
2. OUTSTANDING ITEMS AND SNAGGING
2.1 The following minor items remain outstanding and shall be rectified by the Contractor during the Defects Notification Period: [Outstanding Items].
2.2 The outstanding items listed above do not prevent the Works from being occupied or used for their intended purpose. The issue of this Certificate is not conditional on their completion.
2.3 Notwithstanding this Certificate, the non-excludable ten-year decennial liability under Art. 880 of the UAE Civil Code (Federal Law No. 5 of 1985) runs from the Date of Taking-Over ([Actual Completion Date]) for any structural collapse or defect threatening the structural safety or stability of the Works.
3. REGULATORY APPROVALS
3.1 The following regulatory approvals have been obtained prior to or simultaneously with the issue of this Certificate: [Regulatory Approvals].
3.2 The Contractor shall obtain any remaining regulatory approvals and provide copies to the Employer within 14 days of this Certificate.
4. DEFECTS NOTIFICATION PERIOD AND RETENTION
4.1 The Defects Notification Period commences on the Date of Taking-Over and runs for [Defects Notification Period]. During this period, the Contractor is obliged to remedy, at its own cost, any defect notified by the Engineer or the Employer.
4.2 On the basis of this Certificate, the Employer shall release the following retention: [Retention Released]. The remaining retention shall be released upon issue of the Performance Certificate at the end of the Defects Notification Period, subject to satisfactory rectification of all notified defects.
4.3 The Employer's risk for care of the Works passes to the Employer on the Date of Taking-Over ([Actual Completion Date]), in accordance with the Main Contract and Art. 879 of the UAE Civil Code (Federal Law No. 5 of 1985).
5. ENGINEER'S SIGNATURE
5.1 This Certificate is issued by the Engineer in the exercise of the Engineer's authority under the Main Contract and in accordance with the UAE Civil Code (Federal Law No. 5 of 1985).
Issued by: [Engineer Name]
Certificate Reference: [Engineer Ref]
Date: [Certificate Date]
ACKNOWLEDGED by the EMPLOYER: [Employer Name]
ACKNOWLEDGED by the CONTRACTOR: [Contractor Name]
Engineer / Contract Administrator
________________
Signature
Employer (acknowledged)
________________
Signature
Contractor (acknowledged)
________________
Signature
What Is a Completion Certificate (Construction) (UAE)?
A Completion Certificate in the United Arab Emirates — formally called a Taking-Over Certificate under FIDIC-style contracts, and equivalent to a practical completion certificate or substantial completion certificate in other contracting traditions — is the formal document issued by the Engineer (Contract Administrator) certifying that the Contractor has completed the construction Works to the standard required by the main contract and that the Employer may take over and occupy the completed building. The Completion Certificate is the pivotal milestone in the life of a UAE construction contract: it determines when the Employer's risk for the Works commences, when delay liquidated damages stop accruing, when the Defects Notification Period (DLP) begins, when the first tranche of retention is released, and — critically — when the ten-year decennial liability period under Art. 880 of the UAE Civil Code (Federal Law No. 5 of 1985) starts running.
The legal framework governing Completion Certificates in the UAE is rooted in the UAE Civil Code (Federal Law No. 5 of 1985), Arts 872-896 on muqawala (construction contracts). Article 879 provides that the Employer must accept completed works that conform to the contract and the applicable regulations, and places the risk of care for the Works on the Employer from the date of delivery. Article 880 imposes mandatory, non-excludable ten-year decennial liability on the Contractor and, where applicable, the structural engineer or architect, for structural collapse or defects threatening the safety of the completed building, running from the date of delivery (Taking-Over). Article 892 governs pricing under lump-sum contracts, and Art. 887 addresses the Employer's right to terminate before completion. The Commercial Transactions Law (Federal Decree-Law No. 50 of 2022) governs the commercial obligations flowing from the Completion Certificate, including retention payment timing and late-payment interest under Art. 76 at the Central Bank of the UAE rate.
