Change Order Agreement (UAE)
CHANGE ORDER AGREEMENT
Change Order No.: [Change Order Number]
Dated: [Change Order Date]
Service Provider / Contractor: [Provider Name] (the "Service Provider");
Client: [Client Name] (the "Client").
Original contract: [Original Contract] (the "Original Agreement").
1. CHANGE DESCRIPTION AND REASON
1.1 Description of the change: [Change Description].
1.2 Reason for the change: [Reason for Change].
2. IMPACT ON SCOPE, TIMELINE AND FEE
2.1 Impact on scope and deliverables: [Scope Impact].
2.2 Impact on project timeline: [Timeline Impact].
2.3 Additional fee for this Change Order: [Additional Fee].
2.4 Revised total contract value: [Cumulative Fee].
2.5 All amounts are subject to Value Added Tax at the prevailing rate under the VAT Law (Federal Decree-Law No. 8 of 2017). The Service Provider shall issue valid tax invoices meeting Federal Tax Authority (FTA) requirements for each payment under this Change Order.
3. EFFECT ON ORIGINAL AGREEMENT AND GENERAL
3.1 [Effect on Original].
3.2 This Change Order, once signed by both parties, is a binding amendment to the Original Agreement under Article 257 of the UAE Civil Code (Federal Law No. 5 of 1985). No work outside this Change Order may be treated as authorised or billable unless agreed in a further written change order.
3.3 The Service Provider shall not commence any changed work until this Change Order has been signed by both parties.
3.4 This Change Order is governed by the laws of the United Arab Emirates. Disputes shall be resolved before the [Governing Forum].
Signed for and on behalf of the Service Provider: [Provider Name]
Signed for and on behalf of the Client: [Client Name]
Service Provider
________________
Signature
Client
________________
Signature
What Is a Change Order Agreement (UAE)?
A Change Order Agreement in the United Arab Emirates is a formal written amendment to an existing commercial or services contract — such as a Scope of Work Agreement, a Statement of Work, a Project Management Agreement, or a construction contract — that records an agreed variation to the original scope of work, the additional or reduced fee for the change, the revised project timeline, and the binding consent of both parties to the variation. Under Article 257 of the UAE Civil Code (Federal Law No. 5 of 1985), the contract is the law of the parties, and a Change Order Agreement signed by authorised representatives of both parties has the same binding force as the original contract it modifies. Article 246 requires performance in good faith, which obligates both the service provider and the client to act reasonably in evaluating, pricing, and implementing scope changes.
Change orders are the standard commercial mechanism for managing scope evolution on UAE projects of all types — construction, technology, consulting, and professional services. No project of any complexity proceeds from start to finish without changes to the original scope: client priorities shift, design decisions are made after contracts are signed, technical discoveries require approach changes, or regulatory requirements change mid-project. Without a formal change order process, these variations create disputes about whether additional work was authorised, whether it is included in the original price, and who bears the resulting schedule impact. The Dubai Courts and the Abu Dhabi Judicial Department regularly hear claims arising from uncontrolled scope change on UAE projects.
The legal framework governing UAE Change Order Agreements combines the Civil Code with the Commercial Transactions Law (Federal Decree-Law No. 50 of 2022), which supplements the Civil Code for commercial transactions between merchants and provides rules on commercial evidence and overdue interest under Articles 76 and 77. For construction contracts on major infrastructure projects, FIDIC forms of contract — used by authorities such as the Roads and Transport Authority (RTA), Abu Dhabi National Energy Company (TAQA), and Dubai Electricity and Water Authority (DEWA) — contain built-in variation procedures through which the Engineer issues variation instructions and the contractor claims additional time and cost. The Change Order Agreement template is suited to professional services, technology, and consulting projects where no built-in variation mechanism exists in the original contract.
