Renewable Energy Agreement (Nigeria)
RENEWABLE ENERGY AGREEMENT
Electricity Act 2023 | Nigerian Electricity Regulatory Commission (NERC) Regulations
Rural Electrification Agency (REA) Mini-Grid Regulations 2016
THIS RENEWABLE ENERGY AGREEMENT is entered into on [Agreement Date]
BETWEEN:
(1) [Developer Name] (CAC RC No. [Developer RC Number]) of [Developer Address] ("the Developer"); AND
(2) [Offtaker Name] of [Offtaker Address] ("the Off-Taker / Site Owner").
1. PROJECT DESCRIPTION
1.1 The Developer agrees to develop, install, commission, operate, and maintain a [Technology Type] renewable energy system with an installed capacity of [Installed Capacity] ("the System") at the following site: [Site Address] (Land Title: [Site Title Ref]) ("the Site").
1.2 The transaction structure is [Transaction Structure]. The Developer holds or shall obtain the applicable regulatory authorisation: [NERC Licence] from the Nigerian Electricity Regulatory Commission (NERC) under the Electricity Act 2023.
1.3 The System shall be designed and installed to meet the applicable Standards Organisation of Nigeria (SON) standards and the National Electrical Safety Code.
2. COMMERCIAL TERMS
2.1 The Off-Taker shall purchase electricity generated by the System at a tariff of [Tariff Rate] ("the Tariff"). The Tariff shall be reviewed in accordance with the tariff escalation mechanism agreed between the parties.
2.2 The Developer guarantees an annual energy yield of [Annual Energy Yield]. Where the actual yield falls below the guaranteed level by more than 5%, the Developer shall credit the Off-Taker's account in accordance with the underperformance remedy in Schedule 1.
2.3 Payment Terms: [Payment Terms]
2.4 The Off-Taker shall provide the following payment security: [Security Package]
3. AGREEMENT TERM AND COMMENCEMENT
3.1 This Agreement shall commence on the Commercial Operation Date (COD), targeted for [Commencement Date], and shall continue for [Agreement Term] unless earlier terminated in accordance with this Agreement.
3.2 The Commercial Operation Date (COD) shall be the date on which the System passes the acceptance tests and is commissioned for commercial electricity generation, as confirmed in writing by both parties.
4. OWNERSHIP, INSURANCE, AND MAINTENANCE
4.1 Under the [Transaction Structure] structure, ownership of the System throughout the Agreement term is as set out in Schedule 2. The Developer shall maintain all-risks property insurance and third-party liability insurance for the System under the Insurance Act 2003 throughout the term.
4.2 The Developer shall maintain the System in accordance with the manufacturer's recommendations and Nigerian standards, and shall rectify any material fault within the response times set out in Schedule 3 (Service Level Agreement).
5. FORCE MAJEURE AND GRID CURTAILMENT
5.1 Neither party shall be liable for failure to perform its obligations under this Agreement to the extent caused by a Force Majeure Event — including acts of God, government action, war, grid unavailability due to action or inaction of the Transmission Company of Nigeria (TCN) or the relevant distribution licensee (DisCo), and extended power outages beyond either party's control.
5.2 The financial risk of grid curtailment for on-grid projects shall be allocated between the parties as set out in Schedule 4.
6. GOVERNING LAW AND DISPUTE RESOLUTION
6.1 This Agreement is governed by the laws of the Federal Republic of Nigeria, including the Electricity Act 2023, the NERC Regulations, and the Land Use Act 1978 in respect of the Site.
6.2 Any dispute arising from this Agreement shall first be referred to senior management of both parties for negotiation. If unresolved within 30 days, the dispute shall be referred to arbitration in Lagos, Nigeria under the Arbitration and Mediation Act 2023, with the award enforceable before the Federal High Court of Nigeria.
Developer (Authorised Signatory)
________________
Signature
Off-Taker / Site Owner (Authorised Signatory)
________________
Signature
What Is a Renewable Energy Agreement (Nigeria)?
A Renewable Energy Agreement in Nigeria governs the relationship between the parties by fixing what each must do.
