Skip to main content

Construction Change Order (Canada)

Construction Change Order

Canadian Construction Contract Change Order

Change Order No.: [Change Order Number]

Date: [Change Order Date]

Project: [Project Name]

Site Address: [Project Address]

Province: [Province]

Original Contract Date: [Original Contract Date]

Owner: [Owner Name]

Contractor: [Contractor Name]

DESCRIPTION OF CHANGE

Type of Change: [Change Type]

[Change Description]

CONTRACT PRICE ADJUSTMENT

Original Contract Price: CAD $[Original Contract Price]

Previously Approved Change Orders: CAD $[Previous Change Orders]

This Change Order Amount: CAD $[This Change Order Amount]

REVISED CONTRACT PRICE: CAD $[Revised Total — sum of above]

Applicable GST/HST will be added to the change order amount at the rate applicable in [Province].

SCHEDULE ADJUSTMENT

Current Contract Completion Date: [Original Completion Date]

Time Extension (calendar days): [Time Extension Days] days

REVISED COMPLETION DATE: [Revised Completion Date]

AGREEMENT

The parties hereby agree that the original construction contract is amended to reflect the changes described in this Change Order. The Contractor agrees to perform the changed Work for the adjusted price and within the adjusted schedule noted above. All other terms and conditions of the original contract remain in full force and effect.

This Change Order is issued in accordance with the applicable [Province] Construction Act and the change order provisions of the construction contract. The adjusted contract price is the basis for holdback calculations under the [Province] Construction Act.

Owner / Owner's Representative

________________

Signature

Date: ________________

Contractor

________________

Signature

Date: ________________

Maintained by Vladislav Sergienko, Founder·Template last modified: ·Report an error

What Is a Construction Change Order (Canada)?

A Construction Change Order in Canada authorises a change to the agreed scope, price, or schedule of construction work, governed primarily by common-law construction-contract principles.

Change orders are an inevitable feature of construction projects. Even well-designed projects encounter unforeseen site conditions, owner-requested modifications, design refinements, and coordination issues that require changes to the originally contracted scope. Without a systematic, documented change order process, projects quickly lose financial control — costs escalate without agreed authorization, disputes arise about what work was authorized and at what price, and schedule impacts accumulate without clear contractual time extensions.

In Canada, standard construction contracts — particularly CCDC 2 (Stipulated Price Contract) published by the Canadian Construction Documents Committee — include detailed provisions governing the change order process. CCDC 2 General Condition 6.2 requires that changes to the work be documented in a Change Order signed by both parties before proceeding. In practice, contractors often proceed with changes under owner instruction and document the Change Order after the fact, which creates risk for both parties.

Change orders are legally significant under provincial Construction Acts: the authorized contract price (including all approved change orders) is the basis for holdback calculations, and the additional amounts become part of the contractor's lien claim entitlement. They are also important for GST/HST purposes — additional contract amounts trigger additional HST obligations.

For construction projects of any scale, maintaining a numbered log of all change orders with cumulative totals is essential for budget management, dispute prevention, and accurate final accounting.

The legal framework governing the Construction Change Order (Canada) in Canada draws on several key statutes and regulatory bodies. Under the Canada Business Corporations Act (R.S.C. 1985, c. C-44), Corporations Canada maintains the federal registry. Section 12 of the CBCA governs corporate name requirements. The Competition Bureau enforces the Competition Act (R.S.C. 1985, c. C-34). Provincial securities commissions — including the Ontario Securities Commission (OSC) and British Columbia Securities Commission (BCSC) — regulate capital markets. The Federal Court of Canada has jurisdiction under the Federal Courts Act. Parties executing a Construction Change Order (Canada) in Canada should confirm the document reflects current law, including any amendments enacted since the original drafting date. The Canada Business Corporations Act (R.S.C. 1985, c. C-44) sets the foundational requirements.

When Do You Need a Construction Change Order (Canada)?

A change order is needed whenever a modification to a construction contract is agreed upon:

Owner-requested additions — When the owner requests additional work beyond the original contract scope: additional rooms, upgraded finishes, additional systems, or expanded footprint. A change order documents the agreed scope, price, and time impact.

Design changes and revisions — When the architect, engineer, or designer issues revised drawings or specifications that change the scope of work already contracted, a change order updates the contract accordingly.

Unforeseen conditions — When contractors encounter unforeseen site conditions — underground utilities not shown on drawings, contaminated soil, unexpected structural conditions — that require additional work beyond the contract scope, a change order documents the agreed additional compensation.

