Skip to main content

Notice of Practical Completion (Australia)

Notice of Practical Completion (Australia)

Construction / Project Completion Notice — Security of Payment Acts

Date of Notice: [Notice Date]

TO (PRINCIPAL / OWNER):

[Principal Name] (ABN [Principal ABN])

[Principal Address], [Principal Suburb], [Principal State] [Principal Postcode]

FROM (CONTRACTOR):

[Contractor Name] (ABN [Contractor ABN])

Licence: [Contractor Licence]

[Contractor Address], [Contractor Suburb], [Contractor State] [Contractor Postcode]

Dear [Principal Name],

[Contractor Name] ("Contractor") hereby gives notice to [Principal Name] ("Principal") that Practical Completion of the Works described below has been achieved in accordance with the construction contract described in this Notice ("Contract").

This Notice is given pursuant to the Contract and, where applicable, the building and construction security of payment legislation applying in [Governing State], Australia.

1. CONTRACT DETAILS

1.1 Contract name: [Contract Name]

1.2 Contract date: [Contract Date]

1.3 Contract reference: [Contract Ref]

1.4 Site address: [Site Address]

2. DESCRIPTION OF WORKS

2.1 The works the subject of this Notice are as follows:

[Works Description]

3. NOTICE OF PRACTICAL COMPLETION

3.1 The Contractor hereby gives notice that Practical Completion of the Works was achieved on [Practical Completion Date] ("the Date of Practical Completion").

3.2 Practical Completion has been achieved on the following basis:

[Completion Basis]

3.3 The Contractor confirms that the Works are complete except for any minor defects or omissions listed in clause 4 below, none of which prevents the reasonable occupation or use of the Works.

3.4 The Principal is requested to inspect the Works and, if satisfied that Practical Completion has been achieved, to issue a Certificate of Practical Completion (or equivalent) in accordance with the Contract within the timeframe specified in the Contract.

4. DEFECTS LIABILITY PERIOD

4.1 The Defects Liability Period of [DLP Months] months commences on the Date of Practical Completion ([Practical Completion Date]) and expires on [DLP End Date] (the "DLP Expiry Date").

4.2 During the Defects Liability Period, the Contractor remains obliged to rectify, at its own cost, any defect or deficiency in the Works that: (a) becomes apparent during the Defects Liability Period; and (b) is attributable to the Contractor's failure to carry out the Works in accordance with the Contract.

4.3 The Principal shall give prompt written notice to the Contractor of any defect or deficiency that becomes apparent during the Defects Liability Period. The Contractor shall rectify each notified defect within a reasonable time, having regard to the nature and urgency of the defect.

4.4 Upon expiry of the Defects Liability Period and rectification of all identified defects, the Contractor is entitled to the release of any retention monies held by the Principal in connection with the defects warranty, in accordance with the Contract.

5. GENERAL

5.1 Risk in the Works passes to the Principal on the Date of Practical Completion in accordance with the Contract.

5.2 The Contractor's obligation to maintain construction all-risks insurance and public liability insurance in connection with the Works terminates at the expiry of a reasonable period following the Date of Practical Completion or as specified in the Contract, whichever is earlier. The Principal should ensure that its own property insurance is in place from the Date of Practical Completion.

5.3 This Notice does not limit or waive any right of the Contractor to make further claims in connection with the Works, including claims for delay costs, disruption costs, variations, or other amounts payable under the Contract.

5.4 This Notice and all disputes arising in connection with the Works are governed by the laws of [Governing State], Australia. The parties submit to the non-exclusive jurisdiction of the courts of [Governing State] and, where applicable, the dispute resolution procedures under the applicable Security of Payment legislation.

This Notice of Practical Completion is given by the Contractor on the date stated above.

CONTRACTOR

Name: [Contractor Name]

ABN: [Contractor ABN]

Licence: [Contractor Licence]

Address: [Contractor Address], [Contractor Suburb], [Contractor State] [Contractor Postcode]

ACKNOWLEDGEMENT OF RECEIPT BY PRINCIPAL

Name: [Principal Name]

ABN: [Principal ABN]

Address: [Principal Address], [Principal Suburb], [Principal State] [Principal Postcode]

Contractor

________________

Signature

Date: ________________

Principal (Acknowledged)

________________

Signature

Date: ________________

Maintained by Vladislav Sergienko, Founder·Template last modified: ·Report an error

What Is a Notice of Practical Completion (Australia)?