The legal framework governing renewable energy in Nigeria underwent a fundamental reform with the enactment of the Electricity Act 2023, which repealed the Electric Power Sector Reform Act 2005 (EPSRA) and established a new regulatory architecture for the Nigerian electricity sector. The Electricity Act 2023 devolves significant regulatory authority to state governments — allowing each state to establish its own electricity regulatory framework for intra-state electricity transactions — while the Nigerian Electricity Regulatory Commission (NERC), established under the Nigerian Electricity Regulatory Commission Act 2021, retains jurisdiction over interstate and inter-zonal electricity transactions and over the wholesale electricity market.
The Rural Electrification Agency (REA), established under the Rural Electrification Fund Act and reconstituted under the Electricity Act 2023, administers the Rural Electrification Fund and provides financing and technical support for off-grid and mini-grid renewable energy projects serving rural and underserved communities in Nigeria. REA-supported projects are subject to the REA's Mini-Grid Regulations 2016 (as amended) and the REA's off-grid project development guidelines.
Key transaction structures for renewable energy agreements in Nigeria include: Power Purchase Agreements (PPAs), in which the developer sells electricity to an off-taker (corporate, government agency, or distribution company) at an agreed tariff; Energy-as-a-Service (EaaS) or lease agreements, in which the developer owns and operates the system and charges the host site owner a monthly service fee or per-kWh tariff; Engineering, Procurement, and Construction (EPC) agreements, in which the developer constructs and hands over a system to the site owner; and Build-Operate-Transfer (BOT) structures used for larger utility-scale projects.
NERC licensing requirements are central to renewable energy project development in Nigeria. Developers generating electricity above the NERC permit threshold (currently 1 MW for on-grid projects) must hold a NERC Generation Licence or Permit. Off-grid mini-grid projects may qualify for a simplified NERC Mini-Grid Permit or REA registration depending on their size and commercial structure. Solar installations below 1 MW for self-consumption (captive power) are generally exempt from NERC licensing under the Electricity Act 2023 but must comply with applicable safety standards from the Standards Organisation of Nigeria (SON) and the National Electrical Safety Code.
The legal framework governing the Renewable Energy Agreement (Nigeria) in Nigeria draws on several key statutes and regulatory bodies. Under Nigerian law, the Companies and Allied Matters Act 2020 (CAMA) regulates corporate entities through the Corporate Affairs Commission (CAC). The Labour Act (Cap L1 LFN 2004) and the National Industrial Court of Nigeria (NICN) govern employment disputes. The Nigeria Data Protection Regulation (NDPR) 2019 and the Nigeria Data Protection Commission (NDPC) protect personal data. The Federal Inland Revenue Service (FIRS) administers tax obligations under the Companies Income Tax Act. The Federal High Court and state High Courts have jurisdiction over civil matters. Parties executing a Renewable Energy Agreement (Nigeria) in Nigeria should confirm the document reflects current law, including any amendments enacted since the original drafting date. The Companies and Allied Matters Act (CAMA) 2020 sets the foundational requirements.
When Do You Need a Renewable Energy Agreement (Nigeria)?
A Renewable Energy Agreement is required in Nigeria whenever a developer proposes to develop, install, or operate a renewable energy system at a site owned by another party, or to supply electricity generated from a renewable source to an identified off-taker under a structured commercial arrangement.
A Renewable Energy Agreement is required when a solar energy developer installs a rooftop or ground-mounted solar PV system at a commercial or industrial facility — such as a manufacturing plant, shopping mall, or bank branch — under a power purchase agreement (PPA) or energy-as-a-service arrangement, under which the developer retains ownership of the system and charges the host for electricity consumed.
A Renewable Energy Agreement is needed when a mini-grid developer supported by the Rural Electrification Agency (REA) constructs a solar mini-grid to serve an unelectrified rural community in Nigeria, with the agreement governing the terms of electricity supply to households and small businesses in the community under the REA's Mini-Grid Regulations 2016.
A Renewable Energy Agreement is required when a large industrial energy consumer — such as a cement plant, brewery, or telecommunications company — enters into a long-term power purchase agreement with a renewable energy independent power producer (IPP) holding a NERC Generation Licence for a utility-scale solar or wind farm, under which the IPP supplies electricity at an agreed tariff indexed to the naira-dollar exchange rate.
