Notice of Completion (Canada)
Date: [Notice Date]
From: [Owner's Name], [Owner Type], with a mailing address at [Owner Address] (the "Owner")
To: [Contractor's Name], [Contractor Type], with a mailing address at [Contractor Address] (the "Contractor")
Re: Notice of [Completion Type] - [Project Description]
Project Site: [Project Address]
Original Contract: [Contract Title], dated [Contract Date]
Dear [Contractor's Name],
This Notice of Completion is issued to formally confirm that [Completion Type] of the construction work described in the above-referenced Contract was achieved on [Completion Date].
The Owner hereby acknowledges that the Contractor has substantially performed the obligations under the Contract, subject to any punch list items or deficiencies identified herein.
CONSTRUCTION LIEN NOTICE
This Notice of Completion may trigger the commencement of the statutory lien period under the applicable provincial Construction Lien Act or Builders Lien Act. Subcontractors and suppliers who wish to preserve their lien rights must do so within the timeframes prescribed by the applicable provincial legislation. In Ontario, the lien period is 60 days from substantial completion under the Construction Act (R.S.O. 1990, c. C.30). In British Columbia, the period is 55 days under the Builders Lien Act (S.B.C. 1997, c. 45). In Alberta, the period is 45 days under the Builders' Lien Act (R.S.A. 2000, c. B-7).
This Notice of Completion is governed by the laws of the Province of [Governing Law] and the federal laws of Canada applicable therein.
Please acknowledge receipt of this Notice of Completion. If you have any inquiries, please contact me at [Phone] or [Email].
Sincerely,
[Owner's Name]
[Owner Address]
Party 1
________________
Signature
Date: ________________
Party 2
________________
Signature
Date: ________________
What Is a Notice of Completion (Canada)?
A Notice of Completion in Canada records that the work is complete, marking the start of warranty and payment periods, governed primarily by provincial construction-lien legislation.
Under provincial construction lien legislation, the notice of completion is closely tied to the concept of substantial performance. In Ontario, the Construction Act (R.S.O. 1990, c. C.30, as amended by Bill 142 in 2018) defines substantial performance as when the improvement is ready for use or is being used for its intended purpose, and when the cost of completing the remaining work is not more than 3% of the first $500,000 of the contract price, 2% of the next $500,000, and 1% of the balance. The formal publication of a certificate of substantial performance in a designated construction trade newspaper triggers the lien period for general contractors.
The notice of completion triggers the statutory lien period, during which unpaid subcontractors and suppliers may preserve their lien rights by registering a claim against the property title. In Ontario, this lien period is 60 days. In British Columbia under the Builders Lien Act (S.B.C. 1997, c. 45), the period is 55 days. In Alberta under the Builders' Lien Act (R.S.A. 2000, c. B-7), the period is 45 days. Once the lien period expires without any liens being preserved, the statutory holdback (typically 10% of each progress payment) becomes eligible for release.
The notice also marks the commencement of the contractual warranty period, during which the contractor remains responsible for repairing defects in workmanship and materials at no additional cost. It provides a mechanism for documenting any remaining punch list or deficiency items that the contractor must complete or correct, and establishes deadlines for their resolution.
The legal framework governing the Notice of Completion (Canada) in Canada draws on several key statutes and regulatory bodies. Under the Canada Business Corporations Act (R.S.C. 1985, c. C-44), Corporations Canada maintains the federal registry. Section 12 of the CBCA governs corporate name requirements. The Competition Bureau enforces the Competition Act (R.S.C. 1985, c. C-34). Provincial securities commissions — including the Ontario Securities Commission (OSC) and British Columbia Securities Commission (BCSC) — regulate capital markets. The Federal Court of Canada has jurisdiction under the Federal Courts Act. Parties executing a Notice of Completion (Canada) in Canada should confirm the document reflects current law, including any amendments enacted since the original drafting date. The Canada Business Corporations Act (R.S.C. 1985, c. C-44) sets the foundational requirements.
When Do You Need a Notice of Completion (Canada)?
A Canadian Notice of Completion is needed whenever a construction project reaches the point of substantial or final completion and the property owner must formally acknowledge this milestone. This notice is essential for residential renovation projects, commercial construction, industrial facility construction, institutional building projects, and infrastructure development across all Canadian provinces and territories.
The notice is required to formally trigger the statutory lien period under provincial construction lien legislation, which is a prerequisite for the eventual release of the statutory holdback. Without a formal notice of completion, the lien period may not begin running, leaving the holdback indefinitely frozen and preventing the contractor from receiving the retained funds. In Ontario, a certificate of substantial performance must be published in the Daily Commercial News or other designated trade newspaper to trigger the lien period for the general contractor.
