Construction Change Order (Canada)
Canadian Construction Contract Change Order
Change Order No.: [Change Order Number]
Date: [Change Order Date]
Project: [Project Name]
Site Address: [Project Address]
Province: [Province]
Original Contract Date: [Original Contract Date]
Owner: [Owner Name]
Contractor: [Contractor Name]
DESCRIPTION OF CHANGE
Type of Change: [Change Type]
[Change Description]
CONTRACT PRICE ADJUSTMENT
Original Contract Price: CAD $[Original Contract Price]
Previously Approved Change Orders: CAD $[Previous Change Orders]
This Change Order Amount: CAD $[This Change Order Amount]
REVISED CONTRACT PRICE: CAD $[Revised Total — sum of above]
Applicable GST/HST will be added to the change order amount at the rate applicable in [Province].
SCHEDULE ADJUSTMENT
Current Contract Completion Date: [Original Completion Date]
Time Extension (calendar days): [Time Extension Days] days
REVISED COMPLETION DATE: [Revised Completion Date]
AGREEMENT
The parties hereby agree that the original construction contract is amended to reflect the changes described in this Change Order. The Contractor agrees to perform the changed Work for the adjusted price and within the adjusted schedule noted above. All other terms and conditions of the original contract remain in full force and effect.
This Change Order is issued in accordance with the applicable [Province] Construction Act and the change order provisions of the construction contract. The adjusted contract price is the basis for holdback calculations under the [Province] Construction Act.
Owner / Owner's Representative
________________
Signature
Date: ________________
Contractor
________________
Signature
Date: ________________
What Is a Construction Change Order (Canada)?
A Construction Change Order in Canada authorises a change to the agreed scope, price, or schedule of construction work, governed primarily by common-law construction-contract principles.
Change orders are an inevitable feature of construction projects. Even well-designed projects encounter unforeseen site conditions, owner-requested modifications, design refinements, and coordination issues that require changes to the originally contracted scope. Without a systematic, documented change order process, projects quickly lose financial control — costs escalate without agreed authorization, disputes arise about what work was authorized and at what price, and schedule impacts accumulate without clear contractual time extensions.
In Canada, standard construction contracts — particularly CCDC 2 (Stipulated Price Contract) published by the Canadian Construction Documents Committee — include detailed provisions governing the change order process. CCDC 2 General Condition 6.2 requires that changes to the work be documented in a Change Order signed by both parties before proceeding. In practice, contractors often proceed with changes under owner instruction and document the Change Order after the fact, which creates risk for both parties.
Change orders are legally significant under provincial Construction Acts: the authorized contract price (including all approved change orders) is the basis for holdback calculations, and the additional amounts become part of the contractor's lien claim entitlement. They are also important for GST/HST purposes — additional contract amounts trigger additional HST obligations.
For construction projects of any scale, maintaining a numbered log of all change orders with cumulative totals is essential for budget management, dispute prevention, and accurate final accounting.
The legal framework governing the Construction Change Order (Canada) in Canada draws on several key statutes and regulatory bodies. Under the Canada Business Corporations Act (R.S.C. 1985, c. C-44), Corporations Canada maintains the federal registry. Section 12 of the CBCA governs corporate name requirements. The Competition Bureau enforces the Competition Act (R.S.C. 1985, c. C-34). Provincial securities commissions — including the Ontario Securities Commission (OSC) and British Columbia Securities Commission (BCSC) — regulate capital markets. The Federal Court of Canada has jurisdiction under the Federal Courts Act. Parties executing a Construction Change Order (Canada) in Canada should confirm the document reflects current law, including any amendments enacted since the original drafting date. The Canada Business Corporations Act (R.S.C. 1985, c. C-44) sets the foundational requirements.
When Do You Need a Construction Change Order (Canada)?
A change order is needed whenever a modification to a construction contract is agreed upon:
Owner-requested additions — When the owner requests additional work beyond the original contract scope: additional rooms, upgraded finishes, additional systems, or expanded footprint. A change order documents the agreed scope, price, and time impact.
Design changes and revisions — When the architect, engineer, or designer issues revised drawings or specifications that change the scope of work already contracted, a change order updates the contract accordingly.
Unforeseen conditions — When contractors encounter unforeseen site conditions — underground utilities not shown on drawings, contaminated soil, unexpected structural conditions — that require additional work beyond the contract scope, a change order documents the agreed additional compensation.