A Renewable Energy Agreement is needed when a state government or Local Government Area (LGA) in Nigeria contracts with a renewable energy developer to supply power to government facilities — schools, hospitals, water treatment plants — under the devolved state electricity regulatory framework established by the Electricity Act 2023.
A Renewable Energy Agreement is required when a developer enters into a Build-Operate-Transfer (BOT) arrangement with a site owner — such as a real estate developer or industrial park operator — under which the developer constructs and operates a renewable energy system for an agreed period before transferring ownership to the site owner at the end of the BOT term, with the agreement governing the construction milestones, performance standards, energy yield guarantees, and transfer mechanics.
Under Nigerian law, the Companies and Allied Matters Act 2020 (CAMA) regulates corporate entities through the Corporate Affairs Commission (CAC). The Labour Act (Cap L1 LFN 2004) and the National Industrial Court of Nigeria (NICN) govern employment disputes. The Nigeria Data Protection Regulation (NDPR) 2019 and the Nigeria Data Protection Commission (NDPC) protect personal data. The Federal Inland Revenue Service (FIRS) administers tax obligations under the Companies Income Tax Act. The Federal High Court and state High Courts have jurisdiction over civil matters.
What to Include in Your Renewable Energy Agreement (Nigeria)
A valid Renewable Energy Agreement in Nigeria must contain the following essential elements to comply with the Electricity Act 2023, NERC regulations, and Nigerian contract law.
Parties and Project Description: Full legal names and addresses of the developer (holding or to be obtained NERC licence or permit) and the host site owner or off-taker; a description of the renewable energy technology (solar PV, wind, mini-hydro, biomass); the installed capacity in kilowatts peak (kWp) or megawatts (MW); and the site address with GPS coordinates and Land Use Act 1978 title evidence (Certificate of Occupancy or Right of Occupancy).
Regulatory Compliance: Confirmation that the project will obtain or has obtained the applicable NERC licence or permit — Generation Licence for grid-connected projects above 1 MW, Mini-Grid Permit or REA registration for off-grid projects — and that the equipment will meet Standards Organisation of Nigeria (SON) standards and the National Electrical Safety Code. For REA-funded projects, the agreement must comply with the REA's Mini-Grid Regulations 2016 and the REA's standard project development conditions.
Energy Yield and Performance Guarantee: The developer's obligation to design and install the system to achieve a specified annual energy yield (in kWh/year), with an energy yield guarantee and a performance ratio (PR) standard; the consequences of underperformance (energy credit, liquidated damages, or system upgrade obligation); and the method of measurement using calibrated metering equipment approved by NERC or the relevant state electricity regulator.
Tariff and Payment Terms: The agreed electricity tariff per kWh (in Nigerian naira, NGN, with or without indexation to inflation or the CBN exchange rate); the billing period and payment terms; the consequences of late payment; and the procedure for tariff review over the agreement term — particularly important for long-term PPAs (10–25 years) in the context of Nigeria's electricity tariff regulatory framework administered by NERC.
System Ownership, Insurance, and Maintenance: Whether the developer or the off-taker owns the system throughout the agreement term (under a PPA or EaaS structure, ownership remains with the developer; under an EPC or BOT structure, ownership transfers); the developer's maintenance obligations and service level commitments (response times for fault rectification, scheduled maintenance windows); and the insurance requirements for the system under the Insurance Act 2003, including property all-risk and third-party liability coverage.
Force Majeure and Grid Connection: Treatment of force majeure events relevant to Nigerian renewable energy projects — including grid unavailability, curtailment by the system operator (Transmission Company of Nigeria — TCN), and extreme weather events — with allocation of the financial risk of curtailment between developer and off-taker. For grid-connected projects, the agreement must address the terms of the grid connection agreement with the relevant distribution licensee (DisCo) or the TCN.
Term, Termination, and Transfer: The agreement term (typically 15–25 years for solar PV); the conditions for early termination by either party; the developer's step-in rights if the off-taker defaults; and, for BOT structures, the transfer mechanics including system condition requirements at transfer, assignment of warranties from the EPC contractor, and title transfer under the Land Use Act 1978.