Property owners need this notice to formally transition the project from the construction phase to the warranty and maintenance phase. The notice establishes the date from which the warranty period runs, confirming that both parties have a clear record of when the contractor's warranty obligations begin and end. Without this formal record, disputes about the expiry of the warranty period may arise years after the work was completed.
Contractors need the notice to trigger the holdback release process and to establish the date of substantial completion for accounting, bonding, and insurance purposes. The notice also provides documentation that may be required by surety companies for performance bond release, by lenders for construction loan disbursement, and by insurance companies for transitioning from builder's risk insurance to permanent property insurance.
Municipal authorities may require evidence of completion as part of the occupancy permit process. The notice of completion, combined with final building inspections and code compliance certifications, supports the owner's application for an occupancy permit from the local building department.
Under the Canada Business Corporations Act (R.S.C. 1985, c. C-44), Corporations Canada maintains the federal registry. Section 12 of the CBCA governs corporate name requirements. The Competition Bureau enforces the Competition Act (R.S.C. 1985, c. C-34). Provincial securities commissions — including the Ontario Securities Commission (OSC) and British Columbia Securities Commission (BCSC) — regulate capital markets. The Federal Court of Canada has jurisdiction under the Federal Courts Act.
What to Include in Your Notice of Completion (Canada)
A thorough Canadian Notice of Completion must identify the property owner or client and the contractor with full legal names, entity types, and mailing addresses including province and postal code. Include the project site address, a description of the construction work performed, the original contract title and effective date, and the date of substantial completion.
The notice must clearly specify the completion type, distinguishing between substantial completion (where the work is ready for its intended purpose but minor items may remain) and final completion (where all work has been fully completed, including punch list items). This distinction is critical because it determines the starting point for the statutory lien period and the warranty period under provincial construction lien legislation.
If punch list or deficiency items remain, the notice must document these items in detail and establish a deadline for their completion. The contractor is typically required to complete all punch list items at no additional cost to the owner, and failure to do so may result in the owner deducting the cost of remediation from amounts due.
Statutory holdback release provisions must address the total holdback amount retained, the applicable lien period (60 days in Ontario under the Construction Act, 55 days in BC under the Builders Lien Act, 45 days in Alberta under the Builders' Lien Act), and the earliest date the holdback becomes eligible for release. Emphasize that the holdback cannot be released until the lien period expires and no construction liens have been preserved or perfected against the property.
Include a construction lien notice section informing subcontractors and suppliers of their lien rights and the applicable timeframes for preserving those rights. Include warranty commencement provisions specifying the warranty period duration, start date, and expiration date. Include contact information for follow-up inquiries and a governing law clause referencing the applicable Canadian province and federal laws. The notice should be signed by the property owner with the date of issuance.
Additional compliance elements for a Notice of Completion (Canada) used in Canada include: Under the Canada Business Corporations Act (R.S.C. 1985, c. C-44), Corporations Canada maintains the federal registry. Section 12 of the CBCA governs corporate name requirements. The Competition Bureau enforces the Competition Act (R.S.C. 1985, c. C-34). Provincial securities commissions — including the Ontario Securities Commission (OSC) and British Columbia Securities Commission (BCSC) — regulate capital markets. The Federal Court of Canada has jurisdiction under the Federal Courts Act. Forms-legal.com provides this template as a starting point for Canada-compliant documentation.
Sources & Citations
Statutory citations link to official government sources.
- R.S.C. 1985, c. C-44CA official
- R.S.C. 1985, c. C-34CA official
Cite this page
Reference this free template in an article, syllabus, or research note:
Forms Legal. (2026). Notice of Completion (Canada) (Canada) [Legal document template]. Forms Legal. https://forms-legal.com/canada/business/construction/notice-of-completion-canada
"Notice of Completion (Canada) (Canada)." Forms Legal, 2026, https://forms-legal.com/canada/business/construction/notice-of-completion-canada.
@misc{formslegal-notice-of-completion-canada,
author = {{Forms Legal}},
title = {Notice of Completion (Canada) (Canada)},
year = {2026},
howpublished = {\url{https://forms-legal.com/canada/business/construction/notice-of-completion-canada}},
note = {Free legal document template. Based on Canada Business Corporations Act (R.S.C. 1985, c. C-44)}
}Also available for these jurisdictions:
Frequently Asked Questions
A notice of completion in Canadian construction law is a formal document issued by the property owner or client confirming that the contractor has achieved substantial or final completion of the construction work. Under Ontario's Construction Act (R.S.O. 1990, c. C.30), a certificate of substantial performance may be published in a designated construction trade newspaper to formally trigger the lien period. The notice serves as the official record of the completion date, which is critical for calculating the statutory lien period, triggering holdback release eligibility, and commencing the warranty period. Under Canada law, Canada Business Corporations Act (R.S.C. 1985, c. C-44), parties should seek independent legal advice from a qualified lawyer to confirm compliance with all applicable requirements. Under the Canada Business Corporations Act (R.S.C. 1985, c. Forms-legal.com provides this template as a starting point for Canada-compliant documentation.
