Skip to main content

Work Order (England & Wales)

Work Order

Work Order No.: [Work Order Number]

Date: [Work Order Date]

1. PARTIES

This Work Order is issued by [Client Name] ([Client Type]), of [Client Address], [Client City], [Client Postcode], England and Wales (the "Client") to [Contractor Name], of [Contractor Address], [Contractor City], [Contractor Postcode], England and Wales (the "Contractor").

Company Registration No. (if applicable): [Contractor Registration]

The Client and the Contractor are together referred to as the "Parties". Nothing in this Work Order is intended to confer any benefit on any third party pursuant to the Contracts (Rights of Third Parties) Act 1999.

2. SITE

The works shall be carried out at: [Site Address], [Site City], [Site Postcode] (the "Site").

3. DESCRIPTION OF WORKS

The Contractor agrees to carry out and complete the following works (the "Works"):

[Works Description]

Category of Works: [Works Category]

Building Regulations Approval Required: [Building Regulations Required]

Where Building Regulations approval is required under the Building Regulations 2010 (SI 2010/2214), the Contractor shall be responsible for obtaining all necessary building control approvals, inspections, and completion certificates unless otherwise agreed in writing. The Contractor shall ensure that all Works comply with the relevant Parts of Schedule 1 to the Building Regulations 2010.

4. PROGRAMME

Commencement Date: [Commencement Date]

Date for Completion: [Completion Date]

Time for completion of the Works is important to the Client. The Contractor shall proceed with the Works regularly and diligently and shall complete the Works by the Date for Completion.

5. CONTRACT SUM AND PAYMENT

The total contract sum for the Works is £[Contract Sum] (pounds sterling), [Vat Applicable] as to VAT. Payment shall be made in accordance with the following schedule: [Payment Schedule].

All invoices are payable within [Payment Terms Days] days of receipt. Interest on late payments shall accrue at 8% per annum above the Bank of England base rate in accordance with the Late Payment of Commercial Debts (Interest) Act 1998 (for commercial contracts) or at the statutory rate for consumer contracts.

Under the Housing Grants, Construction and Regeneration Act 1996 (as amended by the Local Democracy, Economic Development and Construction Act 2009), the Contractor is entitled to give a Payment Notice and a Pay Less Notice in accordance with that Act. The pay-due date and final date for payment shall be as set out in this Work Order. Where this Work Order does not comply with the requirements of Part II of the Housing Grants Act 1996, the Scheme for Construction Contracts (England and Wales) Regulations 1998 (SI 1998/649) shall apply as implied terms.

6. VARIATIONS

Variation procedure: [Variations Procedure]. No variation to the Works shall be valid unless authorised in accordance with the agreed variation procedure. The Contractor shall not carry out any varied or additional works without written authorisation from the Client. Any authorised variation shall entitle the Contractor to a reasonable adjustment to the Contract Sum and, where appropriate, the Date for Completion.

7. HEALTH AND SAFETY

The Contractor shall comply with all applicable health and safety legislation including the Health and Safety at Work etc. Act 1974, the Management of Health and Safety at Work Regulations 1999 (SI 1999/3242), and the Construction (Design and Management) Regulations 2015 (SI 2015/51) ("CDM 2015").

CDM 2015 Notifiable Project: [Cdm Applies].

8. DEFECTS LIABILITY PERIOD

The Defects Liability Period shall be [Defects Liability Period] commencing from the date of Practical Completion. During this period, the Contractor shall return to the Site and make good at the Contractor's own expense any defects, shrinkages, or other faults that appear and that are due to materials or workmanship not in accordance with this Work Order.

9. INSURANCE

The Contractor shall maintain throughout the Works: (a) public liability insurance with a minimum indemnity limit of £[Public Liability Amount] per occurrence; (b) employers' liability insurance of at least £5,000,000 as required by the Employers' Liability (Compulsory Insurance) Act 1969; and (c) all-risks insurance for the Works and materials on site. The Contractor shall provide the Client with copies of current insurance certificates on request.

10. GENERAL TERMS

(a) Materials and Workmanship. All materials shall be of satisfactory quality and fit for purpose in accordance with the Sale of Goods Act 1979 (as applied to contracts for work and materials) and the Supply of Goods and Services Act 1982. All workmanship shall be carried out in a good and workmanlike manner and to the reasonable satisfaction of the Client.

