Payment Claim (Singapore)
PAYMENT CLAIM
Served under the Building and Construction Industry Security of Payment Act 2004 (Cap. 30B) ("SOPA")
Payment Claim No.: [Claim Number]
Date: [Claim Date]
FROM (Claimant): [Claimant Name] (UEN: [Claimant UEN]), [Claimant Address]
TO (Respondent): [Respondent Name] (UEN: [Respondent UEN]), [Respondent Address]
1. CONTRACT AND PROJECT REFERENCE
1.1 Contract / PO: [Contract Number]
1.2 Project: [Project Name]
1.3 Claim Period: [Claim Period]
1.4 This Payment Claim is served as a payment claim under section 10 of SOPA.
2. SCHEDULE OF WORK DONE AND GOODS SUPPLIED
[Works Completed]
3. PAYMENT CLAIM SUMMARY
- Gross Progress Claim Amount: [Gross Claim Amount]
- Less: Retention: [Retention]
- Less: Previously certified/paid: [Previous Payments]
- Net Claim Amount (excl. GST): [Net Claim Amount]
- GST (9%): [GST Amount]
- TOTAL AMOUNT CLAIMED: [Total Claim Amount]
4. SOPA NOTICE TO RESPONDENT
4.1 The Respondent is required to serve a Payment Response on the Claimant by [Response Deadline] under section 11 of SOPA.
4.2 A Payment Response must be in writing and must state the response amount (which may be less than the claimed amount) and the reasons for any deduction.
4.3 If no Payment Response is served by [Response Deadline], the Claimant is entitled to make an adjudication application for the full claimed amount under section 12 of SOPA.
4.4 The adjudicated amount becomes a debt due and payable and may be enforced as a court judgment under section 27 of SOPA.
Claimant (Authorised Signatory)
________________
Signature
What Is a Payment Claim (Singapore)?
A Payment Claim in Singapore commences or advances proceedings by stating the claim and the relief sought.
SOPA was enacted by the Singapore Parliament in 2004, modelled on the New South Wales Building and Construction Industry Security of Payment Act 1999, to address the chronic problem of delayed and non-payment in the construction industry. The Building and Construction Authority (BCA) administers the registration of contractors and the regulatory framework for the construction industry, while SOPA is enforced through the adjudication process administered by authorised nominating bodies — the Singapore Mediation Centre (SMC) and the Singapore Institute of Architects (SIA).
Under Section 10(1) of SOPA, a claimant who has carried out construction work or supplied goods and services under a contract is entitled to serve a payment claim on the respondent for each progress payment. The payment claim must: (1) be in writing; (2) identify the contract to which the claim relates; (3) identify the construction work or goods and services to which the claim relates; (4) state the claimed amount (inclusive of GST, if applicable); and (5) be served on the respondent. Section 10(2) requires that the payment claim be served by the last day of each month following the month in which the work was carried out (the reference period), unless the contract specifies a different date.
The Court of Appeal in Grouteam Pte Ltd v UES Holdings Pte Ltd [2016] 5 SLR 1011 confirmed that strict compliance with SOPA's requirements is necessary for a valid payment claim. A payment claim that does not state the claimed amount, does not identify the contract, or is not served within the prescribed time is invalid and cannot found an adjudication application. The High Court in Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd [2018] 1 SLR 317 further clarified that a payment claim must be clearly and expressly identified as a payment claim under SOPA to put the respondent on notice of their obligation to serve a payment response.
The payment claim triggers a strict timeline under SOPA: the respondent must serve a Payment Response within 21 days of being served with the payment claim (or within the period prescribed by the contract, if shorter) under Section 11. If the respondent fails to pay or to serve a payment response, or if there is a dispute about the claimed amount, the claimant may make an adjudication application to an authorised nominating body within 7 days under Section 12. A related Payment Response document is the respondent's formal reply to the payment claim.
When Do You Need a Payment Claim (Singapore)?
A Payment Claim under SOPA is needed whenever a contractor, subcontractor, or supplier in Singapore's building and construction industry wishes to exercise their statutory right to claim payment for construction work done or goods and services supplied under a construction contract.