In UAE regulatory terms, the contractual Completion Certificate issued by the Engineer is distinct from the municipal building completion certificate or occupancy permit issued by the Dubai Municipality (DM) Building Permit Authority (BPA) or the Abu Dhabi Department of Municipalities and Transport (DMT). Both documents are required before the building can be lawfully occupied: the contractual certificate establishes the legal relationship between Employer and Contractor; the municipal certificate confirms regulatory compliance. The UAE Civil Defence Authority must separately issue a No Objection Certificate (NOC) for fire and life safety systems before the municipality issues the occupancy permit.
The forms-legal.com UAE Completion Certificate template provides a legally sound and commercially complete framework for recording completion, triggering retention release, commencing the DLP, and preserving the Employer's Art. 880 rights for the full ten-year decennial period across all types of UAE construction projects — from residential villas in Dubai's villa communities to high-rise commercial towers in Abu Dhabi Global Market Square.
When Do You Need a Completion Certificate (Construction) (UAE)?
A Completion Certificate (Taking-Over Certificate) in the United Arab Emirates is needed at the end of the construction programme when the Contractor notifies the Engineer that the Works are substantially complete, triggering the Engineer's obligation to inspect and, if satisfied, issue the certificate or state reasons for withholding it.
Residential and commercial projects across Dubai, Abu Dhabi, Sharjah, and the Northern Emirates require a contractual Completion Certificate before the Employer can formally accept the Works and take possession. Without a formal Completion Certificate, the Employer's risk allocation remains ambiguous — the Contractor continues to bear responsibility for care of the Works, delay liquidated damages may continue to accrue, and the DLP cannot commence.
Project finance transactions supervised by the Central Bank of the UAE typically require the Completion Certificate as a condition for releasing the final construction loan drawdown to the developer. Lenders treat the Completion Certificate as evidence that the Contractor has fulfilled its contractual obligations and that the building's value as security has been established as a completed structure.
The Dubai Land Department (DLD) and the Real Estate Regulatory Agency (RERA) require a building completion certificate as a prerequisite for registering title to completed off-plan units in the Owners' Register and for issuing title deeds to purchasers. Without the completion certificate, off-plan purchasers cannot take legal title to their purchased units, delaying the entire title registration process.
Insurance transitions at practical completion — from the contractor's all-risks (CAR) policy covering construction risk to the Employer's building property insurance — require a defined completion date, which the Completion Certificate provides. The Insurance Authority of the UAE expects the CAR policy to cover the DLP period but its nature changes at Taking-Over from construction risk to a completed operations cover, and the policy must be endorsed accordingly.
For free-zone developments in the DIFC and ADGM, the relevant free-zone authority's completion approval is required in addition to the contractual Completion Certificate, and the DIFC Courts or ADGM Courts may resolve disputes about the timing and validity of completion under the respective free-zone legal frameworks.
What to Include in Your Completion Certificate (Construction) (UAE)
A UAE Completion Certificate that is legally valid, enforceable before the Dubai Courts and the Abu Dhabi Judicial Department, and sufficient to trigger contractual consequences including retention release and commencement of the Defects Notification Period must contain the following key elements. The forms-legal.com UAE Completion Certificate template addresses each component in a structured, authoritative format.
Engineer identification requires the full name, qualifications, and firm of the Engineer or Contract Administrator issuing the certificate, together with a unique certificate reference number. The Engineer must hold authority under the main contract to issue Taking-Over Certificates, and where the Engineer is a firm, the individual signatory should be identified.
Certificate date, in DD/MM/YYYY format, is the date on which the certificate is issued. This date is critical because it is the date from which the DLP runs, from which the ten-year decennial liability period under Art. 880 of the UAE Civil Code (Federal Law No. 5 of 1985) runs, and from which the retention release right arises.
Project and contract identification must record the project name and address, the main contract reference and date, the Employer's and Contractor's full legal names, the contractual Time for Completion date, and the actual date of Taking-Over. The comparison between contractual and actual completion dates determines whether delay liquidated damages are payable.
Works description must identify the scope certified as complete — whether the whole works or a defined section — with sufficient precision to identify what the Employer is taking over and what, if any, obligations remain.
