Skip to main content

Civil Works Contract (India)

Civil Works Contract (India)

CIVIL WORKS CONTRACT

Indian Contract Act 1872 | PWD General Conditions of Contract

This Civil Works Contract is entered into on [Agreement Date] between [Employer Name], having its office at [Employer Address] (GSTIN: [Employer GSTIN]) (the "Employer"), and [Contractor Name], having its registered office at [Contractor Address] (CIN: [Contractor CIN], GSTIN: [Contractor GSTIN]) (the "Contractor").

1. PROJECT AND SCOPE OF WORKS

1.1 The Employer wishes to have constructed: [Project Name] at [Project Location] (the "Works").

1.2 The Contractor shall execute and complete the Works in accordance with the Contract Documents (comprising this Agreement, the Conditions of Contract, the Specification, the Drawings, and the Priced Bill of Quantities or Activity Schedule) and shall remedy any defects therein.

1.3 The Contractor acknowledges having examined the site, the Contract Documents, and all information relevant to the risks, contingencies, and other circumstances that may affect the execution of the Works.

2. CONTRACT PRICE AND PAYMENT

2.1 The Contract is a [Contract Type] contract. The Contract Price is [Contract Price], exclusive of GST. GST at the applicable rate under SAC 9954 of the CGST Act 2017 shall be payable additionally.

2.2 A mobilisation advance of [Advance Payment] shall be paid to the Contractor against an equivalent bank guarantee, to be recovered from monthly interim payment certificates.

2.3 Retention of [Retention Percent] shall be deducted from each interim payment certificate.

2.4 TDS shall be deducted by the Employer at the rate applicable under Section 194C of the Income Tax Act 1961 from each payment.

3. PROGRAMME AND COMPLETION

3.1 The Contractor shall commence the Works on [Commencement Date] and shall achieve Practical Completion by [Completion Date].

3.2 If the Contractor fails to complete the Works by the Completion Date for reasons within the Contractor's control, the Employer shall be entitled to deduct Liquidated Damages of [Liquidated Damages] as agreed compensation under Section 74 of the Indian Contract Act 1872.

3.3 The Contractor shall submit a detailed programme within 14 days of the commencement date for the Employer's acceptance.

4. PERFORMANCE SECURITY

4.1 The Contractor shall, within 14 days of the agreement date, provide a Performance Security of [Performance Security Percent] in the form of an unconditional bank guarantee from a scheduled commercial bank, valid until the expiry of the Defects Liability Period.

4.2 The Employer may call upon the Performance Security in the event of breach by the Contractor without any obligation to prove actual loss.

5. DEFECTS LIABILITY

5.1 The Defects Liability Period is [Defects Liability Period] from the date of Practical Completion. During this period, the Contractor shall rectify all defects notified by the Employer within 14 days.

5.2 Retention monies shall be released upon satisfactory completion of the Defects Liability Period.

6. SAFETY AND STATUTORY COMPLIANCE

6.1 The Contractor shall comply with the Building and Other Construction Workers Act 1996, the Contract Labour (Regulation and Abolition) Act 1970, the Employees' Compensation Act 1923, and all applicable state labour laws.

6.2 The Contractor shall maintain valid Contractor's All Risk insurance, Public Liability insurance, and Workmen's Compensation insurance.

7. GOVERNING LAW AND DISPUTES

7.1 This Contract is governed by the Indian Contract Act 1872 and the laws of India.

7.2 Disputes shall be resolved by arbitration under the Arbitration and Conciliation Act 1996. The seat of arbitration shall be the city where the Project is located. The arbitral tribunal shall comprise a sole arbitrator or a panel of three arbitrators, as agreed.

Employer (Authorised Signatory)

________________

Signature

Contractor (Authorised Signatory)

________________

Signature

Witness

________________

Signature

Maintained by Vladislav Sergienko, Founder·Template last modified: ·Report an error

What Is a Civil Works Contract (India)?

An India Civil Works Contract is a thorough construction contract under the Indian Contract Act 1872 between an employer (owner or developer) and a civil works contractor for the construction, alteration, repair, or demolition of a building or infrastructure project. The contract defines the scope of works, the contract price (lump sum or remeasured), the payment mechanism, the programme, variations, quality standards, safety obligations, defects liability, and dispute resolution.

In India, civil works contracts for government projects follow the CPWD (Central Public Works Department) General Conditions of Contract or applicable state PWD GCC, which are standard forms developed by the Government of India and state governments for use in public sector construction. For private sector projects, bespoke contracts or adaptations of international standard forms (FIDIC Red Book for remeasured works; FIDIC Yellow Book for design-build) are commonly used.

The Indian Contract Act 1872 governs the formation, performance, and enforcement of civil works contracts. Section 73 (compensation for breach) and Section 74 (liquidated damages) are the core remedies for delay and defective work. The Arbitration and Conciliation Act 1996 provides the framework for dispute resolution by arbitration.

BOCW Act 1996, Contract Labour (R&A) Act 1970, Employees' Compensation Act 1923, and applicable state labour laws impose extensive safety, welfare, and worker protection obligations on civil works contractors. GST on civil works is charged under SAC 9954 at 12% (government projects) or 18% (commercial and other projects), and TDS under Section 194C applies to contractor payments.