Additional compliance elements for a Renewable Energy Agreement (Nigeria) used in Nigeria include: Under Nigerian law, the Companies and Allied Matters Act 2020 (CAMA) regulates corporate entities through the Corporate Affairs Commission (CAC). The Labour Act (Cap L1 LFN 2004) and the National Industrial Court of Nigeria (NICN) govern employment disputes. The Nigeria Data Protection Regulation (NDPR) 2019 and the Nigeria Data Protection Commission (NDPC) protect personal data. The Federal Inland Revenue Service (FIRS) administers tax obligations under the Companies Income Tax Act. The Federal High Court and state High Courts have jurisdiction over civil matters. Forms-legal.com provides this template as a starting point for Nigeria-compliant documentation.
Cite this page
Reference this free template in an article, syllabus, or research note:
Forms Legal. (2026). Renewable Energy Agreement (Nigeria) (Nigeria) [Legal document template]. Forms Legal. https://forms-legal.com/nigeria/business/corporate/renewable-energy-agreement-nigeria
"Renewable Energy Agreement (Nigeria) (Nigeria)." Forms Legal, 2026, https://forms-legal.com/nigeria/business/corporate/renewable-energy-agreement-nigeria.
@misc{formslegal-renewable-energy-agreement-nigeria,
author = {{Forms Legal}},
title = {Renewable Energy Agreement (Nigeria) (Nigeria)},
year = {2026},
howpublished = {\url{https://forms-legal.com/nigeria/business/corporate/renewable-energy-agreement-nigeria}},
note = {Free legal document template. Based on Companies and Allied Matters Act (CAMA) 2020}
}Also available for these jurisdictions:
Frequently Asked Questions
The licensing requirements for renewable energy projects in Nigeria under the Electricity Act 2023 and the Nigerian Electricity Regulatory Commission (NERC) framework depend on the project's size, connection type (on-grid or off-grid), and commercial structure. For on-grid projects generating electricity above 1 MW that will be sold to third parties or fed into the grid, the developer must hold a NERC Generation Licence issued under the Electricity Act 2023. The NERC Generation Licence application requires submission of technical, financial, and environmental documentation, including an Environmental Impact Assessment (EIA) approved by the Federal Ministry of Environment (FMEnv) or a state environmental agency for projects of the applicable scale. For off-grid mini-grid projects serving rural communities, the developer may apply for a NERC Mini-Grid Permit or register with the Rural Electrification Agency (REA) under the REA's Mini-Grid Regulations 2016, depending on the project's capacity and the number of customers served. Solar PV installations below 1 MW used for self-consumption (captive power) at the developer's own or the off-taker's premises are generally exempt from NERC licensing under the Electricity Act 2023, but the equipment must comply with Standards Organisation of Nigeria (SON) certification requirements for solar panels and inverters.
Power Purchase Agreements (PPAs) for solar projects in Nigeria are typically structured as long-term (15–25 year) contracts between the solar developer (as seller) and the off-taker (as buyer) under which the developer agrees to generate and supply a specified quantity of electricity from a solar PV system at a defined site, and the off-taker agrees to purchase the electricity at a negotiated tariff per kWh expressed in Nigerian naira (NGN). The PPA tariff structure in Nigeria typically includes a fixed capacity charge (payable regardless of actual electricity generation, covering the developer's capital costs and debt service) and a variable energy charge (reflecting actual kWh generated). Many Nigerian solar PPAs include a tariff escalation mechanism — either a fixed annual percentage increase or indexation to the Consumer Price Index (CPI) published by the National Bureau of Statistics (NBS) — to protect the developer against naira inflation over the PPA term. Currency risk is a significant issue in Nigerian solar PPAs because the capital cost of solar equipment is denominated in US dollars (USD) while revenues are collected in naira, creating an exchange rate exposure that is typically addressed through partial USD-indexation of the tariff or through project financing structures involving dollar-denominated loans from development finance institutions such as the African Development Bank (AfDB), the International Finance Corporation (IFC), or the Development Finance Institution of Nigeria (DFIN).
