Plumbing Contract (Ireland)
PLUMBING AND GAS INSTALLATION CONTRACT
Date: [Contract Date]
PARTIES
This Contract is entered into between:
(1) [Contractor Name], of [Contractor Address], Tel: [Contractor Phone], Email: [Contractor Email], RGII Registration No. [RGI Number], CIS No. [CIS Number] (the "Contractor"); and
(2) [Client Name], of [Client Address], Tel: [Client Phone] (the "Client").
1. WORKS
1.1 The Contractor agrees to carry out the following works at [Works Address] (the "Works"):
[Works Description]
1.2 Materials: [Materials Supply].
1.3 The Works shall commence on approximately [Start Date] and shall be substantially completed by [Completion Date], subject to any delays caused by circumstances beyond the Contractor's control.
2. REGULATORY COMPLIANCE
2.1 All gas installation and servicing works shall be carried out by an installer registered with the Register of Gas Installers of Ireland (RGII) and shall comply with:
(a) I.S. 813:2014 — Domestic Gas Installations (as amended);
(b) The Gas Safety (Installations and Use) Regulations (S.I. No. 686 of 2002);
(c) Gas Networks Ireland network and meter standards.
2.2 All water supply and drainage works shall comply with Irish Water Connection Conditions, the Building Regulations 2011 (Part H — Drainage and Waste Water Disposal) and the Water Services Act 2007.
2.3 On completion of gas works, the Contractor shall provide the Client with a Completion Certificate / Certificate of Conformance confirming compliance with I.S. 813:2014.
3. PRICE AND PAYMENT
3.1 The Contract Price for the Works is [Contract Price].
3.2 Payment terms: [Deposit Amount].
3.3 Plumbing and heating installation services are subject to VAT at the reduced rate of 13.5% under Schedule 3 of the Value-Added Tax Consolidation Act 2010. All prices stated include VAT unless otherwise specified.
3.4 The Contractor shall provide a valid VAT invoice to the Client upon completion of the Works or at such other time as agreed.
4. WARRANTIES AND LIABILITY
4.1 The Contractor warrants that the Works shall be carried out with reasonable skill and care, using suitable materials, in compliance with the Sale of Goods and Supply of Services Act 1980.
4.2 The Contractor shall maintain public liability insurance of not less than €2,600,000 for any one occurrence and employer's liability insurance as required by the Employees (Employers' Liability) (Compulsory Insurance) Act 1969.
4.3 Nothing in this Contract excludes or limits the Contractor's liability for death or personal injury caused by the Contractor's negligence, or for any other liability that cannot be limited under Irish law.
5. TERMINATION AND DISPUTES
5.1 Either party may terminate this Contract by 7 days' written notice if the other party commits a material breach and fails to remedy it within the notice period.
5.2 Disputes shall be referred in the first instance to negotiation between the parties. Unresolved disputes may be referred to the Construction Contracts Adjudication Service under the Construction Contracts Act 2013, or to the courts of Ireland.
5.3 This Contract shall be governed by and construed in accordance with the laws of Ireland.
SIGNED by the parties on [Contract Date].
Contractor
________________
Signature
Client
________________
Signature
What Is a Plumbing Contract (Ireland)?
A Plumbing Contract in Ireland sets the scope of works, price, programme, and payment terms for the building or installation project, and takes its legal force from the Goods and Supply of Services Act 1980.
For any work involving natural gas or LPG (liquefied petroleum gas) — including the installation or replacement of boilers, gas hobs, gas fires, gas pipework, and pressure testing — the contractor must be RGI-registered (Registered Gas Installers of Ireland). RGI is operated under the Gas Safety Regulations and requires all gas installers to hold appropriate qualifications, maintain insurance, and submit to periodic competency assessment. Only RGI-registered contractors may commission gas appliances, carry out gas tightness tests, and issue the mandatory commissioning certificates required by Gas Networks Ireland and by insurers.