A Notice of Practical Completion in Australia sets the scope of works, price, timeframe, and variation and completion procedures between the principal and the builder or contractor under the Corporations Act 2001 (Cth).

Practical Completion is one of the most significant milestones in any Australian construction contract. It is the trigger for a series of important legal and commercial consequences: the commencement of the Defects Liability Period (DLP) — typically 12 months — during which the contractor must return and rectify any defects that become apparent; the transfer of risk in the works from the contractor to the principal; the termination of the contractor's obligation to maintain construction all-risks insurance; the contractor's entitlement to the release of the first moiety (usually 50%) of any retention held by the principal; and the contractor's entitlement to make a final payment claim for the balance of the contract sum, approved variations, and any other amounts due.

The concept of Practical Completion is defined differently in different standard form contracts used in Australia — including the Australian Standard contracts (AS 4000-1997, AS 2124-1992, AS 4300-1995), the HIA and Master Builders residential contracts, and various government and private sector bespoke contracts. In general, Practical Completion is achieved when the works are complete in accordance with the Contract Documents except for minor defects or omissions that do not prevent the reasonable use or occupation of the works.

In addition to its contractual significance, a Notice of Practical Completion may also serve as a Payment Claim under the applicable Security of Payment legislation — the Building and Construction Industry Security of Payment Act (NSW, VIC, SA, TAS, ACT) or its equivalents in QLD (Building Industry Fairness (Security of Payment) Act 2017), WA (Construction Contracts Act 2004), and NT (Construction Contracts (Security of Payment) Act 2004). These Acts give contractors a fast-track statutory right to payment and adjudication without having to resort to court proceedings.

The legal framework governing the Notice of Practical Completion (Australia) in Australia draws on several key statutes and regulatory bodies. Under the Corporations Act 2001 (Cth), the Australian Securities and Investments Commission (ASIC) regulates companies and financial services. Section 127 of the Corporations Act 2001 governs company execution of documents. The Australian Competition and Consumer Commission (ACCC) enforces the Competition and Consumer Act 2010 (Cth). The Australian Taxation Office (ATO) administers the Goods and Services Tax under the A New Tax System (Goods and Services Tax) Act 1999. The Federal Court of Australia and Supreme Courts of each state have jurisdiction over corporate disputes. Parties executing a Notice of Practical Completion (Australia) in Australia should confirm the document reflects current law, including any amendments enacted since the original drafting date. The Corporations Act 2001 (Cth) sets the foundational requirements.

When Do You Need a Notice of Practical Completion (Australia)?

A Notice of Practical Completion is needed at the point in a construction or building project when the contractor believes the works are substantially complete and meets the contractual definition of Practical Completion, and the contractor wishes to formally notify the principal of this fact and trigger the associated contractual entitlements.

You should issue a Notice of Practical Completion when: you are the contractor and the works are substantially complete in accordance with the Contract Documents — all structural, civil, mechanical, electrical, and hydraulic works are done, any required occupation certificate or building approval has been obtained, and only minor defects or items of no consequence to the use of the works remain outstanding; you are the contractor and you wish to formally start the Defects Liability Period clock, which entitles you to have the DLP run concurrently with any outstanding rectification works rather than remaining open-ended; you are the contractor and you are seeking to make a final payment claim for the balance of the contract sum, approved variations, and any retention due upon Practical Completion — combining the Notice of Practical Completion with a Payment Claim under the applicable Security of Payment Act is a common and efficient approach; you are the contractor and you need to formally transfer risk in the completed works to the principal, so that the principal's insurance obligation commences and the contractor can wind down construction insurance cover; and you are the principal or superintendent and you wish to issue a Certificate of Practical Completion acknowledging the contractor's Notice — this document can also be used by a principal or superintendent to record and certify Practical Completion.