The Rural Electrification Agency (REA) is a Federal Government agency established under the Rural Electrification Fund Act and reconstituted under the Electricity Act 2023 with the mandate to enable access to electricity in rural and underserved communities in Nigeria through off-grid and mini-grid renewable energy solutions. The REA administers the Rural Electrification Fund (REF), which provides grant financing, concessional loans, and technical assistance to developers of mini-grid and standalone solar home system (SHS) projects serving communities without grid access. The REA's Mini-Grid Regulations 2016 (as amended) establish the regulatory framework for mini-grid projects under 1 MW in Nigeria, providing for REA registration, tariff-setting guidelines, and protections for mini-grid operators against grid encroachment (the risk that a distribution company extends the main grid to the mini-grid's service area, threatening the mini-grid's commercial viability). The REA has developed standard project development templates — including standard power purchase agreements for mini-grid projects and standard host community agreements — that developers using REA funding are required to use. The REA also administers the Energising Economies Initiative and the Energising Education Programme, through which it funds solar mini-grids for markets and university campuses respectively.
The Electricity Act 2023 (EA 2023) introduced fundamental changes to the Nigerian electricity sector regulatory framework that significantly affect renewable energy project development. First, devolution: the EA 2023 devolves regulatory authority over intra-state electricity generation, transmission, and distribution to state governments, allowing each state to establish its own electricity regulatory body and licensing framework. This means renewable energy developers in states that have activated their state electricity markets — such as Lagos, Rivers, and Kaduna — must engage with both NERC (for interstate and wholesale transactions) and the relevant state regulator (for intra-state retail supply). Second, the EA 2023 introduces provisions for eligible customers — large industrial and commercial consumers — to procure electricity directly from licensed generators (including renewable IPPs) bypassing the distribution companies (DisCos), enabling corporate renewable PPAs of the type common in South Africa. Third, the EA 2023 establishes the Nigerian Electricity Liability Management Authority (NEMA) to manage legacy sector liabilities, improving the financial health of sector participants and the bankability of renewable energy projects. Fourth, the EA 2023 includes provisions for the issuance of stranded asset certificates and for the monetisation of renewable energy certificates (RECs) — important for attracting private investment into the sector.
Renewable energy agreements in Nigeria involve a distinctive set of risks arising from the Nigerian operating environment, and the allocation of these risks between developer and off-taker is a central negotiation in PPA and EaaS transactions. The principal risks and their typical allocation are as follows. Currency risk: the mismatch between USD-denominated capital costs and naira revenues is typically shared, with partial USD-indexation of the tariff negotiated between the parties — larger corporate off-takers may accept greater currency risk while smaller or government off-takers typically resist tariff USD-indexation. Grid connectivity risk: the risk that the distribution company (DisCo) or the Transmission Company of Nigeria (TCN) is unable to provide grid connection or that grid instability causes curtailment is typically borne by the developer for on-grid projects, with force majeure provisions addressing extended grid unavailability. Off-taker credit risk: the risk that the off-taker fails to pay the PPA tariff is a significant concern in the Nigerian market — it is addressed through security packages including irrevocable standby letters of credit from CBN-regulated banks, escrow arrangements, or government guarantees (for public sector off-takers, the Partial Risk Guarantee from the World Bank/Multilateral Investment Guarantee Agency — MIGA — or the Nigerian Sovereign Investment Authority — NSIA — is sometimes available).
This template is provided for informational purposes only and does not constitute legal advice. Laws vary by jurisdiction and change over time. Consult a qualified attorney for advice specific to your situation.Full disclaimer
Found an error? Let us knowRelated Documents
You may also find these documents useful:
Construction Contract — Nigeria
A comprehensive construction contract for Nigeria covering scope of works, contract sum, payment milestones, variation orders, defects liability, and dispute resolution. Consistent with Nigerian Institute of Building (NIOB) standards and the Arbitration and Conciliation Act Cap A18 LFN 2004.
Escrow Agreement (Nigeria) (Contracts)
A Nigeria escrow agreement under which a neutral third-party escrow agent holds funds or documents pending satisfaction of agreed conditions. Governed by the Nigerian Contract law, CAMA 2020, and CBN guidelines. Used for property transactions, M&A deals, and commercial contracts.
Community Development Agreement (Nigeria)
A Nigeria Community Development Agreement (CDA) between a company and a host community setting out corporate social responsibility obligations, community benefits, development commitments, and dispute resolution mechanisms. Particularly relevant to oil and gas, mining, and infrastructure sectors under the Petroleum Industry Act 2021 (PIA 2021).