Value Added Tax at 5% under the VAT Law (Federal Decree-Law No. 8 of 2017), administered by the Federal Tax Authority (FTA), applies to the additional taxable supply created by a change order, and the service provider must issue a supplemental tax invoice for each change order payment. The change order should state whether the additional fee is inclusive or exclusive of VAT. Electronic execution is valid under the Electronic Transactions and Trust Services Law (Federal Decree-Law No. 46 of 2021), and disputes are resolved by the Dubai Courts, the Abu Dhabi Judicial Department, the DIFC Courts, the ADGM Courts, or arbitration before the Dubai International Arbitration Centre (DIAC) under the Federal Arbitration Law (Federal Law No. 6 of 2018), applying the same forum as the original contract.
When Do You Need a Change Order Agreement (UAE)?
A Change Order Agreement in the United Arab Emirates is needed whenever the scope, timeline, or fee of an existing contract is varied by agreement between the service provider and the client, and both parties want a binding record of the change enforceable under the UAE Civil Code (Federal Law No. 5 of 1985). The change order prevents the most common professional services and construction dispute — unauthorised or unpriced scope change — by documenting the variation before work begins.
Additional scope requests are the most frequent trigger. A client that asks the service provider to add a new feature, a new deliverable, or a new phase to a technology or consulting project must sign a Change Order Agreement before the work begins, to confirm the price and the timeline extension. Without a signed change order, the service provider risks performing additional work for which it cannot collect payment before the Dubai Courts.
Scope reductions arise when a client needs to reduce the contracted scope to manage budget constraints. A Change Order Agreement recording the reduced scope and the corresponding reduction in fee protects both parties: the service provider is not obliged to deliver the removed items, and the client has a binding record of the price adjustment.
Specification changes — for example a change in the technical standard, the platform version, or the design specification — may appear minor but can significantly affect the service provider's costs and timeline. A Change Order Agreement records the change and prices it, preventing a later dispute about whether the revised approach was authorised at the original price.
Emergency and unforeseen-circumstances changes arise on construction and infrastructure projects in the UAE when sub-surface conditions, utility conflicts, or regulatory changes require adjustments to the original programme. The Change Order Agreement documents the instruction, the cause, and the agreed compensation, protecting both parties and providing the evidence required if a dispute reaches the Dubai International Arbitration Centre (DIAC) or the Abu Dhabi Judicial Department.
For projects funded by government or semi-government entities — including those under the supervision of the Ministry of Finance, the Abu Dhabi Department of Finance, or the Dubai Government — change orders typically require formal approval through the client's procurement governance process before being signed. The Change Order Agreement provides the document that triggers and records that approval.
What to Include in Your Change Order Agreement (UAE)
A UAE Change Order Agreement compliant with the UAE Civil Code (Federal Law No. 5 of 1985) and the Commercial Transactions Law (Federal Decree-Law No. 50 of 2022) must contain the following elements. The forms-legal.com UAE change order agreement template addresses each component in a structure accepted by the Dubai Courts, the Abu Dhabi Judicial Department, the DIFC Courts, and the ADGM Courts.
Party identification must record the names of the service provider and the client consistent with the original contract, so that the change order is clearly linked to the parties bound by the original agreement.
Original contract reference must identify the original agreement being varied — by title, date, and if applicable the Scope of Work or Statement of Work reference number — so that there is no ambiguity about which contract is being amended. A change order that does not clearly reference the original contract may be treated as a standalone agreement rather than an amendment.
Change order number must be a sequential reference — for example CO-001, CO-002 — that allows both parties to track the cumulative change orders issued on a project and to identify each change in correspondence and invoices.
Description of the change must state precisely what is being added, removed, or modified, referencing the relevant deliverable or section of the original contract. Vague change descriptions — 'additional work as discussed' — are unenforceable before the Dubai Courts because they do not establish what was agreed.
Reason for the change should record whether the change was requested by the client, required by a regulatory change, or necessitated by an unforeseen circumstance, to provide context for the impact on the original obligations.
Impact on scope and deliverables must describe the effect of the change on each affected deliverable, confirming what remains unchanged in the original contract.
Impact on timeline must state the revised target completion date or milestone dates resulting from the change, to avoid the service provider being held in delay for an extension that was not recorded.