A Notice of Practical Completion is a critical document in the administration of any commercial construction contract. Failure to issue the Notice promptly upon achieving Practical Completion may delay the commencement of the DLP, delay the contractor's entitlement to final payment, and create ambiguity about when risk passed to the principal.

What to Include in Your Notice of Practical Completion (Australia)

A well-drafted Australian Notice of Practical Completion should contain the following key elements.

Identification of the Contract and Parties — The Notice should clearly identify the construction contract by name, date, and reference number, and identify the contractor (as the party issuing the Notice) and the principal (as the party receiving it). Both parties' legal names, ABNs, and addresses should be included, together with the contractor's relevant licence number (for example, QBCC Licence in Queensland, NSW Fair Trading Contractor Licence, or VBA Registration in Victoria).

Clear Statement of the Date of Practical Completion — The Notice must state the specific date on which Practical Completion was achieved. This is the date from which the Defects Liability Period commences, risk passes to the principal, and the contractor's entitlement to final payment is triggered.

Description of the Works and Site — The Notice should include a description of the works that are the subject of the Notice and the address of the site. This is important for clarity, particularly where a contract encompasses multiple stages or separate works.

Basis for Practical Completion — The Notice should explain why the contractor considers Practical Completion to have been achieved — for example, the works are substantially complete in accordance with the Contract Documents, an occupation certificate has been obtained from the relevant local authority, or the works are ready for their intended use.

Outstanding Minor Defects Schedule — If any minor defects or items remain outstanding at the date of Practical Completion, these should be listed in the Notice with proposed completion dates. This demonstrates that the contractor is not claiming Practical Completion for works that contain significant outstanding items.

Defects Liability Period — The Notice should state the commencement date and duration of the DLP, and calculate the DLP expiry date. This avoids any dispute about when the DLP runs.

Final Payment Claim (Security of Payment) — Where the Notice is also serving as a Payment Claim under the applicable Security of Payment Act, it should clearly state the amount claimed, the breakdown of the claim, and the due date for payment. The reference to the applicable Act should be included to activate the statutory rights and obligations under that Act.

Additional compliance elements for a Notice of Practical Completion (Australia) used in Australia include: Under the Corporations Act 2001 (Cth), the Australian Securities and Investments Commission (ASIC) regulates companies and financial services. Section 127 of the Corporations Act 2001 governs company execution of documents. The Australian Competition and Consumer Commission (ACCC) enforces the Competition and Consumer Act 2010 (Cth). The Australian Taxation Office (ATO) administers the Goods and Services Tax under the A New Tax System (Goods and Services Tax) Act 1999. The Federal Court of Australia and Supreme Courts of each state have jurisdiction over corporate disputes. Forms-legal.com provides this template as a starting point for Australia-compliant documentation.

Cite this page

Reference this free template in an article, syllabus, or research note:

APA

Forms Legal. (2026). Notice of Practical Completion (Australia) (Australia) [Legal document template]. Forms Legal. https://forms-legal.com/australia/business/contracts/notice-of-practical-completion-australia

MLA

"Notice of Practical Completion (Australia) (Australia)." Forms Legal, 2026, https://forms-legal.com/australia/business/contracts/notice-of-practical-completion-australia.

BibTeX
@misc{formslegal-notice-of-practical-completion-australia,
  author       = {{Forms Legal}},
  title        = {Notice of Practical Completion (Australia) (Australia)},
  year         = {2026},
  howpublished = {\url{https://forms-legal.com/australia/business/contracts/notice-of-practical-completion-australia}},
  note         = {Free legal document template. Based on Corporations Act 2001 (Cth)}
}

Also available for these jurisdictions:

Frequently Asked Questions

Based on Corporations Act 2001 (Cth) — Template last modified June 2026Verify the source →

This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer

Found an error? Let us know

Related Documents

You may also find these documents useful:

Construction Contract (Australia)

Create a legally compliant Australian Construction Contract covering progress claims and payment schedules under the Security of Payment Acts (NSW Building and Construction Industry Security of Payment Act 1999, VIC Building and Construction Industry Security of Payment Act 2002, QLD Building Industry Fairness (Security of Payment) Act 2017), practical completion, defect liability, liquidated damages, retention at 5%, builder's licence requirements (QBCC/VBA), public liability and construction all risks insurance, home warranty insurance, WHS obligations under the Work Health and Safety Act 2011, and dispute resolution including statutory adjudication. Suitable for residential new builds, renovations, extensions, and commercial construction projects across all Australian states and territories.

