Skip to main content

Business

Renovation Contract (Malaysia)

A Renovation Contract for Malaysia governing interior and exterior renovation, refurbishment, or fitting-out works by a licensed contractor.

Key facts

MalaysiaMalaysiaEnglish (MY)FreePDF & Word
Legal basisCompanies Act 2016 (Act 777)Signature lines in this template: 2 parties
Renovation Contract

Contracts Act 1950 (Act 136) | CIDB Act 1994 (Act 520) | CIPAA 2012 (Act 746) | Street, Drainage and Building Act 1974 (Act 133)

THIS RENOVATION CONTRACT is entered into on [Contract Date]

BETWEEN:

(1) [Owner Name] (NRIC/SSM: [Owner IC/SSM]) of [Owner Address] (hereinafter referred to as the "Owner"); AND

(2) [Contractor Name] (Registration No. [Contractor Registration]) of [Contractor Address] (hereinafter referred to as the "Contractor").

1. RENOVATION WORKS

1.1 The Contractor shall carry out and complete the following renovation works (the "Works") at the property located at [Property Address] ([Property Type]):

[Scope of Works]

1.2 Key materials specification: [Materials Specification]

1.3 Owner-supplied materials: [Owner Supplied Materials]

1.4 Regulatory approvals: [MC/LA Approval]. The Contractor is responsible for complying with local authority requirements under the Street, Drainage and Building Act 1974 (Act 133) and the Uniform Building By-Laws 1984. For strata properties, the Contractor shall comply with the Strata Management Act 2013 (Act 757) and the Management Corporation's renovation by-laws.

2. CONTRACT PRICE AND PAYMENT

2.1 The Owner shall pay the Contractor the total contract price of [Contract Price] for the complete execution of the Works.

2.2 Payment schedule: [Payment Schedule].

2.3 Variations: [Variation Allowance]. All variation works must be agreed in writing by both Parties before commencement.

2.4 All payment claims and disputes are subject to the Construction Industry Payment and Adjudication Act 2012 (CIPAA 2012, Act 746). Pay-when-paid clauses are void under Section 35 of CIPAA 2012.

3. PROGRAMME AND COMPLETION

3.1 The Contractor shall commence the Works on [Commencement Date] and shall complete the Works by [Completion Date].

3.2 If the Works are not completed by [Completion Date], the Contractor shall pay liquidated damages at the rate of [Liquidated Damages], representing a genuine pre-estimate of the Owner's loss under Section 75 of the Contracts Act 1950.

3.3 Extensions of time may be granted in writing by the Owner for delays caused by the Owner, Force Majeure events, or other events beyond the Contractor's reasonable control.

4. DEFECTS LIABILITY

4.1 The defects liability period is [Defects Liability Period] from the date of practical completion.

4.2 During the defects liability period, the Contractor shall rectify at its own cost any defects in workmanship or materials notified by the Owner in writing. If the Contractor fails to rectify within 14 days of notice, the Owner may engage others and deduct the cost from retention monies or pursue recovery under the Contracts Act 1950, Section 74.

4.3 The Owner shall withhold 5% of the contract price as retention money until expiry of the defects liability period and satisfactory completion of all defect rectification.

5. SAFETY AND COMPLIANCE

5.1 The Contractor shall comply with the Occupational Safety and Health Act 1994 (Act 514) and all applicable DOSH regulations throughout the renovation period.

5.2 The Contractor shall obtain all necessary local authority permits, Fire Services Act 1988 (Act 341) approvals, and other regulatory approvals required for the Works, unless otherwise agreed in writing with the Owner.

6. DISPUTE RESOLUTION AND GOVERNING LAW

6.1 Dispute resolution: [Dispute Resolution].

6.2 This Contract is governed by the laws of Malaysia, including the Contracts Act 1950 (Act 136), the CIDB Act 1994 (Act 520), CIPAA 2012 (Act 746), and the Street, Drainage and Building Act 1974 (Act 133).

Owner

________________

Signature

Contractor

________________

Signature

What Is a Renovation Contract (Malaysia)?

A Renovation Contract in Malaysia fixes the respective duties and entitlements of the parties to the arrangement.

All renovation contractors in Malaysia who undertake works exceeding MYR 200,000 in value must be registered with the Construction Industry Development Board Malaysia (CIDB) under the CIDB Act 1994 (Act 520). For residential renovation works, the contractor may also need to be licensed under the Housing Development (Control and Licensing) Act 1966 (Act 118) if the works form part of a housing development. Even for minor renovation works below the CIDB threshold, local authority regulations — such as those issued by Dewan Bandaraya Kuala Lumpur (DBKL) or Majlis Bandaraya Petaling Jaya (MBPJ) — may require a building permit before structural works commence.

The Construction Industry Payment and Adjudication Act 2012 (CIPAA 2012, Act 746) applies to written renovation contracts. An unpaid renovation contractor may invoke CIPAA 2012 adjudication at the Asian International Arbitration Centre (AIAC) to recover progress payments without awaiting the outcome of litigation. This makes written renovation contracts with clear payment terms essential for both property owners and contractors.