For plumbing works involving connections to the public water supply (including new service connections, the installation of water meters, and works within the curtilage of the boundary), the contractor must comply with Irish Water's (Uisce Éireann's) Infrastructure Development requirements and technical standards under the Water Services Acts 2007 and 2012. Irish Water requires prior approval and connection agreements for new connections to the public water main.
The Sale of Goods and Supply of Services Act 1980 implies mandatory terms into every plumbing contract that the contractor has the necessary skill, will perform the work with due skill, care and diligence, and will use materials that are sound and reasonably fit for purpose. These implied warranties cannot be excluded in consumer contracts.
The Building Regulations (Parts G, H, and J) and the associated Technical Guidance Documents set the mandatory standards for water supply, drainage, and heating appliance installations in all buildings in Ireland. The Health and Safety Authority (HSA) and the Commission for Regulation of Utilities (CRU) jointly oversee the safety framework for gas installations.
The Safety, Health and Welfare at Work Act 2005 and the Construction Regulations (S.I. No. 291 of 2013) impose obligations on both the client and the contractor in relation to health and safety on construction sites. For larger plumbing and heating projects, the client may be required to appoint a Project Supervisor for the Design Process (PSDP) and a Project Supervisor for the Construction Stage (PSCS) under the Construction Regulations. The plumbing contractor, as a principal contractor or a subcontractor, must comply with all applicable health and safety requirements and must have a current Safety Statement under section 20 of the Safety, Health and Welfare at Work Act 2005. A thorough plumbing contract should confirm the contractor's compliance with the Construction Regulations and their obligation to cooperate with the PSCS where one is appointed. For domestic clients, the Home Building Competence Scheme and the Building Control (Amendment) Regulations 2014 (S.I. No. 9 of 2014) have introduced greater accountability and certification requirements for construction works in Ireland, including plumbing and mechanical services. Under the 2014 Regulations, the builder and the assigned certifier are required to provide a Certificate of Compliance on Completion, and all inspections (including of services installations) must be carried out in accordance with the agreed inspection plan. Plumbing contractors working on new builds or substantial extensions must be prepared to cooperate with the assigned certifier and to provide all records and test certificates required to support the Certificate of Compliance on Completion.
When Do You Need a Plumbing Contract (Ireland)?
An Irish Plumbing Contract is needed whenever a property owner, developer, or main contractor engages a plumbing or gas contractor to install, alter, maintain, or repair plumbing, drainage, or heating systems in a property. A written contract protects both parties by documenting the agreed scope, price, standards, and programme, and by establishing the contractor's certification and warranty obligations.
You need a Plumbing Contract when you are: commissioning the plumbing fit-out of a new dwelling or commercial building, including all cold and hot water supply, drainage, and sanitary ware; engaging a plumber to install or replace a central heating system (gas boiler, heat pump, or oil boiler); replacing or upgrading a gas boiler, water heater, or gas hob; installing a new bathroom, en-suite, or utility room; carrying out an extension or renovation requiring new plumbing, heating, or drainage; commissioning a gas connection or upgrading gas pipework; or engaging a contractor for any significant plumbing or heating works where the scope, price, and RGI registration status need to be documented clearly.
From the client's perspective, the plumbing contract must confirm the contractor's RGI registration (where gas work is involved), define the scope of works precisely (including the fixtures and fittings to be supplied or fitted), specify the required testing and commissioning procedures, and set out the contractor's obligation to issue all required certificates (RGI commissioning certificate, gas tightness test certificate, and — for new connections — Irish Water connection approval documentation).
From the contractor's perspective, the contract documents the agreed price and scope, establishes the client's obligations (including providing access, installing required service connections, and making prompt decisions), provides a basis for claiming additional payments for variations or unforeseen conditions in the existing installation, and protects the contractor against claims for delay caused by the client or other trades.
For properties being sold or let, properly certified plumbing and gas installations are essential. The Building Energy Rating (BER) certificate required for all properties sold or let under the European Communities (Energy Performance of Buildings) Regulations 2012 takes into account the efficiency of the heating system, and prospective buyers and tenants will require evidence that all gas and plumbing installations are certified as safe and compliant.