(b) Compliance with Laws. The Contractor shall comply with all applicable legislation including, without limitation, the Health and Safety at Work etc. Act 1974, the Building Regulations 2010, the Equality Act 2010, and all applicable environmental legislation.

(c) Entire Agreement. This Work Order constitutes the entire agreement between the Parties in relation to the Works and supersedes all prior negotiations and correspondence. Any modification must be in writing signed by both Parties.

(d) Third Party Rights. Nothing in this Work Order confers any right on any third party under the Contracts (Rights of Third Parties) Act 1999.

11. GOVERNING LAW

This Work Order shall be governed by and construed in accordance with the laws of England and Wales. Any disputes arising out of or in connection with this Work Order shall be subject to the jurisdiction of the courts of England and Wales. Nothing in this clause prevents either Party from seeking adjudication under the Housing Grants, Construction and Regeneration Act 1996.

AGREED AND ACCEPTED by the Parties on the date first written above.

CLIENT

Name: [Client Name]

Address: [Client Address], [Client City], [Client Postcode]

CONTRACTOR

Name: [Contractor Name]

Address: [Contractor Address], [Contractor City], [Contractor Postcode]

Client

________________

Signature

Date: ________________

Contractor

________________

Signature

Date: ________________

Maintained by Vladislav Sergienko, Founder·Template last modified: ·Report an error

What Is a Work Order (England & Wales)?

A Work Order in the United Kingdom sets the scope of works, price, programme, and payment terms for the building or installation project, as regulated by the Construction and Regeneration Act 1996.

The principal statute governing payment in construction contracts is the Housing Grants, Construction and Regeneration Act 1996 (as amended by the Local Democracy, Economic Development and Construction Act 2009). This legislation applies to 'construction contracts' as defined in section 104, which includes contracts for the carrying out of construction operations, arranging for such operations, and providing labour for construction. The Act grants contractors the right to periodic payments, the right to suspend performance for non-payment, and access to adjudication as a fast-track dispute resolution mechanism.

For the design and safety management of construction projects, the Construction (Design and Management) Regulations 2015 (SI 2015/51) — the CDM Regulations — establish a thorough framework of duties for clients, designers, and contractors. Every construction project is subject to CDM 2015 to some degree, with larger notifiable projects requiring the formal appointment of a Principal Designer and Principal Contractor.

The Building Regulations 2010 (SI 2010/2214) set out the technical standards that building work must meet in England and Wales, covering structural integrity, fire safety, drainage, energy efficiency, accessibility, and other aspects of building performance. Works that are subject to the Building Regulations must be approved by a building control body — either the local authority or an approved inspector.

For standard-form construction contracts in the UK, the Joint Contracts Tribunal (JCT) publishes a widely used suite of contract documents, including the JCT Minor Works Building Contract, the JCT Standard Building Contract, and the JCT Design and Build Contract. This Work Order is drafted on principles consistent with the JCT Minor Works framework, but as a standalone document suitable for smaller construction and maintenance projects.

The legal framework governing the Work Order (England & Wales) in United Kingdom draws on several key statutes and regulatory bodies. Under the Companies Act 2006, Companies House maintains the register of UK companies. Section 386 of the Companies Act 2006 sets accounting record obligations. The Competition and Markets Authority (CMA) enforces the Consumer Rights Act 2015. The Financial Conduct Authority (FCA) regulates financial services under the Financial Services and Markets Act 2000. The High Court of Justice has jurisdiction under the Senior Courts Act 1981. Parties executing a Work Order (England & Wales) in United Kingdom should confirm the document reflects current law, including any amendments enacted since the original drafting date. The Companies Act 2006 sets the foundational requirements.

When Do You Need a Work Order (England & Wales)?

A Work Order is needed whenever a client wishes to commission construction or maintenance work from a contractor in England or Wales and wishes to document the scope, price, programme, and terms of the engagement in a formal written record. A Work Order serves as both the instruction to proceed and the contractual framework for the works.