Additional fee must state the price for the change in AED, the payment schedule, VAT treatment under the VAT Law (Federal Decree-Law No. 8 of 2017), and the revised total contract value including all previous change orders.
No-commencement clause must require the service provider not to start the changed work until both parties have signed the change order.
Effect on original agreement must confirm that all other terms of the original contract remain in force.
Governing law and forum must state UAE law and the same dispute resolution forum as the original contract, unless the parties expressly agree a different forum in the change order.
How to Fill Out Your Change Order Agreement (UAE)
Completing a Change Order Agreement for the United Arab Emirates is straightforward when the change has been clearly defined and priced before the template is filled. Work through the template in order.
Start with the parties and the original contract. Enter the names of the service provider and the client exactly as they appear in the original contract — consistency in party names is important for enforceability. Record the title, date, and reference number of the original agreement being varied. Assign the change order a sequential number — CO-001 if it is the first change, CO-002 if the second — and enter the date in DD/MM/YYYY format.
Describe the change precisely. State what is being added, removed, or modified and reference the specific deliverable or section of the original contract to which the change relates. Avoid general language such as 'additional work'; instead state the specific deliverable, the platform, the number of screens, the quantity, or the functional area being varied. The Dubai Courts and the Abu Dhabi Judicial Department interpret contracts on their express terms under Article 257 of the UAE Civil Code (Federal Law No. 5 of 1985), so precision protects both parties.
Record the reason for the change — whether client-requested, regulatory, or due to unforeseen circumstances — to contextualise the variation.
State the impact on scope and deliverables: what new deliverable is being added, what existing deliverable is being removed or modified, and what remains unchanged.
Record the timeline impact: the new target completion date or the new milestone dates. If the change can be absorbed within the existing timeline, state that explicitly.
Complete the additional fee in AED, exclusive of VAT under the VAT Law (Federal Decree-Law No. 8 of 2017), the payment schedule, and the revised total contract value.
Select the effect on the original agreement and the governing forum. Sign and date the change order. The service provider should not commence the changed work until the change order is signed by both parties.
Electronic signatures are valid under the Electronic Transactions and Trust Services Law (Federal Decree-Law No. 46 of 2021). Keep the signed change order together with the original contract as part of the project record.
Legal Requirements for Change Order Agreement (UAE)
A Change Order Agreement in the United Arab Emirates is governed by the UAE Civil Code (Federal Law No. 5 of 1985). Article 125 confirms that the amendment is formed by offer and acceptance on the agreed terms. Article 246 requires both parties to perform in good faith. Article 257 makes the agreed terms of the change order binding on both parties. Articles 282 and 389 govern damages for breach — the service provider is entitled to the agreed change-order fee if it performs the additional work, and the client may claim damages if the service provider fails to deliver.
For commercial parties, the Commercial Transactions Law (Federal Decree-Law No. 50 of 2022) supplements the Civil Code, requiring commercial transactions to be documented and setting the rules on commercial evidence and overdue interest under Articles 76 and 77. While the Civil Code and the Commercial Transactions Law do not require amendments to be in writing as a rule, the practical and evidentiary benefit of a signed change order is significant: the Dubai Courts and the Abu Dhabi Judicial Department look for written evidence of commercial agreements, and an unsigned or verbal variation is difficult to enforce.
For construction projects using FIDIC contract forms — the FIDIC Yellow Book and Red Book are widely used in the UAE for major infrastructure projects — the variation mechanism in the contract governs how instructions are issued and claims are submitted. The Change Order Agreement template supplements FIDIC by providing a record of agreed variations in plain-language format.
VAT at 5% under the VAT Law (Federal Decree-Law No. 8 of 2017) applies to additional taxable supplies arising from change orders, administered by the Federal Tax Authority (FTA). A supplemental tax invoice must be issued for each change order payment. Electronic execution is valid under the Electronic Transactions and Trust Services Law (Federal Decree-Law No. 46 of 2021). Arbitration under the Federal Arbitration Law (Federal Law No. 6 of 2018) is available where the parties have agreed arbitration in the original contract.