For residential rental properties, the landlord has additional obligations in relation to gas and plumbing installations. Under the Housing (Standards for Rented Houses) Regulations 2019 (S.I. No. 137 of 2019), every rented dwelling must have a properly functioning heating system capable of providing a room temperature of at least 18 degrees Celsius, and the dwelling must be maintained in good structural condition with all services in good repair. A landlord who engages a plumbing contractor to install, repair, or replace heating or plumbing systems in a rented property should retain the contractor's commissioning certificates, gas safety records, and any Irish Water approval documentation as evidence of compliance with the 2019 Regulations. Under the Residential Tenancies Acts 2004–2024, tenants may refer disputes about the condition of the dwelling — including failures of the heating or plumbing system — to the Residential Tenancies Board (RTB) for dispute resolution.
Under the Companies Act 2014, the Companies Registration Office (CRO) maintains the register of Irish companies. Section 343 of the Companies Act 2014 sets annual confirmation obligations. The Competition and Consumer Protection Commission (CCPC) enforces the Consumer Rights Act 2022. The Central Bank of Ireland regulates financial services under the Central Bank Act 1971. The High Court of Ireland has jurisdiction under Section 212 of the Companies Act 2014.
What to Include in Your Plumbing Contract (Ireland)
A thorough Irish Plumbing Contract should include the following key provisions.
The parties clause identifies the client and the plumbing contractor, including the contractor's RGI registration number (where gas works are included), CRO number if the contractor is a company, and confirmation of the contractor's public liability and employers' liability insurance cover.
The scope of works clause defines in detail the plumbing and heating works to be carried out, specifying the systems to be installed or altered (cold water, hot water, central heating, gas, drainage), the fixtures and fittings to be supplied and fitted, and any exclusions (such as tiling around sanitary ware or making good after chasing walls, which may be carried out by other trades). Precise scoping reduces the risk of disputes about what is and is not included in the agreed price.
The standards and compliance clause requires the contractor to carry out all works in accordance with the current BSEN standards applicable to plumbing and gas installations (including I.S. 813 for domestic gas installations), the Building Regulations (Parts G, H, and J), TGD G, TGD H, and TGD J, the Gas Safety Regulations, and all Irish Water technical standards and connection requirements.
The price and payment clause specifies the agreed contract price (inclusive or exclusive of VAT at the applicable rate — standard rate 23% or reduced rate 13.5% for qualifying works under the VAT Consolidation Act 2010), the payment schedule (for example, staged payments on completion of defined milestones), and the basis for pricing any additional or varied works arising during the project. The contract should specify the mechanism for agreeing and authorising variations in advance to avoid post-completion disputes about additional costs.
The programme clause should specify the agreed start date, the programme of works, and the target completion date. Where the client requires the works to be completed by a specific date (for example, before a house sale or a new tenancy commences), this should be expressly stated and the consequences of delay addressed.
The certification clause requires the contractor to carry out all required pressure testing and commissioning procedures, to issue an RGI commissioning certificate (for gas works), to provide a gas tightness test certificate, and to submit all required documentation to Gas Networks Ireland and Irish Water as applicable.
The defects liability clause requires the contractor to remedy any defects in the installation appearing within the defects liability period (typically 12 months after completion) at the contractor's own cost, distinguishing between defects in workmanship and faults in manufacturer-supplied equipment covered by product warranties. The contract should specify the procedure for notifying defects and the timeframe for remediation.
The insurance clause requires the contractor to maintain public liability insurance of at least EUR 2.5 million per occurrence and employers' liability insurance of at least EUR 13 million, and to produce evidence of cover on request.