Deductive changes — When the owner deletes or reduces previously contracted scope (a 'deductive change order'), reducing the contract price accordingly. Deductive change orders also affect the holdback calculation.

Substitutions and alternatives — When the contractor proposes (and the owner accepts) a material, product, or method substitution that changes the contract price, a change order documents the price adjustment.

Regulatory changes — When changes in applicable building code or zoning requirements during construction require modifications to the work beyond the original design, a change order may be required.

Coordination issues between trades — When coordination between different contractors or subcontractors on a project requires changes to each party's scope, change orders to each contract document the adjustments.

Without a formal written change order, disputes about whether additional work was authorized, at what price, and what time extension was agreed are among the most common and expensive disputes in Canadian construction litigation.

Parties in Canada should prepare a Construction Change Order (Canada) proactively rather than waiting for a dispute to arise. Courts interpret agreements based on the written terms rather than oral representations. Under the Canada Business Corporations Act (R.S.C. 1985, c. C-44), Corporations Canada maintains the federal registry. Section 12 of the CBCA governs corporate name requirements. The Competition Bureau enforces the Competition Act (R.S.C. 1985, c. C-34). Provincial securities commissions — including the Ontario Securities Commission (OSC) and British Columbia Securities Commission (BCSC) — regulate capital markets. The Federal Court of Canada has jurisdiction under the Federal Courts Act. Where the transaction involves regulated activities, prior approval from the relevant authority may be required before execution.

What to Include in Your Construction Change Order (Canada)

Change Order Number — Each change order should be sequentially numbered for tracking and reference. Maintain a change order log recording all change orders and their cumulative impact on the contract price and schedule.

Project and Contract Reference — The project name, site address, original contract number, and date, so the change order is clearly tied to the correct construction contract.

Parties — The owner (or owner's authorized representative) and the contractor, with their full legal names and signing authority.

Description of Change — A clear, specific description of the additional, deleted, or modified work, referencing applicable drawings, specifications, or directives that define the change.

Price Adjustment — The agreed price adjustment: a lump sum addition or credit, a unit price adjustment, or a reference to cost-plus calculation. Show the original contract price, this change order amount, and the revised contract price.

Schedule Impact — The number of calendar days added to (or deleted from) the contract completion date as a result of this change, the original completion date, and the revised completion date.

Cumulative Summary — A table showing all approved change orders to date, their individual amounts, and the cumulative revised contract price and completion date.

GST/HST — The applicable GST/HST on the change order amount.

Authorization — Signatures of the owner or owner's authorized representative (architect, engineer, or project manager) and the contractor, with their printed names, titles, and date of signing.

Governing Contract and Act — Reference to the original construction contract and the applicable provincial Construction Act.

Additional compliance elements for a Construction Change Order (Canada) used in Canada include: Under the Canada Business Corporations Act (R.S.C. 1985, c. C-44), Corporations Canada maintains the federal registry. Section 12 of the CBCA governs corporate name requirements. The Competition Bureau enforces the Competition Act (R.S.C. 1985, c. C-34). Provincial securities commissions — including the Ontario Securities Commission (OSC) and British Columbia Securities Commission (BCSC) — regulate capital markets. The Federal Court of Canada has jurisdiction under the Federal Courts Act. Forms-legal.com provides this template as a starting point for Canada-compliant documentation.

Sources & Citations

Statutory citations link to official government sources.

  1. R.S.C. 1985, c. C-44CA official
  2. R.S.C. 1985, c. C-34CA official

Cite this page

Reference this free template in an article, syllabus, or research note:

APA

Forms Legal. (2026). Construction Change Order (Canada) (Canada) [Legal document template]. Forms Legal. https://forms-legal.com/canada/business/construction/construction-change-order-canada

MLA

"Construction Change Order (Canada) (Canada)." Forms Legal, 2026, https://forms-legal.com/canada/business/construction/construction-change-order-canada.

BibTeX
@misc{formslegal-construction-change-order-canada,
  author       = {{Forms Legal}},
  title        = {Construction Change Order (Canada) (Canada)},
  year         = {2026},
  howpublished = {\url{https://forms-legal.com/canada/business/construction/construction-change-order-canada}},
  note         = {Free legal document template. Based on Canada Business Corporations Act (R.S.C. 1985, c. C-44)}
}

Also available for these jurisdictions:

Frequently Asked Questions

Based on Canada Business Corporations Act (R.S.C. 1985, c. C-44) — Template last modified June 2026Verify the source →

This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer

Found an error? Let us know