Common Mistakes to Avoid in Your Change Order Agreement (UAE)
A UAE Change Order Agreement is only effective when it is completed before the changed work begins. The following errors are common and can leave one or both parties without adequate protection.
1. Starting changed work without a signed change order. Performing additional work based on a verbal instruction and expecting to collect payment later is the most common and costly mistake in UAE project disputes. The Dubai Courts and the Abu Dhabi Judicial Department require evidence of what was agreed. Always sign the change order before commencing work.
2. Vague change description. A change order that describes the variation as 'additional features as discussed' without specifying the deliverables, the platforms, or the functionality is unenforceable because neither party can determine what was agreed. State the change precisely, referencing the affected deliverables from the original contract.
3. No timeline impact recorded. Failing to record the revised completion date when a change adds work allows the client to hold the service provider in delay for a schedule extension that was caused by the client's own scope change. Record the timeline impact — even if it is nil — for every change order.
4. Missing revised total contract value. Not recording the cumulative contract value after each change order leaves both parties uncertain about the total authorised commitment. State the revised total in every change order.
5. No VAT clause. Change order fees within the UAE are taxable at 5% under the VAT Law (Federal Decree-Law No. 8 of 2017). Omitting the VAT clause creates disputes at the invoicing stage and prevents the client from recovering input tax. State the fee as exclusive of VAT.
6. Not referencing the original contract clearly. A change order that does not clearly identify the original contract it amends may be treated as a standalone agreement rather than an amendment, creating uncertainty about which terms govern the overall project.
7. Failing to state the no-commencement rule. Without a clause requiring the service provider to wait for both signatures before starting the changed work, disputes arise about whether the work was authorised when only one party has signed.
Cite this page
Reference this free template in an article, syllabus, or research note:
Forms Legal. (2026). Change Order Agreement (UAE) (United Arab Emirates) [Legal document template]. Forms Legal. https://forms-legal.com/uae/business/contracts/change-order-agreement-uae
"Change Order Agreement (UAE) (United Arab Emirates)." Forms Legal, 2026, https://forms-legal.com/uae/business/contracts/change-order-agreement-uae.
@misc{formslegal-change-order-agreement-uae,
author = {{Forms Legal}},
title = {Change Order Agreement (UAE) (United Arab Emirates)},
year = {2026},
howpublished = {\url{https://forms-legal.com/uae/business/contracts/change-order-agreement-uae}},
note = {Free legal document template. Based on UAE Civil Code (Federal Law No. 5 of 1985)}
}Frequently Asked Questions
A Change Order Agreement in the United Arab Emirates is a written amendment to an existing contract — such as a Scope of Work Agreement, a Statement of Work, or a construction contract — that records an agreed variation to the original scope, the additional or reduced fee for the change, the impact on the project timeline, and the consent of both parties to the variation. Under Article 257 of the UAE Civil Code (Federal Law No. 5 of 1985), the contract is the law of the parties, and a change order signed by both parties has the same legal force as the original contract it amends.
A Change Order Agreement is needed whenever the scope of work agreed under the original contract changes after the contract is signed. Common triggers include: the client requests additional features, functionality, or deliverables not included in the original scope; the client removes previously agreed deliverables to reduce cost; the client changes the specification or standard after work has begun; or external circumstances — such as a regulatory change or a third-party dependency — require the scope or timeline to be adjusted.
Without a written Change Order, disputes frequently arise before the Dubai Courts and the Abu Dhabi Judicial Department about whether additional work was authorised, whether it was included in the original price, and who is responsible for the resulting delay. The Commercial Transactions Law (Federal Decree-Law No. 50 of 2022) requires commercial transactions of significance to be evidenced in writing, and a verbal instruction to vary the scope is difficult to enforce. The Change Order Agreement provides the documentary evidence both parties need.