The dispute resolution clause should specify that any disputes arising from the contract will first be referred to negotiation between the parties, then to mediation under the Mediation Act 2017, and ultimately to the Irish courts (District Court for claims up to EUR 15,000, Circuit Court for claims up to EUR 75,000, or the High Court for larger claims). The governing law clause confirms the contract is governed by the laws of Ireland. Under the European Communities (Late Payment in Commercial Transactions) Regulations 2012 (S.I. No. 580 of 2012), implementing EU Directive 2011/7/EU, the contractor is entitled to statutory interest at 8 percentage points above the ECB reference rate on late payments by business clients, plus a fixed compensation of EUR 40 per late invoice. For VAT purposes, qualifying energy-efficient heating and insulation works carried out on qualifying residential properties attract VAT at the reduced rate of 9% under section 86 of the Value-Added Tax Consolidation Act 2010, rather than the standard 13.5% rate for general construction services — the contract should confirm the correct VAT rate applicable to the works. The forms-legal.com Plumbing Contract (Ireland) template covers the mandatory elements under Companies Act 2014.
Cite this page
Reference this free template in an article, syllabus, or research note:
Forms Legal. (2026). Plumbing Contract (Ireland) (Ireland) [Legal document template]. Forms Legal. https://forms-legal.com/ireland/business/construction/plumbing-contract-ireland
"Plumbing Contract (Ireland) (Ireland)." Forms Legal, 2026, https://forms-legal.com/ireland/business/construction/plumbing-contract-ireland.
@misc{formslegal-plumbing-contract-ireland,
author = {{Forms Legal}},
title = {Plumbing Contract (Ireland) (Ireland)},
year = {2026},
howpublished = {\url{https://forms-legal.com/ireland/business/construction/plumbing-contract-ireland}},
note = {Free legal document template. Based on Companies Act 2014}
}Also available for these jurisdictions:
Frequently Asked Questions
RGI (Registered Gas Installers of Ireland) is the statutory register of competent gas installers in Ireland, operated by the Commission for Regulation of Utilities (CRU, formerly CER) under the Gas Safety Regulations and the Gas Act 1976 (as amended). RGI registration is mandatory for any contractor carrying out gas installation, maintenance, or repair work on natural gas or LPG (liquefied petroleum gas) appliances, pipework, and systems in Ireland. The legal basis for RGI registration derives from the Gas Safety Regulations (S.I. No. 246 of 2002, as amended by S.I. No. 329 of 2009 and subsequent instruments) and European gas safety standards. Gas Networks Ireland (GNI) — the operator of the natural gas distribution network in Ireland — requires that all gas connection work and all work on gas installations connected to the national grid be carried out only by RGI-registered contractors. An RGI-registered contractor who carries out gas work and issues a certification that the installation is safe is legally responsible for the safety of that installation. To become RGI-registered, a contractor must hold appropriate gas industry qualifications (typically a City and Guilds or FETAC qualification in gas fitting or plumbing with a gas endorsement), pass a technical assessment, maintain adequate public liability insurance (minimum EUR 2 million), agree to abide by the RGI Code of Practice, and submit to periodic surveillance assessment.
Irish Water (Uisce Éireann) is the national water utility responsible for the provision of public water supply and wastewater services in Ireland. Plumbing contractors must comply with Irish Water's technical standards and bye-laws when carrying out works that connect to or affect the public water supply system. Under the Water Services Acts 2007 and 2012 (as amended), Irish Water has statutory responsibility for the public water supply network. The Water Services (No. 2) Act 2013 established Irish Water and transferred water services functions from local authorities. Plumbing contractors who carry out new connections to the public water main, install or alter water service connections, or install water meters must comply with Irish Water's Infrastructure Development requirements and obtain the relevant approvals from Irish Water before commencing work. For new building connections, the contractor must apply to Irish Water for a connection agreement, which sets out the technical requirements for the water service connection — including the diameter of the connection, the location of the boundary box and meter, the materials to be used, and the reinstatement requirements. Irish Water's Standard Details for Water Service Connections must be followed. Failure to comply with these requirements can result in the refusal of a connection or the requirement to relay non-compliant work at the contractor's cost. The Water Supply (Water Quality) Regulations 2014 (implementing the EU Drinking Water Directive) set quality standards for drinking water.