Deductive changes — When the owner deletes or reduces previously contracted scope (a 'deductive change order'), reducing the contract price accordingly. Deductive change orders also affect the holdback calculation.
Substitutions and alternatives — When the contractor proposes (and the owner accepts) a material, product, or method substitution that changes the contract price, a change order documents the price adjustment.
Regulatory changes — When changes in applicable building code or zoning requirements during construction require modifications to the work beyond the original design, a change order may be required.
Coordination issues between trades — When coordination between different contractors or subcontractors on a project requires changes to each party's scope, change orders to each contract document the adjustments.
Without a formal written change order, disputes about whether additional work was authorized, at what price, and what time extension was agreed are among the most common and expensive disputes in Canadian construction litigation.
Parties in Canada should prepare a Construction Change Order (Canada) proactively rather than waiting for a dispute to arise. Courts interpret agreements based on the written terms rather than oral representations. Under the Canada Business Corporations Act (R.S.C. 1985, c. C-44), Corporations Canada maintains the federal registry. Section 12 of the CBCA governs corporate name requirements. The Competition Bureau enforces the Competition Act (R.S.C. 1985, c. C-34). Provincial securities commissions — including the Ontario Securities Commission (OSC) and British Columbia Securities Commission (BCSC) — regulate capital markets. The Federal Court of Canada has jurisdiction under the Federal Courts Act. Where the transaction involves regulated activities, prior approval from the relevant authority may be required before execution.
What to Include in Your Construction Change Order (Canada)
Change Order Number — Each change order should be sequentially numbered for tracking and reference. Maintain a change order log recording all change orders and their cumulative impact on the contract price and schedule.
Project and Contract Reference — The project name, site address, original contract number, and date, so the change order is clearly tied to the correct construction contract.
Parties — The owner (or owner's authorized representative) and the contractor, with their full legal names and signing authority.
Description of Change — A clear, specific description of the additional, deleted, or modified work, referencing applicable drawings, specifications, or directives that define the change.
Price Adjustment — The agreed price adjustment: a lump sum addition or credit, a unit price adjustment, or a reference to cost-plus calculation. Show the original contract price, this change order amount, and the revised contract price.
Schedule Impact — The number of calendar days added to (or deleted from) the contract completion date as a result of this change, the original completion date, and the revised completion date.
Cumulative Summary — A table showing all approved change orders to date, their individual amounts, and the cumulative revised contract price and completion date.
GST/HST — The applicable GST/HST on the change order amount.
Authorization — Signatures of the owner or owner's authorized representative (architect, engineer, or project manager) and the contractor, with their printed names, titles, and date of signing.
Governing Contract and Act — Reference to the original construction contract and the applicable provincial Construction Act.
Additional compliance elements for a Construction Change Order (Canada) used in Canada include: Under the Canada Business Corporations Act (R.S.C. 1985, c. C-44), Corporations Canada maintains the federal registry. Section 12 of the CBCA governs corporate name requirements. The Competition Bureau enforces the Competition Act (R.S.C. 1985, c. C-34). Provincial securities commissions — including the Ontario Securities Commission (OSC) and British Columbia Securities Commission (BCSC) — regulate capital markets. The Federal Court of Canada has jurisdiction under the Federal Courts Act. Forms-legal.com provides this template as a starting point for Canada-compliant documentation.
Sources & Citations
Statutory citations link to official government sources.
- R.S.C. 1985, c. C-44CA official
- R.S.C. 1985, c. C-34CA official
Cite this page
Reference this free template in an article, syllabus, or research note:
Forms Legal. (2026). Construction Change Order (Canada) (Canada) [Legal document template]. Forms Legal. https://forms-legal.com/canada/business/construction/construction-change-order-canada
"Construction Change Order (Canada) (Canada)." Forms Legal, 2026, https://forms-legal.com/canada/business/construction/construction-change-order-canada.
@misc{formslegal-construction-change-order-canada,
author = {{Forms Legal}},
title = {Construction Change Order (Canada) (Canada)},
year = {2026},
howpublished = {\url{https://forms-legal.com/canada/business/construction/construction-change-order-canada}},
note = {Free legal document template. Based on Canada Business Corporations Act (R.S.C. 1985, c. C-44)}
}Also available for these jurisdictions:
Frequently Asked Questions
Most standard Canadian construction contracts — including CCDC 2 (Stipulated Price Contract), CCDC 3, and CCDC 5 — require that changes to the scope of work, contract price, or completion date be documented in writing through a formal Change Order or Change Directive. While verbal instructions to perform additional work are sometimes given on construction sites, a contractor who performs additional work based on an oral instruction without a written change order is at significant risk of non-payment. Under Canadian common law, quantum meruit claims (claiming the fair value of work performed) can be pursued for verbal change orders, but they are uncertain and expensive to litigate. Several provincial courts have held that contractual requirements for written change authorization must be followed to create binding obligations. Ontario's Construction Act (R.S.O. 1990, c. C.30) does not specifically require change orders to be in writing, but the contract documents govern the change order procedure, and most construction contracts impose written authorization requirements.