A change order should be signed by both parties before the service provider starts the changed work in the United Arab Emirates, because work performed without a signed change order creates significant uncertainty about whether it was authorised, at what price, and on what timeline. A service provider that proceeds on a verbal instruction and later seeks payment for the additional work must prove before the Dubai Courts or the Abu Dhabi Judicial Department that the instruction was given and that a price was agreed, which is difficult without written documentation.
The Commercial Transactions Law (Federal Decree-Law No. 50 of 2022) and the UAE Civil Code (Federal Law No. 5 of 1985) do not preclude oral amendments to written contracts, but Article 36 of the Civil Code provides that a contract of a kind that the law requires to be in writing cannot be proved otherwise, and commercial contracts are expected to be documented. In practice, UAE courts look for the best available evidence of what was agreed, and a signed change order is the strongest evidence of an authorised variation.
Where urgency makes it impractical to sign a change order before commencing work — for example where a construction emergency requires immediate action — the service provider should at minimum record the instruction in a contemporaneous email or letter, confirm the price, obtain a response from the client acknowledging the instruction, and follow up with a signed change order as soon as practicable. The Change Order Agreement template includes a clause requiring the service provider not to commence changed work until the change order is signed, which is the recommended standard position for all planned scope changes.
The additional fee for a change order in the United Arab Emirates should be priced on the same basis as the original contract — fixed price if the original was fixed, time-and-materials at the agreed rates if the original was time-and-materials — and should be stated in AED, exclusive of Value Added Tax, in the Change Order Agreement. Under the UAE Civil Code (Federal Law No. 5 of 1985), the contract is the law of the parties, so the pricing methodology agreed in the original contract should normally apply to variations unless both parties agree otherwise.
For a fixed-price change to a fixed-price contract, the service provider should prepare a cost estimate for the specific change and negotiate a fixed price with the client before signing the change order. The estimate should identify the additional labour, the materials (if any), the overhead allocation, and any risk contingency. Once agreed and stated in the change order, the fixed price is binding regardless of actual cost, protecting the client from overruns on the specific change.
The change order should also state the revised total contract value — the original fee plus the cumulative change orders to date — so that both parties have a clear record of the total authorised commitment. For VAT compliance under the VAT Law (Federal Decree-Law No. 8 of 2017), the Federal Tax Authority (FTA) requires the service provider to issue a supplemental tax invoice for the additional taxable supply arising from the change order, separate from the invoices for the original contract. The client can recover the input VAT on the change order fee in the same way as on the original fee.
When a change order is issued on a UAE project, the impact on the project timeline should be assessed and recorded in the Change Order Agreement before the service provider starts the changed work. Under the UAE Civil Code (Federal Law No. 5 of 1985), Article 257 makes the agreed timeline an express contractual term, and Article 290 provides that compensation may be reduced where the injured party's own acts contributed to the harm — which applies where the client's scope changes caused a project delay.
The change order should state specifically how the change affects the target completion date: for example, that the go-live date extends from 30/06/2026 to 15/08/2026 to accommodate the additional localisation work, or that the change can be absorbed within the original timeline because it is performed in parallel. Where the extension is not agreed upfront, the client may later argue that the delay was caused by the service provider's inefficiency rather than the scope change, which the Dubai Courts would require the service provider to disprove.
For construction projects governed by a FIDIC form of contract — commonly used in the UAE for infrastructure projects overseen by authorities such as the Roads and Transport Authority (RTA) or Abu Dhabi National Energy Company (TAQA) — the variation provisions of the contract and the Engineer's instruction process should be followed, and the Change Order Agreement should cross-reference the relevant FIDIC clause. For technology and professional services projects, the change order process is typically simpler, requiring only a written amendment signed by both parties as contemplated by the original contract.
A UAE client generally cannot require the service provider to perform additional work outside the agreed scope without signing a change order, unless the original contract expressly grants the client the right to issue binding variation instructions without prior price agreement. Under the UAE Civil Code (Federal Law No. 5 of 1985), Article 246 requires both parties to perform in good faith, and Article 257 makes the agreed scope the law of the parties. The service provider's obligation is to deliver the work described in the original contract — not more.