Subcontractor Agreement (Australia)

Create a legally compliant Subcontractor Agreement for the Australian building and construction industry. Covers Security of Payment Act rights, payment claims, adjudication, retention, defects liability, variations, WHS obligations, public liability and workers' compensation insurance. Suitable for all states and territories.

Heads of Agreement (Australia)

Create an Australian Heads of Agreement (HOA) reflecting the three categories of preliminary agreement identified by the High Court of Australia in Masters v Cameron (1955) 91 CLR 353. Covers binding vs non-binding provisions, subject to contract clauses, good faith negotiation obligations, exclusivity periods, confidentiality, conditions precedent (including due diligence and regulatory approvals), costs allocation, and a long stop date. Suitable for mergers and acquisitions, joint ventures, distribution arrangements, licensing deals, and other commercial transactions in all Australian states and territories.

Demand Letter (Australia)

Create a formal Australian Demand Letter for contract breaches, defective works, misrepresentation, misleading conduct, or other civil wrongs — distinct from a simple debt collection letter. This template covers the full spectrum of pre-litigation civil demands under Australian law, including the Australian Consumer Law (ACL s 18, s 20–21), common law breach of contract, and the civil procedure requirements of all Australian states and territories. A demand letter of this type is a critical pre-litigation step used whenever a party has breached a contractual obligation beyond simply failing to pay an invoice. Common examples include: a builder or contractor who has abandoned works or delivered defective construction; a supplier who has failed to deliver goods as specified or has supplied goods that do not conform to the contract description; a party who has made misrepresentations that induced the other to enter into a contract; a business that has unlawfully terminated a service or supply agreement; a party who has breached confidentiality obligations; or a business whose conduct has been misleading or deceptive in trade or commerce contrary to section 18 of the Australian Consumer Law. The Australian Consumer Law, set out in Schedule 2 to the Competition and Consumer Act 2010 (Cth), applies throughout Australia and provides powerful rights for both consumers and businesses. Section 18 prohibits conduct in trade or commerce that is misleading or deceptive, or likely to mislead or deceive. Sections 20 and 21 prohibit unconscionable conduct. Where a breach of these provisions has caused loss or damage, the affected party is entitled to recover compensation under section 236 of the ACL. A formal demand letter is the appropriate first step before commencing proceedings in the applicable court. For contract breaches at common law, the innocent party is entitled to sue for damages representing the loss suffered as a result of the breach — either expectation damages (putting the innocent party in the position they would have been in had the contract been performed) or reliance damages (reimbursing expenditure wasted in reliance on the contract). In some cases, specific performance or an injunction may be available. A demand letter is the appropriate vehicle to put the breaching party on notice, demand specific performance or damages, and provide a deadline before proceedings are commenced. The applicable civil courts in each state and territory are: the Local Court (NSW, up to $100,000), Magistrates Court (VIC, up to $100,000; QLD, up to $150,000; WA, SA, TAS), District Court or County Court (intermediate claims), and Supreme Court (high-value claims). The Australian Capital Territory and Northern Territory have their own court hierarchy. Tribunals such as NCAT (NSW) and VCAT (VIC) handle consumer and home building disputes. The limitation period for contract claims in most Australian states is 6 years from the date the cause of action arose (Limitation Act 1969 (NSW), Limitation of Actions Act 1958 (VIC), Limitation of Actions Act 1974 (QLD) and equivalent). Issuing a formal demand letter well within the limitation period is important both to preserve rights and to comply with any pre-action requirements of the applicable court. This demand letter template is suitable for use throughout Australia in all states and territories. It includes space for a full factual background, identification of the legal basis of the claim under both common law and the ACL, a precise statement of the remedy demanded (payment of damages, completion of works, rectification, delivery of goods, or specific performance), a compliance deadline, an optional legal action warning identifying the intended court, and supporting documentation references. The letter may optionally be marked 'Without Prejudice' where settlement negotiations are intended to follow.