Main contractors claiming progress payments from project owners or developers must serve a Payment Claim under Section 10 of SOPA for each progress payment cycle. SOPA applies to all construction contracts entered into after 1 April 2005, including contracts for building works, civil engineering works, mechanical and electrical (M&E) works, renovation and fit-out works, and the supply of construction-related goods and services. The only contracts excluded from SOPA are construction contracts with the Government (Section 4(1)) and contracts for the supply of labour only (Section 4(2)).
Subcontractors claiming payment from main contractors need a SOPA Payment Claim to protect their cash flow when payment is disputed or delayed. The construction industry's multi-tier subcontracting structure means that subcontractors and sub-subcontractors are particularly vulnerable to payment delays. SOPA gives subcontractors a direct statutory right to claim payment from the party who engaged them, regardless of whether the main contractor has been paid by the project owner — SOPA specifically overrides pay-when-paid clauses under Section 9.
Suppliers of construction materials, equipment, and prefabricated components claiming payment from contractors need a SOPA Payment Claim for goods supplied under a construction contract. Section 2 of SOPA defines construction work broadly to include the supply of goods and services related to construction, and material suppliers who supply concrete, steel, timber, or other construction materials under a supply contract linked to a construction project are entitled to serve payment claims under SOPA.
Design consultants — including architects, engineers, and quantity surveyors — claiming professional fees from project owners or contractors may serve a SOPA Payment Claim for services rendered under a consultancy agreement that is a construction contract within the meaning of SOPA. The definition of supply of goods and services in Section 2 includes the provision of professional services in connection with construction work.
Contractors and subcontractors who have received a disputed payment response or no payment response at all need to serve a valid SOPA Payment Claim as a prerequisite to adjudication. Without a properly served payment claim, the claimant cannot apply for adjudication under Section 12 of SOPA. A related Construction Contract or Subcontractor Agreement establishes the underlying contractual relationship.
What to Include in Your Payment Claim (Singapore)
A Singapore Payment Claim compliant with Section 10 of the Building and Construction Industry Security of Payment Act 2004 (SOPA, Cap. 30B) and the case law of the Singapore courts must include the following mandatory elements. The forms-legal.com Payment Claim template addresses all statutory requirements and incorporates standard practices established by the Court of Appeal and High Court decisions on SOPA payment claims.
SOP identification: The payment claim must be clearly and expressly identified as a payment claim made under SOPA. The Court of Appeal in Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd held that a payment claim must put the respondent on notice that the claim is made under SOPA, triggering the respondent's statutory obligation to serve a payment response within the prescribed period. A prominent header stating "Payment Claim under the Building and Construction Industry Security of Payment Act (Cap. 30B)" satisfies this requirement.
Party identification requires the claimant's full name or company name and UEN registered with ACRA, the claimant's address, and the respondent's full name or company name and UEN and address. Where the claimant is a subcontractor, the respondent is the main contractor or the party who engaged the subcontractor directly.
Contract identification must specify the contract to which the payment claim relates — including the contract title or reference number, the contract date, the project name and address, and a brief description of the contracted scope of work. Where the claimant is working under a purchase order or letter of award rather than a formal contract, the purchase order or letter of award details should be stated.
Reference period must identify the period of work to which the payment claim relates — typically the month in which the construction work was carried out or the goods and services were supplied. Under Section 10(2) of SOPA, the payment claim must be served by the last day of the month following the reference period (or the date prescribed by the contract, if different).
Claimed amounts must be itemised and must state the total amount claimed inclusive of Goods and Services Tax (GST) at the prevailing rate (currently 9% under the Goods and Services Tax Act, Cap. 117A). The claim should include: a breakdown of work done by trade, item, or milestone; the total contract sum and the cumulative value of work done to date; the value of previous payment claims and payments received; retention amounts (if applicable); and the net amount now claimed. Supporting documentation — including progress valuation certificates, delivery orders, invoices, and attendance records — should accompany the claim.