Where a client issues an instruction to vary the scope and refuses to sign a change order agreeing the price and timeline impact, the service provider should not commence the additional work, should confirm in writing that it has received the instruction and requests a signed change order before proceeding, and should document the exchange carefully. If the service provider performs the work without a change order and the client later refuses to pay, the service provider will need to prove before the Dubai Courts or the Abu Dhabi Judicial Department that the instruction was given and that a reasonable price was agreed or implied.
In construction contracts based on FIDIC forms used in the UAE, the Engineer or supervising authority has the right to issue variation instructions that are binding on the contractor, but the contractor is entitled to claim additional time and cost through the FIDIC claims mechanism. The Dubai International Arbitration Centre (DIAC) and the Abu Dhabi Commercial Conciliation and Arbitration Centre (ADCCAC) regularly handle construction variation disputes. For professional services projects, where no equivalent unilateral variation right exists, the service provider's position is stronger: without a signed change order, no obligation to perform the additional work arises.
There is no statutory limit in the UAE on the number of change orders that can be issued on a project, but when the cumulative change orders have substantially altered the original scope or more than doubled the original fee, the parties should consider whether a replacement contract would better reflect the current project reality. Under the UAE Civil Code (Federal Law No. 5 of 1985), a heavily amended contract remains binding on its amended terms, but a project whose scope has changed significantly through multiple change orders may become difficult to administer and enforce because the current obligations are dispersed across many documents.
Practical considerations should drive the decision. Where the cumulative change orders represent changes of more than 25-30% of the original contract value, parties often issue a consolidated contract amendment that sets out the current scope, the revised total fee, and the current programme as a single coherent document, replacing the chain of change orders. This approach is particularly useful for long-running technology and construction projects in the UAE where the original scope was set before full design development and multiple variations are expected.
From a VAT compliance perspective under the VAT Law (Federal Decree-Law No. 8 of 2017), the Federal Tax Authority (FTA) requires that each taxable supply be supported by a valid tax invoice. Where cumulative change orders are consolidated into a replacement contract, the fee structure and the invoicing obligation should be clearly restated, and any VAT previously invoiced should be accounted for so that the client's input-tax recovery record is accurate. The Abu Dhabi Judicial Department and the Dubai Courts both treat the most recent signed agreement or amendment as the authoritative statement of the parties' obligations.
This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer
Found an error? Let us knowRelated Documents
You may also find these documents useful:
Scope of Work Agreement (UAE)
A Scope of Work Agreement for UAE projects defining the project description, deliverables, timeline, fees, and acceptance criteria under the UAE Civil Code (Federal Law No. 5 of 1985) and Commercial Transactions Law (Federal Decree-Law No. 50 of 2022). Suitable as a standalone document or as an exhibit to a master services agreement.
Statement of Work (UAE)
A Statement of Work (SOW) template for UAE technology, consulting, and professional services projects. Covers work description, deliverables, milestone payments, key assumptions, and acceptance criteria under the UAE Civil Code (Federal Law No. 5 of 1985).
Project Management Agreement (UAE)
A project management agreement for UAE construction, technology, and commercial projects. Defines the PM scope, management fee, authority limits, reporting obligations, and health-and-safety responsibilities under the UAE Civil Code (Federal Law No. 5 of 1985).
Service Agreement (UAE)
A commercial service agreement setting out the scope, fees, and obligations between a service provider and client under the UAE Civil Code (Federal Law No. 5 of 1985) and the Commercial Transactions Law (Federal Decree-Law No. 50 of 2022). Includes VAT and data protection clauses for the United Arab Emirates.
Construction Contract (FIDIC-Style) (UAE)
A FIDIC-style lump-sum construction contract for UAE projects, incorporating muqawala provisions under Arts 872-896 of the UAE Civil Code (Federal Law No. 5 of 1985), Art. 880 decennial liability, VAT under Federal Decree-Law No. 8 of 2017, and DIAC arbitration. Covers Employer, Contractor, Engineer, performance security, defects, and variations.