The construction lien period begins on the date of substantial completion or the date of last supply of services or materials, whichever is later. In Ontario under the Construction Act (R.S.O. 1990, c. C.30), the lien period is 60 days. In British Columbia under the Builders Lien Act (S.B.C. 1997, c. 45), it is 55 days. In Alberta under the Builders' Lien Act (R.S.A. 2000, c. B-7), it is 45 days. During this period, subcontractors and suppliers who have not been paid may preserve their lien rights by registering a claim against the property title. Under Canada law, Canada Business Corporations Act (R.S.C. 1985, c. C-44), parties should seek independent legal advice from a qualified lawyer to confirm compliance with all applicable requirements. Under the Canada Business Corporations Act (R.S.C. 1985, c. Forms-legal.com provides this template as a starting point for Canada-compliant documentation.
The statutory holdback can be released after the expiry of the applicable lien period, provided no construction liens have been preserved or perfected against the property. In Ontario, this means 60 days after substantial completion under the Construction Act (R.S.O. 1990, c. C.30). In BC, it is 55 days under the Builders Lien Act. In Alberta, it is 45 days under the Builders' Lien Act. The owner should conduct a title search before releasing the holdback to confirm that no liens have been registered. Under Canada law, Canada Business Corporations Act (R.S.C. 1985, c. C-44), parties should seek independent legal advice from a qualified lawyer to confirm compliance with all applicable requirements. Under the Canada Business Corporations Act (R.S.C. 1985, c. Forms-legal.com provides this template as a starting point for Canada-compliant documentation.
A Notice of Completion (Canada) does not legally require a lawyer in Canada, and individuals and businesses may draft and execute the document independently. The Canada Business Corporations Act (R.S.C. 1985, c. C-44) does not mandate legal representation for the creation or signing of this type of document. However, seeking independent legal advice from a qualified Canada lawyer is recommended for transactions involving substantial financial value, complex regulatory requirements, or cross-border elements where multiple legal jurisdictions may apply. A lawyer can verify that the document complies with all applicable statutory requirements, identify potential risks specific to the transaction, and confirm that the terms adequately protect the interests of all parties involved. The Federal Court of Canada has jurisdiction over disputes arising from this type of document, and Corporations Canada may impose additional compliance obligations depending on the nature of the underlying transaction. Professional legal review is particularly advisable where the document will be submitted to government agencies or used as evidence in legal proceedings.
A Notice of Completion (Canada) does not legally require a lawyer in Canada, though legal advice is recommended for complex transactions. Under Canadian law, individuals may draft and execute this type of document independently. The Competition Act (R.S.C. 1985, c. C-34) provides consumer protections. However, Corporations Canada, the Canada Revenue Agency (CRA), or provincial regulatory bodies may have specific requirements. For property transactions, provincial land title offices require qualified lawyers or notaries. PIPEDA and provincial privacy legislation impose obligations on parties handling personal data. Where disputes arise, provincial superior courts or the Federal Court of Canada have jurisdiction. Forms-legal.com provides this template as a starting point — always review with a qualified Canadian lawyer for significant transactions.
This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer
Found an error? Let us knowRelated Documents
You may also find these documents useful:
Construction Contract (Canada)
Canadian construction contract with provincial Construction Lien Act compliance, holdback requirements, prompt payment legislation, and WSIB/WCB clearance certificates.
General Contractor Agreement (Canada)
Hire a general contractor for construction or renovation projects in Canada with this comprehensive agreement. Includes scope of work, payment schedules with provincial statutory holdback requirements (ON: Construction Act s. 22, BC: Builders Lien Act s. 4, AB: Prompt Payment Act s. 18), WSIB/WCB insurance provisions, construction lien protections, change order procedures, and warranty terms.
Subcontractor Agreement (Canada)
Canadian subcontractor agreement with Construction Lien Act compliance, WSIB/WCB clearance requirements, CRA independent contractor tests, and prompt payment protections.
Indemnity Agreement (Canada)
Protect against third-party claims with a Canadian Indemnity Agreement. Covers hold harmless provisions, duty to defend, and liability limitations.