Outstanding items (snag list) should be referenced or attached as Schedule 1 to the certificate, recording minor defects that do not prevent use but must be remedied during the DLP.
Regulatory approvals must list all obtained approvals — Dubai Municipality completion certificate, Civil Defence NOC, DEWA/ADDC utility approvals, Lift Authority certificate — and flag any outstanding approvals with the date by which they must be obtained.
Defects Notification Period must state the DLP duration and expiry date, commencing from the certificate date.
Retention release must state the AED amount of the first retention tranche released on this certificate and the conditions for the second tranche release.
Decennial liability acknowledgement must confirm that Art. 880 of the UAE Civil Code applies from the certificate date and cannot be excluded.
How to Fill Out Your Completion Certificate (Construction) (UAE)
Completing a UAE Completion Certificate requires the Engineer to conduct a thorough inspection of the completed Works before issuing the certificate and to assemble the supporting regulatory documentation.
Start with the Engineer's details. Enter the full name and qualifications of the issuing Engineer and the firm they represent. Assign a unique certificate reference number using a sequential numbering system (e.g., CC-2026-001). Enter the certificate date in DD/MM/YYYY format — this is the date of issue, which must follow the inspection.
Enter the Employer's and Contractor's full legal names exactly as they appear in the main contract. Enter the main contract reference and date. Enter the contractual Time for Completion date and the actual date of Taking-Over — these dates determine whether delay liquidated damages are payable for late completion.
In the Works Completed section, describe the scope certified as complete. For a whole-works Taking-Over, state 'the whole of the Works as defined in the Contract Documents.' For sectional Taking-Over, specify the section by reference to the contract's sections schedule. Be precise: vague descriptions create disputes about what was certified.
In the Outstanding Items section, describe or reference the snag list. If a detailed snag list is attached as Schedule 1 to the certificate, state the total number of items and reference the schedule. Note any items affecting regulatory compliance — Civil Defence, DEWA, ADDC — separately and set short deadlines for those.
In the Regulatory Approvals section, list each approval with its reference number and date. For approvals not yet obtained, note them and set a 14-day deadline for the Contractor to provide copies.
Enter the Defects Notification Period — typically 12 months from the certificate date — and calculate the expiry date.
State the retention tranche released — typically the first half — in AED with the calculation basis (e.g., 2.5% of the Contract Price of AED X = AED Y).
The Engineer signs the certificate. Both the Employer and the Contractor acknowledge receipt in writing. Electronic signatures are valid under the Electronic Transactions and Trust Services Law (Federal Decree-Law No. 46 of 2021).
Legal Requirements for Completion Certificate (Construction) (UAE)
A Completion Certificate (Taking-Over Certificate) in the United Arab Emirates derives its legal effect from the following statutory framework.
The UAE Civil Code (Federal Law No. 5 of 1985) is the primary source. Article 879 governs the Employer's obligation to accept completed works conforming to the contract and places the risk of care on the Employer from the date of delivery. Article 880 imposes non-excludable ten-year decennial liability on the Contractor and the structural engineer or architect, running from the date of delivery (Taking-Over), for structural collapse or defects threatening structural safety. Article 877 permits the Engineer to verify the works before handover and certify completion. Articles 872-896 govern muqawala obligations generally.
The Commercial Transactions Law (Federal Decree-Law No. 50 of 2022) governs retention payment timing and late-payment interest under Art. 76 at the Central Bank of the UAE rate.
The Commercial Companies Law (Federal Decree-Law No. 32 of 2021) requires each signatory — the Engineer, the Employer's representative, and the Contractor's representative — to hold authority to bind their respective entities.
Regulatory requirements: Dubai Municipality (DM) Building Permit Authority (BPA) issues the building completion certificate and occupancy permit required for lawful occupation in Dubai. Abu Dhabi Department of Municipalities and Transport (DMT) issues the equivalent in Abu Dhabi. The UAE Civil Defence Authority issues the fire and life safety NOC. DEWA and ADDC/AADC issue utility connection approvals. Dubai Land Department (DLD) requires the completion certificate for title registration of off-plan units.