A plumber carrying out work for a homeowner in Ireland owes several implied and express warranties under Irish law, primarily derived from the Sale of Goods and Supply of Services Act 1980, the general law of negligence, and any express terms of the plumbing contract. Under section 39 of the Sale of Goods and Supply of Services Act 1980, where a supplier supplies a service in the course of a business, there is an implied warranty that: (a) the supplier has the necessary skill to render the service; (b) the service will be supplied with due skill, care and diligence; and (c) where materials are used, those materials will be sound and reasonably fit for the purpose for which they are required. These implied terms cannot be excluded or limited by contract terms in consumer contracts. Any attempt by a contractor to include a clause in the contract limiting or excluding these statutory warranties in a consumer context would be void under section 40 of the 1980 Act and the Unfair Contract Terms Directive. In negligence, the plumber owes a duty of care to the homeowner and to any third parties who may foreseeably be affected by defective plumbing or gas installations. Where a burst pipe, a gas leak, or a defective central heating installation causes water damage, fire, or personal injury, the plumber may be liable in negligence for all foreseeable loss flowing from the breach of their duty of care. For gas work, the RGI-registered contractor who issues a commissioning certificate is also making a statutory representation that the gas installation is safe.
Water damage caused by a plumber's negligence is a common source of claims in Ireland, and the legal principles governing liability are well established. The claim may be founded in negligence (the tort of negligence), breach of contract (the implied terms under the Sale of Goods and Supply of Services Act 1980), or both. In negligence, the claimant must establish that: (1) the plumber owed them a duty of care (which is readily established where the plumber is carrying out work on the claimant's property); (2) the plumber breached that duty by failing to exercise the standard of care of a competent plumber; (3) the breach caused the damage; and (4) the damage was not too remote. The standard of care is assessed by reference to what a competent plumber with the skill and qualifications reasonably to be expected of the contractor would have done — a standard informed by BSEN standards, manufacturer installation guidelines, and good trade practice. Common causes of plumbing-related water damage claims include failure to adequately test joints and connections before covering them (leading to concealed leaks discovered only after damage has occurred), incorrect installation of appliances (washing machines, dishwashers, boilers) resulting in flooding, failure to properly isolate the water supply before removing fittings, and poor quality materials or fittings that fail prematurely.
Yes. Plumbing works in Ireland are subject to the Building Regulations and the Building Control Acts 1990 and 2007, as well as associated Technical Guidance Documents. Several parts of the Building Regulations are specifically relevant to plumbing and drainage installations. Part H of the Building Regulations — Drainage and Waste Water Disposal — sets requirements for the design and installation of drainage systems, including below-ground drainage, branch drainage, stacks, ventilation of drainage systems, and connection to sewers. The Technical Guidance Document H (TGD H) provides detailed guidance on the minimum acceptable standards for drainage design, pipe sizes, gradients, access points, and materials. Part G of the Building Regulations — Hygiene — sets requirements for the provision of sanitary facilities, hot and cold water supply, and the prevention of contamination of the water supply. TGD G requires the provision of an adequate supply of wholesome water to every dwelling and building, the separation of foul and surface water drainage, and the prevention of contamination by back-siphonage. Part J of the Building Regulations — Heat Producing Appliances — sets requirements for the installation of heating appliances (boilers, water heaters, ranges, and flues). TGD J requires that all heating appliances be installed in accordance with the manufacturer's instructions and with reference to I.S. 813 (Domestic Gas Installations), and that flues and chimneys be properly sized and constructed to ensure safe discharge of combustion products.
This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer
Found an error? Let us knowRelated Documents
You may also find these documents useful:
Building Contract (Ireland)
A contract between a client and a building contractor for construction works in Ireland, compliant with the Construction Contracts Act 2013.
Electrical Works Contract (Ireland)
A contract for electrical installation and works in Ireland by a RECI-registered electrician, compliant with the Electricity Regulation Act 1999 and ETCI National Rules.
Subcontractor Agreement (Ireland)
A contract between a main contractor and a subcontractor for specialist construction works in Ireland, compliant with the Construction Contracts Act 2013.
Scope of Works (Ireland)
A document defining the scope, specifications, and deliverables for a construction project in Ireland, compliant with the Construction Contracts Act 2013.
Service Agreement (Ireland)
A contract for the provision of professional or commercial services between a provider and a client in Ireland.