---
title: "Power Purchase Agreement (Nigeria)"
url: "https://forms-legal.com/nigeria/business/contracts/power-purchase-agreement-nigeria"
description: "A Power Purchase Agreement in Nigeria records the terms on which a buyer acquires the assets, fixing price, conditions and completion."
language: "en"
jurisdiction: "Nigeria"
category: "Business / Contracts & Agreements"
primaryStatute: "Electricity Act 2023"
dateModified: "2026-11-01"
maintainer: "Vladislav Sergienko, founder (not a lawyer)"
---

# Power Purchase Agreement (Nigeria)

- Nigeria · Business / Contracts & Agreements
- Legal basis: Electricity Act 2023

## What Is a Power Purchase Agreement (Nigeria)?

A Power Purchase Agreement in Nigeria records the terms on which a buyer acquires the assets, fixing price, conditions and completion.

The Nigerian electricity sector regulatory framework was substantially reformed by the Electricity Act 2023, which replaced the Electric Power Sector Reform Act 2005 (EPSRA) and extended concurrent legislative competence over electricity to state governments. The Electricity Act 2023 established the Federal Electricity Regulatory Commission (FERC) for inter-state electricity transactions (succeeding the Nigerian Electricity Regulatory Commission, NERC) while state electricity regulatory commissions may be established for intra-state transactions. NERC, operating under the EPSRA framework until fully transitioned, continues to issue generation, transmission, and distribution licences and approve tariffs under the Multi-Year Tariff Order (MYTO).

Under the EPSRA and the Electricity Act 2023, any person wishing to generate electricity for sale in Nigeria — except for captive generation below prescribed thresholds — must obtain a generation licence from NERC or the applicable state regulator. The National Integrated Power Project (NIPP) programme and the Presidential Power Initiative have added significant generation capacity, while the Eligible Customer Regulations (ECR) issued by NERC permit large industrial consumers to procure electricity directly from generators under bilateral PPAs, bypassing the distribution companies (DisCos) and the bulk trader (Nbet — Nigerian Bulk Electricity Trading Plc).

A PPA differs from a Grid Connection Agreement, which is the contract between the generator and the Transmission Company of Nigeria (TCN) or an electricity distribution company governing connection to the national grid or distribution network. A PPA also differs from a Fuel Supply Agreement (FSA), which governs the supply of gas or other fuel to the generator. For gas-fired power plants, the PPA, FSA, and Grid Connection Agreement together form the essential contractual triangle for project financing purposes, with international lenders such as the International Finance Corporation (IFC), African Development Bank (AfDB), and commercial banks requiring all three documents before financial close.

Renewable energy PPAs — for solar, wind, or mini-grid projects — are increasingly common in Nigeria. The Rural Electrification Agency (REA) promotes mini-grid PPAs for off-grid communities under the Rural Electrification Fund (REF) programme, and the Nigeria Electrification Project (NEP) provides viability gap funding for off-grid renewable energy developers.

## When Do You Need a Power Purchase Agreement (Nigeria)?

A Power Purchase Agreement is required in Nigeria whenever an independent power producer (IPP) or generator intends to sell electricity commercially to a utility, industrial consumer, or bulk buyer.

A Power Purchase Agreement is needed when an IPP with a generation licence from NERC constructs a gas-fired, hydro, or renewable energy power plant and wishes to sell its output to the Nigerian Bulk Electricity Trading Plc (Nbet) as the single buyer entity under the vesting contract framework established by NERC's Vesting Contract Regulations.

A Power Purchase Agreement is required when a large industrial consumer — such as a cement plant, telecommunications company, steel mill, or refinery — qualifies as an Eligible Customer under NERC's Eligible Customer Regulations and wishes to enter into a bilateral electricity supply agreement directly with a licensed generator, bypassing the distribution company (DisCo).

A Power Purchase Agreement is needed when a renewable energy developer — operating under a NERC generation licence or a state regulator's permit — installs a solar photovoltaic (PV) system or wind farm for a commercial or industrial (C&I) offtaker and requires a bankable long-term offtake agreement to support project financing from lenders including the Bank of Industry (BOI) or Development Bank of Nigeria (DBN).

A Power Purchase Agreement is required when a mini-grid operator licensed by NERC or the REA establishes an off-grid electricity supply system for a rural community and enters into a supply agreement with the host community or anchor customers (e.g., a health clinic, school, or agro-processing facility) under the REA Mini-Grid Regulations 2016.

A Power Purchase Agreement is needed when a government agency, university, or hospital wishes to procure captive solar power under a rooftop or ground-mounted PPA arrangement with a solar energy service company (ESCO), under which the ESCO finances, builds, owns, and operates the system while the client pays a fixed tariff per kilowatt-hour consumed.

## What to Include in Your Power Purchase Agreement (Nigeria)

A bankable Power Purchase Agreement in Nigeria must contain the following essential provisions.

Parties and Licences: Full legal names, addresses, CAMA 2020 RC numbers, and NERC (or state regulator) licence numbers of both the generator/seller and the offtaker/buyer. The generator's generation licence details — including capacity, fuel type, and licensed location — must be referenced.

Generation Facility Description: Location, installed capacity (in megawatts, MW), net dependable capacity, technology type (gas turbine, combined cycle, solar PV, wind, hydro, biomass), and connection point to the grid or distribution network.

Contract Capacity and Energy Quantities: The contracted capacity (MW) committed to the offtaker, the minimum contracted energy quantity (in megawatt-hours, MWh) per annum, and the dispatch and scheduling procedures under the TCN Grid Code or NERC dispatch protocols.