Payment due date must state the date by which payment is due under the contract. Under Section 8(1) of SOPA, the payment due date is the date specified in the contract or, if the contract does not specify a due date, 35 days after the payment claim is served. Interest on late payment accrues at the rate specified in the contract or, in the absence of contractual provision, at the prescribed rate.
SOPA notice must include a statement advising the respondent that failure to serve a Payment Response within the prescribed period (21 days from service of the payment claim, or the contractual period if shorter) entitles the claimant to apply for adjudication under Section 12 of SOPA, and that an adjudication determination may be enforced as a judgment of the court under Section 27. A related Performance Bond may secure the respondent's payment obligations under the construction contract.
Cite this page
Reference this free template in an article, syllabus, or research note:
Forms Legal. (2026). Payment Claim (Singapore) (Singapore) [Legal document template]. Forms Legal. https://forms-legal.com/singapore/business/construction/payment-claim-singapore
"Payment Claim (Singapore) (Singapore)." Forms Legal, 2026, https://forms-legal.com/singapore/business/construction/payment-claim-singapore.
@misc{formslegal-payment-claim-singapore,
author = {{Forms Legal}},
title = {Payment Claim (Singapore) (Singapore)},
year = {2026},
howpublished = {\url{https://forms-legal.com/singapore/business/construction/payment-claim-singapore}},
note = {Free legal document template. Based on Companies Act 1967 (Cap. 50)}
}Also available for these jurisdictions:
Frequently Asked Questions
The Building and Construction Industry Security of Payment Act 2004 (SOPA, Cap. 30B) is Singapore's principal legislation protecting the cash flow rights of persons who carry out construction work or supply goods and services in the building and construction industry. SOPA was enacted by Parliament in 2004 and is modelled on the New South Wales Building and Construction Industry Security of Payment Act 1999.
SOPA establishes a statutory payment framework that: (1) creates a right to progress payments for construction work done and goods and services supplied; (2) requires respondents (employers, main contractors) to serve payment responses within prescribed timelines; (3) provides a rapid adjudication process (typically completed within 7-14 days) for disputed payment claims; and (4) allows adjudication determinations to be enforced as judgments of the court.
SOPA applies to all construction contracts entered into after 1 April 2005, with limited exceptions — contracts with the Government and contracts for the supply of labour only are excluded under Section 4. SOPA overrides contractual provisions that restrict or deny a claimant's right to payment, including pay-when-paid clauses (Section 9), pay-if-paid clauses, and conditional payment mechanisms that make payment dependent on the respondent receiving payment from a higher-tier party.
If the respondent fails to serve a Payment Response within the prescribed period after receiving a valid Payment Claim under SOPA, the consequences are significant and immediate.
Under Section 11(1) of SOPA (Cap. 30B), the respondent must serve a payment response within 21 days of being served with the payment claim, or within the period specified in the contract (whichever is shorter). The payment response must state the response amount (the amount the respondent proposes to pay) and the reasons for any difference between the claimed amount and the response amount.
If the respondent fails to serve a payment response within the prescribed period, the claimant may apply for adjudication under Section 12 of SOPA. Critically, under Section 15(3), the adjudicator must treat the claimant's claimed amount as the adjudicated amount if the respondent has not served a payment response — the respondent is effectively barred from contesting the quantum of the claim in the adjudication proceedings. The Court of Appeal in W Y Steel Construction Pte Ltd v Osko Pte Ltd [2013] 3 SLR 380 confirmed that the failure to serve a payment response has severe consequences and that respondents must comply strictly with SOPA's timelines.
Service of a payment claim under SOPA must comply with Section 37 of the Building and Construction Industry Security of Payment Act 2004 (Cap. 30B), which prescribes the modes of service for documents under the Act.
Section 37 provides that a payment claim may be served by: (1) delivering it personally to the respondent or to a person authorised to accept service on behalf of the respondent; (2) leaving it at the respondent's usual or last known place of residence or business; (3) sending it by registered post to the respondent's usual or last known place of residence or business (deemed served 2 days after posting under the Interpretation Act, Cap. 1); or (4) any other mode of service agreed between the parties in the contract.