Federal Decree-Law No. 8 of 2017 on VAT governs the VAT treatment of retention payments released on the Completion Certificate. The Electronic Transactions and Trust Services Law (Federal Decree-Law No. 46 of 2021) validates electronic certificates and digital delivery.
Common Mistakes to Avoid in Your Completion Certificate (Construction) (UAE)
Completion Certificates on UAE construction projects frequently contain errors or omissions that generate disputes about whether the Works have been validly accepted, when the DLP starts, and when retention must be released. The following mistakes recur in disputes before the Dubai Courts and DIAC arbitration panels.
1. No certificate issued — relying on email exchanges. Some UAE projects proceed to handover on the basis of email exchanges between the Employer and the Contractor, without a formal Completion Certificate signed by the Engineer. This approach creates uncertainty about the exact date of Taking-Over, which directly affects the start of the DLP, the decennial liability period under Art. 880 of the UAE Civil Code (Federal Law No. 5 of 1985), and the retention release timeline. A formal, signed certificate with a unique reference and a defined date eliminates this ambiguity.
2. No outstanding items schedule attached. A certificate that states 'the Works are complete' without any attached snag list gives the Employer no leverage to require the Contractor to return and remedy outstanding items during the DLP. The outstanding items schedule is essential for managing the transition from construction to the defects liability phase.
3. Confusing contractual completion with regulatory approval. Contractors sometimes pressure Engineers to issue the Completion Certificate before the Civil Defence NOC or the DEWA connection approval has been obtained, arguing that regulatory delays are the Employer's risk. The Completion Certificate should not be issued before all safety-critical regulatory approvals — particularly the Civil Defence NOC — are in place.
4. Not specifying the DLP expiry date. Failing to state the DLP expiry date leaves both parties uncertain about when the Engineer must issue the Performance Certificate and when the remaining retention is due. Calculate and state the expiry date explicitly in the certificate.
5. Omitting the decennial liability acknowledgement. A Completion Certificate that does not reference Art. 880 of the UAE Civil Code can create ambiguity about whether the certificate constitutes a full and final acceptance of the Works that extinguishes the Employer's decennial rights. The acknowledgement clause preserves the Employer's statutory rights.
6. Delay in releasing the first retention tranche. Unreasonable delay in releasing the first retention tranche after issuing the Completion Certificate exposes the Employer to interest claims under Art. 76 of the Commercial Transactions Law (Federal Decree-Law No. 50 of 2022) and may constitute a breach of the main contract's payment provisions.
Cite this page
Reference this free template in an article, syllabus, or research note:
Forms Legal. (2026). Completion Certificate (Construction) (UAE) (United Arab Emirates) [Legal document template]. Forms Legal. https://forms-legal.com/uae/business/contracts/completion-certificate-uae
"Completion Certificate (Construction) (UAE) (United Arab Emirates)." Forms Legal, 2026, https://forms-legal.com/uae/business/contracts/completion-certificate-uae.
@misc{formslegal-completion-certificate-uae,
author = {{Forms Legal}},
title = {Completion Certificate (Construction) (UAE) (United Arab Emirates)},
year = {2026},
howpublished = {\url{https://forms-legal.com/uae/business/contracts/completion-certificate-uae}},
note = {Free legal document template. Based on UAE Civil Code (Federal Law No. 5 of 1985), Art. 879 (delivery and risk) and Art. 880 (decennial liability)}
}Frequently Asked Questions
A Taking-Over Certificate in a UAE FIDIC-style construction contract is the formal document issued by the Engineer (Contract Administrator) certifying that the Contractor has completed the Works — or a defined section of the Works — to the standard required by the main contract, and that the Employer may take over and use the completed structure. The Taking-Over Certificate is the equivalent of a 'practical completion certificate' in other contract traditions and is the most significant milestone in the FIDIC project lifecycle.