For strata properties in Malaysia — apartments, condominiums, or stratified commercial properties — renovation works must comply with the Strata Management Act 2013 (Act 757) and the Management Corporation's by-laws. Section 32 of the Strata Management Act 2013 prohibits owners from carrying out renovations that affect common property, load-bearing walls, or structural elements without the Management Corporation's prior written approval.

When Do You Need a Renovation Contract (Malaysia)?

A Renovation Contract in Malaysia is required whenever a contractor is engaged to carry out renovation, fitting-out, or refurbishment works on a property.

A Renovation Contract is needed when a property owner commissions a contractor to renovate a residential terrace house, semi-detached, or bungalow in Malaysia. The contract defines the scope of works, materials to be used, completion date, and payment schedule, protecting both parties in the event of disputes over workmanship or non-payment.

A Renovation Contract is required when a business tenant fits out leased commercial premises. The tenant's obligations under the tenancy agreement to restore the premises typically make a detailed renovation contract essential to document original conditions, scope of alterations, and reinstatement obligations on expiry of the lease.

A Renovation Contract is needed for condominium or stratified property renovations requiring Management Corporation approval under the Strata Management Act 2013 (Act 757). The contract provides documentary evidence that works were carried out under agreed specifications, which may be required by the Management Corporation or the Commissioner of Buildings (COB) under the Strata Management (Maintenance and Management) Regulations 2015.

A Renovation Contract is required when a hotel, resort, or serviced apartment undergoes refurbishment by a hospitality operator. The contract must address disruption to existing operations, phasing of works, and compliance with the Fire Services Act 1988 (Act 341) and Occupational Safety and Health Act 1994 (Act 514) requirements during the renovation period.

A Renovation Contract is needed when a Malaysian employer engages a contractor for commercial office fit-out. The Jabatan Bomba dan Penyelamat Malaysia (JBPM, Fire and Rescue Department) requires fire safety compliance certification for commercial buildings under the Fire Services Act 1988 before the Certificate of Completion and Compliance (CCC) or Occupation Permit can be issued.

What to Include in Your Renovation Contract (Malaysia)

A valid Renovation Contract in Malaysia must contain the following key elements.

Parties and CIDB Status: Full legal names, identity card (MyKad) or company registration numbers, and, where applicable, CIDB contractor registration grade and category under CIDB Act 520. For works above MYR 200,000, CIDB registration is mandatory.

Scope of Works: A detailed, itemised description of all renovation works including demolition, structural, civil, finishing, mechanical, electrical, and IT works. Scope descriptions should reference approved drawings and material specifications to prevent disputes over 'what was included'. Vague scope is the primary cause of renovation disputes in Malaysia.

Materials Specification: Brand, grade, and specifications of all major materials including tiles, sanitary ware, electrical fittings, paint, and joinery. Where the owner supplies materials, the contract must specify supply responsibilities and risk transfer.

Contract Price in MYR: The total contract price in Malaysian Ringgit (MYR) on a lump-sum or schedule-of-rates basis. If variations are anticipated, a contingency sum and variation mechanism must be included consistent with CIPAA 2012 requirements.

Payment Schedule: Progress payment milestones tied to physical completion stages (e.g., 30% on commencement, 30% on completion of structural works, 30% on completion of finishing, 10% retention on completion). CIPAA 2012 (Act 746) governs payment disputes and prohibits 'pay when paid' clauses under Section 35.

Completion Date and Liquidated Damages: A definite completion date and a liquidated damages provision for delay, enforceable under Section 75 of the Contracts Act 1950 as a genuine pre-estimate of loss.

Permits and Approvals: Responsibility for obtaining local authority building permits under the Street, Drainage and Building Act 1974, Management Corporation approval under the Strata Management Act 2013, and any Fire Services Act 1988 compliance certificates.

Defects Liability Period: Typically 12-18 months for renovation works during which the contractor rectifies defects at its own cost. Retention money of 5% of contract value is commonly held until expiry of the defects period.

Dispute Resolution: Adjudication under CIPAA 2012 at the AIAC for payment disputes, followed by arbitration or litigation at the Kuala Lumpur Magistrate's Court or High Court depending on the amount in dispute.

Cite this page

CC BY 4.0 · free to cite

Reference this free template in an article, syllabus, or research note:

APA
Forms Legal. (2026). Renovation Contract (Malaysia) [Legal document template]. Forms Legal. https://forms-legal.com/malaysia/business/construction/renovation-contract-malaysia
MLA
"Renovation Contract (Malaysia)." Forms Legal, 2026, https://forms-legal.com/malaysia/business/construction/renovation-contract-malaysia.
Chicago
Forms Legal. "Renovation Contract (Malaysia)." Forms Legal, 2026. https://forms-legal.com/malaysia/business/construction/renovation-contract-malaysia.
BibTeX
@misc{formslegal-renovation-contract-malaysia,
  author       = {{Forms Legal}},
  title        = {Renovation Contract (Malaysia)},
  year         = {2026},
  howpublished = {\url{https://forms-legal.com/malaysia/business/construction/renovation-contract-malaysia}},
  note         = {Free legal document template. Based on Companies Act 2016 (Act 777)}
}
Wikipedia
{{cite web |title=Renovation Contract (Malaysia) |website=Forms Legal |publisher=Forms Legal |date=2026 |url=https://forms-legal.com/malaysia/business/construction/renovation-contract-malaysia}}
RIS
TY  - ELEC
T1  - Renovation Contract (Malaysia)
T2  - Forms Legal
PB  - Forms Legal
PY  - 2026
UR  - https://forms-legal.com/malaysia/business/construction/renovation-contract-malaysia
ER  - 
Forms Legal

Also available for these jurisdictions:

Frequently Asked Questions

Do I need a written Renovation Contract in Malaysia?

While Malaysian law under the Contracts Act 1950 does not require renovation contracts to be in writing to be legally binding, a written Renovation Contract is strongly recommended for several practical and legal reasons. First, the Construction Industry Payment and Adjudication Act 2012 (CIPAA 2012, Act 746) applies only to 'written construction contracts', meaning payment adjudication — the fast-track remedy for unpaid contractors — is available only if there is a written agreement. Without a written contract, an unpaid contractor must resort to civil litigation, which is slower and more expensive. Second, disputes over scope, materials, and payment terms are extremely common in Malaysian renovation projects, and a written contract provides the authoritative reference point for resolving these disputes. Third, Management Corporations of strata properties under the Strata Management Act 2013 typically require written renovation contracts and approved drawings before permitting works to commence.

What permits are needed before starting renovation works in Malaysia?

Renovation works in Malaysia may require several categories of permits depending on the nature and extent of the works. For structural alterations — including demolishing or relocating load-bearing walls, adding rooms, or changing the building's external appearance — a building plan approval from the local authority (pihak berkuasa tempatan) is required under the Street, Drainage and Building Act 1974 (Act 133) and the Uniform Building By-Laws 1984. In Kuala Lumpur, applications are submitted to Dewan Bandaraya Kuala Lumpur (DBKL). For strata properties, prior written approval from the Management Corporation is required under the Strata Management Act 2013 (Act 757) and the Strata Management (Maintenance and Management) Regulations 2015. Fire safety requirements may require approval from the Jabatan Bomba dan Penyelamat Malaysia (JBPM) for works affecting fire escape routes or fire suppression systems. Minor cosmetic works (painting, replacing non-structural fixtures) typically do not require permits.

What happens if a renovation contractor abandons a project in Malaysia?

If a renovation contractor abandons a project in Malaysia, the property owner has several legal remedies. Under the Contracts Act 1950, Section 40, the contractor's abandonment constitutes a repudiation of the contract, entitling the owner to accept the repudiation, treat the contract as terminated, and claim damages for the cost of completing the works with another contractor above the original contract price. The owner may claim damages under Section 74 of the Contracts Act 1950 for losses naturally arising from the breach. If the contractor has been paid in advance, the owner may also claim restitution for unjust enrichment. The owner should issue a formal notice of termination citing abandonment before engaging a replacement contractor to preserve the damages claim. If the contract includes a performance bond issued by a Malaysian bank or insurer, the owner may call on the bond as security. Adjudication under CIPAA 2012 is available for payment-related aspects of the dispute at the Asian International Arbitration Centre (AIAC).

Can a landlord require a tenant's Renovation Contract in Malaysia?

A landlord in Malaysia can and frequently does require a tenant to submit a written renovation contract, approved drawings, and contractor credentials as a condition of approving fit-out works. Most commercial tenancy agreements in Malaysia contain a landlord's approval requirement for alterations, and landlords routinely exercise this right to protect the structural integrity of the building and ensure regulatory compliance under the Street, Drainage and Building Act 1974 and the Uniform Building By-Laws 1984. Strata commercial property owners are governed by the Strata Management Act 2013 (Act 757), which grants the Management Corporation authority to approve or reject renovation plans. The landlord may also require the tenant to obtain reinstatement insurance and to include a reinstatement clause in the renovation contract requiring the contractor to restore the premises to original condition on expiry of the lease.

What is the warranty period for renovation works in Malaysia?

The warranty or defects liability period for renovation works in Malaysia is a matter of contract rather than statute, typically agreed at 12 to 18 months from practical completion. During this period, the renovation contractor must rectify defects in workmanship and materials at its own cost upon written notification from the owner. Malaysian courts apply the general law of contract under the Contracts Act 1950 to assess defects claims, with remedies including damages for cost of repair and consequential losses under Section 74. The Sale of Goods Act 1957 (Act 382) may also apply where defects arise from supplied goods, implying conditions of merchantable quality. For newly constructed properties, the Housing Development (Control and Licensing) Act 1966 provides a statutory defect liability period for housing developers, but this does not apply to purely renovation works carried out by independent contractors on existing properties.

Based on Companies Act 2016 (Act 777) — text last edited October 2026

This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer

Found an error? Let us know