Many construction contracts in Singapore specify additional or alternative modes of service, such as email or courier delivery to the project site office. The Court of Appeal in Grouteam Pte Ltd v UES Holdings Pte Ltd [2016] 5 SLR 1011 held that service must comply strictly with SOPA's requirements, and a payment claim that is not properly served may be invalid for the purposes of founding an adjudication application.
Yes, a SOPA payment claim in Singapore should include Goods and Services Tax (GST) in the claimed amount where the claimant is a GST-registered entity. Under the Goods and Services Tax Act (Cap. 117A), GST at the standard rate (currently 9%) is charged on the supply of construction work and goods in Singapore by a GST-registered person.
The claimed amount in a SOPA payment claim is typically stated as the net value of work done plus GST. The payment claim should clearly show the net amount and the GST amount separately, and the total claimed amount inclusive of GST. This is consistent with standard construction industry practice in Singapore and the requirements of IRAS for GST accounting.
The adjudicator, when determining the adjudicated amount under Section 17 of SOPA (Cap. 30B), determines the amount payable inclusive of any applicable tax. The respondent's payment response should similarly state the response amount inclusive of GST where the claimant is GST-registered.
Claimants who are not GST-registered (because their annual taxable turnover is below the S$1 million registration threshold) do not charge GST and should state their claimed amount without GST. Respondents should verify the claimant's GST registration status when processing payment claims to avoid incorrect input tax claims. GST-registered respondents who pay the claimed amount inclusive of GST may claim the GST component as input tax credit on their GST returns, subject to the input tax claiming rules.
A payment claim under SOPA and a standard commercial invoice are legally distinct documents with different purposes, requirements, and consequences in Singapore's construction industry.
A SOPA payment claim is a statutory document governed by Section 10 of the Building and Construction Industry Security of Payment Act 2004 (Cap. 30B). A valid payment claim must: identify itself as a claim under SOPA; identify the contract; specify the construction work or goods and services; state the claimed amount; and be served on the respondent within the prescribed timeframe. A valid payment claim triggers the respondent's statutory obligation to serve a payment response within 21 days and gives the claimant the right to adjudication if payment is disputed.
A standard commercial invoice is a billing document issued for accounting and tax purposes. While an invoice typically contains similar information — the parties, the work or goods, and the amount — it does not carry the statutory consequences of a SOPA payment claim. An invoice that does not expressly state it is a SOPA payment claim may not satisfy the requirements of Section 10 and may not found an adjudication application.
This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer
Found an error? Let us knowRelated Documents
You may also find these documents useful:
Payment Response (Singapore)
A statutory response to a SOPA Payment Claim served under the Building and Construction Industry Security of Payment Act 2004 in Singapore. The respondent (employer or main contractor) must serve this document within the prescribed period to dispute or accept the claimed amount. Failure to respond in time deems the full claimed amount payable and allows immediate adjudication.
Construction Contract (Singapore)
A building and construction contract for Singapore, compliant with the Building and Construction Industry Security of Payment Act 2004 (BCIA) and the Building Control Act 1989. Covers scope of works, payment claims, variations, defects liability, adjudication rights, and dispute resolution under Singapore construction law.
Subcontractor Agreement (Singapore)
A subcontracting agreement for construction works in Singapore, addressing BCIA payment claim rights for subcontractors, back-to-back main contract conditions, WSHA safety obligations, nominated and domestic subcontractor arrangements, and retention money under the Building and Construction Industry Security of Payment Act 2004.
Performance Bond (Singapore)
A construction performance guarantee bond issued by a bank or insurance company in Singapore, guaranteeing a contractor's performance of a construction contract. Covers on-demand and conditional bond forms, call procedures, and the employer's right to call on the bond for contractor default. Addresses the Singapore Court of Appeal's position on unconscionability as a defence to bond calls.
Defects Liability Notice (Singapore)
A formal written notice from an employer or building owner to a contractor identifying construction defects requiring rectification during the defects liability period in Singapore. Serves as the contractual trigger for the contractor's obligation to return and make good defects without additional charge. Relevant to all construction contracts including SIA, PSSCOC, and REDAS standard forms.