Under FIDIC Red Book (Design-Bid-Build) and Yellow Book (Design-Build) conditions, the Taking-Over Certificate triggers several legal and financial consequences simultaneously: the risk for care of the Works passes from the Contractor to the Employer; the Defects Notification Period (DLP) commences; the first half of the contractual retention is released; the Contractor's liability for delay liquidated damages for late completion ceases; and the ten-year decennial liability period under Art. 880 of the UAE Civil Code (Federal Law No. 5 of 1985) begins.
UAE law requires the Employer to accept the Works if they substantially conform to the contract — the Employer cannot refuse Taking-Over for minor defects that do not prevent use of the building. Art. 879 of the UAE Civil Code (Federal Law No. 5 of 1985) places the risk of care on the employer once the contractor has delivered the works in a condition that allows handover, so unreasonable refusal to issue the Taking-Over Certificate can be challenged before the Dubai Courts or the Abu Dhabi Judicial Department.
For projects in Abu Dhabi, the Abu Dhabi Department of Municipalities and Transport (DMT) issues a separate building completion certificate upon satisfying the municipal authority's inspection requirements, which is distinct from but typically aligns with the contractual Taking-Over Certificate.
The ten-year decennial liability period under Art. 880 of the UAE Civil Code (Federal Law No. 5 of 1985) runs from the date the Employer takes over the completed building — the date of the Taking-Over Certificate (or its equivalent) under the main contract, not from the date the contract was signed, not from the commencement of construction, and not from the date of the occupancy permit.
UAE courts, including the Dubai Courts and the Abu Dhabi Judicial Department, have consistently held that the decennial period runs from the contractual 'date of delivery' of the completed works to the Employer. Where the Taking-Over Certificate and the occupancy permit are issued on different dates — for example, where the municipality issues the occupancy permit several months after contractual practical completion — UAE courts have generally treated the Taking-Over Certificate date as the start of the decennial period for claims between Contractor and Employer, because that is when the Employer accepted the Works.
The Employer has three years from the date it discovers the structural defect to bring a claim under Art. 883 of the UAE Civil Code, but the three-year limitation period cannot extend beyond the end of the ten-year decennial period. Structural defects discovered in year 11 are time-barred.
For phased projects where different sections are completed and taken over at different times, the decennial liability period runs separately for each section from its own Taking-Over date. Contractors should ensure that their professional indemnity insurance covers each phase's separate ten-year period from its respective Taking-Over date.
A completed building in the United Arab Emirates cannot be lawfully occupied until several regulatory approvals have been obtained from different authorities, and the issuance of a contractual Completion or Taking-Over Certificate does not substitute for these statutory permits.
In Dubai, the primary occupancy authorisation is the building completion certificate issued by Dubai Municipality (DM), based on a final inspection by the Dubai Building Permit Authority (BPA). The BPA inspects the completed structure against the approved drawings and must be satisfied that the building has been constructed in compliance with the approved permit. A separate Certificate of Occupancy (or 'Izin Istighlal') may also be required depending on building type and use.
The UAE Civil Defence Authority must issue a No Objection Certificate (NOC) confirming that fire suppression, detection, and alarm systems meet the UAE Fire and Life Safety Code of Practice. Without the Civil Defence NOC, the municipality will not issue the occupancy certificate. Civil Defence inspections are a frequent cause of handover delays on UAE projects, as fire system deficiencies must be fully remedied and re-inspected before sign-off.
Utility connections require authorisation from DEWA (Dubai Electricity and Water Authority) in Dubai or ADDC/AADC (Abu Dhabi Distribution Company/Al Ain Distribution Company) in Abu Dhabi, confirming that permanent electrical and water connections have been inspected and energised/activated. Lift installations require a Lift Authority certificate from Dubai Municipality or the Abu Dhabi Department of Municipalities and Transport, as applicable.
For projects in free zones — DIFC, ADGM, DMCC, JAFZA — the relevant free-zone authority issues its own completion approval in addition to or instead of the mainland municipal authority's certificate, and the specific requirements differ by zone.
If the Engineer refuses to issue a Taking-Over Certificate on a UAE construction project, the Contractor has contractual and legal remedies to challenge the refusal.