The legal framework governing the Civil Works Contract (India) in India draws on several key statutes and regulatory bodies. Under Indian law, the Indian Contract Act 1872 governs contractual obligations, with Section 10 setting essential requirements for valid agreements. The Companies Act 2013 regulates corporate entities through the Registrar of Companies (ROC) and Ministry of Corporate Affairs (MCA). The Industrial Disputes Act 1947 and state labour commissioners govern employment disputes. The Information Technology Act 2000 and IT (Reasonable Security Practices) Rules 2011 protect personal data. The Income Tax Act 1961 and Goods and Services Tax Act 2017 govern tax obligations through the Central Board of Direct Taxes (CBDT) and GST Council. Parties executing a Civil Works Contract (India) in India should confirm the document reflects current law, including any amendments enacted since the original drafting date. The Indian Contract Act, 1872 sets the foundational requirements.

When Do You Need a Civil Works Contract (India)?

A Civil Works Contract is needed for any construction, civil engineering, infrastructure, or demolition project involving a direct contract between an employer and a main contractor. It should be signed before any works commence on site.

A written contract is essential for government tenders and procurement, private sector commercial and industrial projects, infrastructure projects (roads, bridges, water supply, drainage), housing and residential development projects, and fit-out and refurbishment projects above a modest size. Without a written contract, disputes over scope, price, payment, and quality are extremely difficult to resolve and typically result in prolonged arbitration or litigation before the High Court or under the Arbitration and Conciliation Act 1996.

For public works contracts, government departments such as the Central Public Works Department (CPWD), National Highways Authority of India (NHAI), and state PWDs use standard form contracts based on the CPWD General Conditions of Contract or FIDIC-based documents. Private sector employers engage their own lawyers or use IIA/CIDC standard forms. In either case, a written Civil Works Contract is the mandatory starting point.

Under the Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act 1996 (BOCW Act), contractors employing 10 or more construction workers must register with the state BOCW board and pay BOCW cess at 1% of construction cost to the relevant authority. This obligation must be documented in the contract. The Contract Labour (Regulation and Abolition) Act 1970 regulates the employment of contract labour and requires the principal employer to register and the contractor to obtain a licence from the Labour Commissioner where 20 or more contract workers are engaged. Forms-legal.com provides this India Civil Works Contract as a starting point — for high-value projects, engage a construction lawyer to tailor the contract to the specific project requirements.

What to Include in Your Civil Works Contract (India)

A thorough India Civil Works Contract must include the following provisions to protect both employer and contractor and satisfy applicable statutory requirements.

Party details: Employer and contractor full legal names, registered addresses, CIN (for companies), PAN, and GSTIN. If the contractor is a partnership or proprietorship, names of all partners or proprietor.

Scope of works: Defined by reference to the contract drawings, specifications, and Bill of Quantities (BOQ) or Schedule of Works annexed to the contract. Any ambiguity in scope is typically resolved in the employer's favour in CPWD contracts, but in privately negotiated contracts, the interpretation rules must be stated.

Contract price: State whether lump sum, remeasured (BOQ-based), or cost-plus. For lump sum contracts, include the basis for price adjustment (price escalation formula, if any). For remeasured contracts, include the BOQ and unit rates. GST is charged at 12% on government construction works (SAC 9954, Item 3(iii)) or 18% on commercial and other projects.

Payment mechanism: Advance payment amount and conditions for its release; interim payment certificates based on work done (monthly or milestone-based); retention percentage (typically 5-10%) and conditions for its release; final account procedures. TDS under Section 194C of the Income Tax Act 1961 applies to contractor payments at 1% (individual/HUF) or 2% (others).

Programme: Contract commencement date, milestone dates, and completion date. State that time is of the essence where applicable, or specify that the remedy for delay is liquidated damages.

Liquidated damages: Rate per day or per week of delay (typically 0.5% of contract value per week, capped at 10%). Under Section 74 of the Indian Contract Act 1872, the court may award reasonable compensation up to the stipulated sum.

Variation procedure: Employer's right to order variations; written variation orders required; valuation of variations at contract rates where applicable, or at agreed rates for new items.

Defects liability: Period (typically 12 months from practical completion); contractor's obligation to rectify notified defects within the DLP; for RERA-registered projects, the statutory 5-year structural defects liability under Section 14(3) of RERA 2016 must be reflected.

Labour law compliance: BOCW Act 1996 cess payment; Contract Labour (R&A) Act 1970 compliance; Employees' Compensation Act 1923 obligations; minimum wages under the Minimum Wages Act 1948 as notified by the state Labour Commissioner.

Insurance: Contractor's All Risk (CAR) policy; public liability insurance; workmen's compensation insurance as required by the Employees' Compensation Act 1923.

Dispute resolution: Conciliation followed by arbitration under the Arbitration and Conciliation Act 1996; seat of arbitration; number of arbitrators; governing law is the Indian Contract Act 1872. Forms-legal.com provides this India Civil Works Contract — for projects above ₹1 crore, engage a qualified construction lawyer to review and tailor the contract.

Cite this page

Reference this free template in an article, syllabus, or research note:

APA

Forms Legal. (2026). Civil Works Contract (India) (India) [Legal document template]. Forms Legal. https://forms-legal.com/india/business/construction/civil-works-contract-india

MLA

"Civil Works Contract (India) (India)." Forms Legal, 2026, https://forms-legal.com/india/business/construction/civil-works-contract-india.

BibTeX
@misc{formslegal-civil-works-contract-india,
  author       = {{Forms Legal}},
  title        = {Civil Works Contract (India) (India)},
  year         = {2026},
  howpublished = {\url{https://forms-legal.com/india/business/construction/civil-works-contract-india}},
  note         = {Free legal document template. Based on Indian Contract Act, 1872}
}

Frequently Asked Questions

Based on Indian Contract Act, 1872 — Template last modified June 2026Verify the source →

This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer

Found an error? Let us know