A properly documented change order has important implications for a contractor's lien rights under provincial Construction Acts. When the contract price is increased through a change order, the increased amount becomes part of the contractor's lien claim entitlement — the lien is registered for the amount owing for services and materials supplied, including authorized change orders. Conversely, if additional work is performed without a written change order, the contractor may face challenges proving their lien claim for the additional amounts, as the lien is generally limited to amounts owing under the contract and authorized extras. Under Ontario's Construction Act, lien preservation periods run from the date of last supply, so documenting each change order with a clear date of completion helps establish the lien timeline. The written change order also establishes the contract price for holdback calculation purposes — the owner's holdback obligation is calculated on the contract price as adjusted by all approved change orders.
Under CCDC 2 (the Canadian Construction Documents Committee's standard stipulated price contract), there are two mechanisms for instructing changes to the scope of work. A Change Order (CCDC 2 GC 6.2) is a written agreement between the owner and contractor documenting a change to the work, the adjustment to the contract price, and the adjustment to the contract time — it requires the agreement of both parties to the price and time impacts. A Change Directive (CCDC 2 GC 6.3) is a written instruction from the owner directing the contractor to proceed with a change in the work when the owner and contractor have not reached agreement on the price or time adjustment. The contractor must proceed with the change in response to a Change Directive, and the price is determined after the fact based on cost records plus overhead and profit, or by other means defined in the contract. The key distinction is mutual agreement (Change Order) versus unilateral owner instruction pending pricing (Change Directive).
Change orders in Canadian construction contracts can affect both the contract price and the contract completion date. When additional scope is added, the contractor is typically entitled to a time extension commensurate with the impact of the change on the critical path of the project schedule. The change order document should specify both the additional cost (or credit for a deductive change) and the number of calendar or working days added to the contract completion date. Failure to document time extensions in change orders can result in the contractor being assessed liquidated damages for late completion — even where the delays were caused by owner-directed changes — because the original completion date remains contractually binding unless formally extended. The cumulative impact of multiple change orders on the project schedule is an important issue in Canadian construction disputes: courts and arbitrators recognize that a large number of changes can create cumulative schedule impacts (sometimes called 'acceleration' or 'disruption' claims) beyond the sum of individual change order time extensions.
A Construction Change Order (Canada) does not legally require a lawyer in Canada, and individuals and businesses may draft and execute the document independently. The Canada Business Corporations Act (R.S.C. 1985, c. C-44) does not mandate legal representation for the creation or signing of this type of document. However, seeking independent legal advice from a qualified Canada lawyer is recommended for transactions involving substantial financial value, complex regulatory requirements, or cross-border elements where multiple legal jurisdictions may apply. A lawyer can verify that the document complies with all applicable statutory requirements, identify potential risks specific to the transaction, and confirm that the terms adequately protect the interests of all parties involved. The Federal Court of Canada has jurisdiction over disputes arising from this type of document, and Corporations Canada may impose additional compliance obligations depending on the nature of the underlying transaction. Professional legal review is particularly advisable where the document will be submitted to government agencies or used as evidence in legal proceedings.
This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer
Found an error? Let us knowRelated Documents
You may also find these documents useful:
Practical Completion Certificate (Canada)
Certify that construction work has reached practical completion under a Canadian construction contract. Covers Construction Act / Construction Lien Act requirements, certificate of substantial performance, deficiency holdback release, and warranty period commencement.
Subcontractor Agreement — Construction (Canada)
Subcontract construction work from a general contractor to a subcontractor in Canada. Covers Construction Act lien rights, Workplace Safety and Insurance Board (WSIB) clearance, scope of work, payment schedule, holdback, defects liability, and safety compliance.
Service Agreement (Canada)
Create a comprehensive Canadian service agreement covering the terms between a service provider and client. Includes GST/HST tax provisions, PIPEDA data protection compliance, limitation of liability, and province-specific governing law. Suitable for consulting, IT, marketing, and professional services across all provinces.