Contractually, under standard FIDIC conditions adapted for the UAE, the Contractor may submit a formal notice of completion to the Engineer, triggering a 28-day period in which the Engineer must either issue the Taking-Over Certificate or notify the Contractor of the reasons for refusal. If the Engineer neither issues the certificate nor gives reasons within 28 days, the Contractor may treat the failure as a dispute and refer it to the agreed dispute resolution mechanism — typically DIAC arbitration or a dispute adjudication board.
Under UAE law, Article 879 of the UAE Civil Code (Federal Law No. 5 of 1985) places the risk of care on the Employer once the Contractor delivers the Works in a condition substantially conforming to the contract. If the Employer (through the Engineer) refuses to accept works that do in fact conform to the contract, the Employer may be liable for the Contractor's prolongation costs from the date the Works were ready for Taking-Over. The Dubai Courts and the Abu Dhabi Judicial Department have held that unreasonable refusal to accept completed works exposes the Employer to liability for the Contractor's extended preliminaries and financing costs.
For the Employer's perspective: the Engineer is entitled to refuse Taking-Over where the Works contain material defects — not merely snags — that prevent use of the building for its intended purpose. Structural defects, fire system failures, utility connection failures, and major MEP commissioning failures are legitimate grounds for refusal. Minor cosmetic defects are not grounds for refusal, and issuing a Taking-Over Certificate with a snag list is the standard approach for projects with minor outstanding items.
The Completion Certificate (Taking-Over Certificate) in a UAE construction contract triggers the release of the first tranche of contractual retention, typically 50% of the total retention withheld. The second tranche is released at the end of the Defects Notification Period (DLP) upon issue of the Performance Certificate by the Engineer.
The standard UAE market structure for a 5% retention on a lump-sum contract is: the Employer withholds 5% from each interim payment certificate throughout construction; on issue of the Taking-Over Certificate, 2.5% (the first half) is released; on satisfactory completion of the DLP and issue of the Performance Certificate, the remaining 2.5% is released. This structure is aligned with FIDIC Red Book and Yellow Book conditions and is respected by the Dubai Courts and the Abu Dhabi Judicial Department as a commercially reasonable retention mechanism.
The Contractor has a contractual and legal right to the first retention tranche on issue of the Taking-Over Certificate. Failure by the Employer to release this tranche promptly — typically within 14 days of the certificate date — gives the Contractor a right to interest on the overdue amount under Art. 76 of the Commercial Transactions Law (Federal Decree-Law No. 50 of 2022) at the Central Bank of the UAE rate.
For larger projects, UAE banks and finance houses sometimes issue retention bonds in lieu of cash retention — the Contractor provides a bank guarantee from a Central Bank of the UAE licensed bank in lieu of withholding cash, allowing the Contractor to maintain positive cash flow. Retention bonds must be on terms acceptable to the Employer and must remain valid through the end of the DLP plus an additional grace period for Performance Certificate release.
Sectional completion is expressly recognised in FIDIC-style construction contracts in the United Arab Emirates and in the UAE Civil Code (Federal Law No. 5 of 1985). Where the main contract provides for the Works to be completed in defined sections — each section having its own Time for Completion, delay liquidated damages rate, and Taking-Over provisions — the Engineer may issue a Taking-Over Certificate for each section as it is completed, without waiting for the entire project to be finished.
Sectional Taking-Over is practically important for large UAE projects such as phased residential developments, hospital campuses, and multi-building mixed-use schemes, where the Employer wishes to occupy and use completed buildings while construction of remaining buildings continues. RERA (Real Estate Regulatory Agency) in Dubai requires sectional handover records for phased off-plan developments so that unit purchasers can take delivery of their units as each phase is completed.
The legal consequences of sectional Taking-Over are the same as for whole-works Taking-Over, but apply only to the section taken over: risk of care passes to the Employer for that section; the DLP commences for that section; delay liquidated damages for late completion of that section cease; and the ten-year decennial liability period under Art. 880 of the UAE Civil Code (Federal Law No. 5 of 1985) begins for that section from the section's Taking-Over date.