Work Orders are appropriate for a wide variety of scenarios, including: a commercial property owner commissioning a contractor to carry out repairs or refurbishment; a facilities manager authorising maintenance works at a managed property; a residential developer commissioning a subcontractor to carry out specialist trade work; a retail business commissioning a fit-out contractor; or a housing association commissioning planned maintenance works across a portfolio of properties.

For small to medium-sized projects (typically below £500,000), a Work Order provides all the essential contractual protections without the administrative complexity of a full JCT Standard Building Contract. It is suitable for projects where a detailed architect's specification or bill of quantities has been prepared and can be annexed to the Work Order, or where the works can be adequately described in a short narrative description.

From the contractor's perspective, a signed Work Order provides clear evidence of the client's instruction, the agreed price, the payment terms, and the programme. This is essential if the contractor later needs to enforce payment under the Housing Grants Act 1996 or bring a claim for unpaid sums. Without a written work order or contract, contractors may find it difficult to recover the full value of work carried out if a dispute arises.

From the client's perspective, a Work Order provides the basis for managing the contractor's performance against agreed timescales and specifications, imposing liquidated damages for delay, withholding retention, and enforcing the defects liability provisions. It is also an essential document for any insurance claim arising from the works.

What to Include in Your Work Order (England & Wales)

A legally compliant Work Order for use in England and Wales must address several key elements to confirm it provides adequate protection for both parties and complies with the relevant statutory requirements.

The parties section should identify the client and the contractor with precision, including their full legal names, addresses, and (for limited companies) Companies House registration numbers. The site address where the works will be carried out should be clearly distinguished from the parties' registered addresses.

The description of works is the most important element of the Work Order and should leave no room for ambiguity. A vague or incomplete specification is the most common cause of disputes in construction contracts. The description should specify the materials to be used (including any relevant British Standards), the method of construction, the extent of the works, and any interfaces with existing structures or services. For works involving structural alterations, the relevant parts of the Building Regulations 2010 should be referenced.

The programme section must specify the commencement date and the date for completion. The inclusion of a liquidated damages clause is strongly recommended for any project where delay would cause measurable financial harm to the client. The rate must represent a genuine pre-estimate of loss to be enforceable under English law following Cavendish Square Holding BV v Talal El Makdessi [2015] UKSC 67.

The payment provisions must comply with Part II of the Housing Grants, Construction and Regeneration Act 1996. This means providing for periodic payments where the contract period exceeds 45 days, specifying the payment due dates, and providing for the issuance of Payment Notices and Pay Less Notices. Where the Work Order does not adequately address these requirements, the Scheme for Construction Contracts (England and Wales) Regulations 1998 will apply as implied terms.

The defects liability period and retention provisions protect the client's interests after practical completion. The health and safety section addresses the parties' obligations under CDM 2015 and the Health and Safety at Work etc. Act 1974. The insurance section confirms that the contractor maintains adequate cover throughout the project.

Additional compliance elements for a Work Order (England & Wales) used in United Kingdom include: Under the Companies Act 2006, Companies House maintains the register of UK companies. Section 386 of the Companies Act 2006 sets accounting record obligations. The Competition and Markets Authority (CMA) enforces the Consumer Rights Act 2015. The Financial Conduct Authority (FCA) regulates financial services under the Financial Services and Markets Act 2000. The High Court of Justice has jurisdiction under the Senior Courts Act 1981. Forms-legal.com provides this template as a starting point for United Kingdom-compliant documentation.

Cite this page

Reference this free template in an article, syllabus, or research note:

APA

Forms Legal. (2026). Work Order (England & Wales) (United Kingdom) [Legal document template]. Forms Legal. https://forms-legal.com/uk/business/contracts/work-order-uk

MLA

"Work Order (England & Wales) (United Kingdom)." Forms Legal, 2026, https://forms-legal.com/uk/business/contracts/work-order-uk.

BibTeX
@misc{formslegal-work-order-uk,
  author       = {{Forms Legal}},
  title        = {Work Order (England & Wales) (United Kingdom)},
  year         = {2026},
  howpublished = {\url{https://forms-legal.com/uk/business/contracts/work-order-uk}},
  note         = {Free legal document template. Based on Companies Act 2006}
}

Also available for these jurisdictions:

Frequently Asked Questions

Based on Companies Act 2006 — Template last modified June 2026Verify the source →

This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer

Found an error? Let us know