Retention under a sectional Taking-Over is typically released on a pro-rata basis calculated by reference to the Contract Price attributable to the section taken over. The main contract must contain clear provisions allocating the Contract Price between sections and specifying the retention release mechanism for sectional Taking-Over; in the absence of such provisions, the Dubai Courts and DIAC arbitration panels determine the appropriate pro-rata release.
A Completion Certificate (Taking-Over Certificate) on a UAE construction project is typically accompanied by a package of handover documentation that the Contractor must assemble and deliver to the Employer as a condition of or simultaneously with the Taking-Over inspection. The composition of the handover package is usually specified in the main contract's Schedule of Submittals or in the Employer's Requirements.
Operation and Maintenance (O&M) manuals are required for all installed plant and equipment — HVAC systems, electrical distribution boards, fire systems, lift installations, building management systems, plumbing, and specialist equipment. Each manual should include equipment schedules, manufacturer's data sheets, commissioning test results, and maintenance schedules. Without O&M manuals, the Employer's facilities management team cannot maintain the building effectively after handover.
As-built drawings must record the actual installed positions of all structural, MEP, and civil works as they were constructed, reflecting any changes made during construction from the approved permit drawings. As-built drawings are required by the Dubai Building Permit Authority (BPA) for updating municipal records, and by DEWA and ADDC for updating utility network records.
Regulatory approvals — the Dubai Municipality completion certificate (or Abu Dhabi DMT equivalent), the UAE Civil Defence Authority NOC, the DEWA/ADDC connection approval, and the Lift Authority certificate — must be assembled and provided in hard copy and electronic form.
Warranty and guarantee certificates from equipment manufacturers (typically 12-24 months) should be assigned to the Employer on Taking-Over. Specialist systems — curtain walls, waterproofing membranes, roofing — typically carry separate manufacturer's warranties. Test and commissioning records for all MEP systems must be provided, together with certificates of compliance with applicable UAE standards. Insurance certificates covering the Contractor's ongoing obligations during the DLP must also be confirmed as valid.
This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer
Found an error? Let us knowRelated Documents
You may also find these documents useful:
Construction Contract (FIDIC-Style) (UAE)
A FIDIC-style lump-sum construction contract for UAE projects, incorporating muqawala provisions under Arts 872-896 of the UAE Civil Code (Federal Law No. 5 of 1985), Art. 880 decennial liability, VAT under Federal Decree-Law No. 8 of 2017, and DIAC arbitration. Covers Employer, Contractor, Engineer, performance security, defects, and variations.
Snagging & Defects Liability Agreement (UAE)
A UAE snagging and defects liability agreement executed after Taking-Over, documenting outstanding items and the Contractor's rectification obligations under the UAE Civil Code (Federal Law No. 5 of 1985). Covers the snag register, rectification period, retention release, third-party remedy rights, and Art. 880 decennial liability preservation.
Variation Order (Construction) (UAE)
A UAE construction Variation Order (VO) instructed by the Engineer under Art. 887 of the UAE Civil Code (Federal Law No. 5 of 1985) for lump-sum contract changes, recording scope, valuation (Bill of Quantities rates or Engineer's determination), Extension of Time, adjusted Contract Price, and VAT under Federal Decree-Law No. 8 of 2017.
Construction Subcontract (UAE)
A back-to-back construction subcontract for UAE projects, flowing down obligations from the main contract under the UAE Civil Code (Federal Law No. 5 of 1985), Arts 872-896 muqawala. Covers scope, payment, retention, delay damages, decennial liability under Art. 880, and dispute resolution through DIAC or UAE courts.
MEP Works Contract (UAE)
A UAE MEP works contract for mechanical, electrical, and plumbing installation projects, covering design (where applicable), supply, testing, commissioning, and handover. Governed by the UAE Civil Code (Federal Law No. 5 of 1985) Arts 872-896, with Art. 880 decennial liability, DEWA/ADDC commissioning requirements, UAE Civil Defence NOC, and VAT under Federal Decree-Law No. 8 of 2017.