Tariff Structure: The energy charge (NGN/MWh or USD/MWh), capacity charge (NGN/MW-month), and any fuel cost pass-through mechanism. For projects denominated in USD, a foreign currency tariff indexed to the CBN official exchange rate is typical for bankability. NERC's Multi-Year Tariff Order (MYTO) provides the regulatory tariff framework.

Term and Commissioning: The PPA term (typically 15–25 years for thermal plants; 20–30 years for hydro or renewable), the long-stop commissioning date (the date by which the plant must achieve first generation), and the conditions precedent to commencement.

Take-or-Pay Obligations: The offtaker's obligation to pay for a minimum contracted energy quantity whether or not actually dispatched (take-or-pay), protecting the generator's revenue and debt service coverage.

Force Majeure and Change in Law: Provisions excusing performance for force majeure events (natural disasters, grid outages, government orders) and allocating risk for changes in Nigerian electricity law or NERC regulations that affect project economics.

Security and Credit Support: Payment security instruments — typically a letter of credit (LC), escrow account, or sovereign guarantee — required from the offtaker (particularly DisCos or Nbet) to manage Nigerian counterparty credit risk.

Governing Law and Dispute Resolution: Nigerian law (Electricity Act 2023, Arbitration and Mediation Act 2023) with disputes referred to arbitration, typically under the ICC Rules or the Lagos Court of Arbitration (LCA) Rules.

## Frequently Asked Questions

### What licences are required for a Power Purchase Agreement in Nigeria?

A generator wishing to sell electricity under a Power Purchase Agreement in Nigeria must hold a valid generation licence issued by the Nigerian Electricity Regulatory Commission (NERC) under the Electricity Act 2023 (or its predecessor, the Electric Power Sector Reform Act 2005). The licence specifies the technology, installed capacity, location, and term of the generation business. Captive generation for own use below 1 MW is exempt from licensing under NERC's captive generation regulations. For off-grid and mini-grid projects, a licence or permit from NERC under the Mini-Grid Regulations 2016 or from the Rural Electrification Agency (REA) may be required depending on the project scale. The offtaker under an Eligible Customer arrangement must hold an eligible customer permit from NERC confirming it meets the eligibility criteria (minimum demand threshold of 2 MW under the current NERC Eligible Customer Regulations).

### How is the electricity tariff determined under a PPA in Nigeria?

The electricity tariff under a Power Purchase Agreement in Nigeria is determined by negotiation between the generator and offtaker, within the regulatory framework established by NERC's Multi-Year Tariff Order (MYTO). For regulated utilities (DisCos and Nbet), NERC approves the bulk electricity purchase tariff under the MYTO methodology, which sets cost-reflective tariffs based on generation, transmission, distribution, and administrative costs. For bilateral PPAs with Eligible Customers under NERC's Eligible Customer Regulations, tariffs are freely negotiated between the generator and the industrial consumer. For renewable energy C&I PPAs, tariffs are typically structured as a capacity charge (USD/kW/month) and an energy charge (USD/kWh or NGN/kWh), with indexation clauses linked to the CBN official exchange rate and the Nigerian Consumer Price Index (CPI) published by the National Bureau of Statistics (NBS).

### What currency is used in Nigerian Power Purchase Agreements?

Nigerian Power Purchase Agreements for large IPP projects are typically denominated in United States Dollars (USD) or structured as a USD-equivalent NGN tariff linked to the Central Bank of Nigeria (CBN) official exchange rate, because most generation equipment, fuel supply contracts, and project debt are USD-denominated. A pure NGN tariff exposes the generator to naira depreciation risk, which can erode debt service coverage ratios — a key concern for international lenders including the IFC, AfDB, and Afreximbank. However, NERC's tariff framework and the Electricity Act 2023 require end-user tariffs to be expressed in NGN, creating a currency mismatch that must be managed through the tariff structure, hedging, or government support mechanisms. Domestic C&I solar PPAs for smaller projects (below 1 MW) are commonly structured in NGN.

### What is a take-or-pay clause in a Nigerian Power Purchase Agreement?

A take-or-pay clause in a Nigerian Power Purchase Agreement requires the offtaker (buyer) to pay for a minimum quantity of electrical energy — expressed as a percentage of the contracted annual energy quantity, typically 70%–85% — whether or not that energy is actually dispatched or consumed. The take-or-pay obligation protects the generator's revenue stream and ensures that the generator can service its project debt (bonds, term loans) even during periods of low system demand, grid outages, or offtaker dispatch curtailment. For IPPs selling to Nbet or DisCos — which have historically had payment discipline issues in Nigeria — the take-or-pay clause is a fundamental bankability requirement insisted upon by project finance lenders. The clause is typically backed by a payment security mechanism such as an escrow account funded by tariff collections, a letter of credit from a first-class Nigerian or international bank, or a sovereign payment guarantee from the Federal Government of Nigeria.

### How are disputes resolved under a Power Purchase Agreement in Nigeria?

Disputes under a Power Purchase Agreement in Nigeria are typically resolved through a tiered dispute resolution mechanism beginning with senior management negotiation, followed by expert determination for technical and metering disputes, and finally international arbitration for unresolved commercial disputes. Most bankable Nigerian PPAs specify arbitration under the International Chamber of Commerce (ICC) Rules with seat in London, Paris, or Lagos, reflecting the preference of international lenders and equity investors for a neutral forum with enforcement under the New York Convention on the Recognition and Enforcement of Foreign Arbitral Awards 1958, to which Nigeria acceded in 1970. For purely domestic transactions, arbitration under the Arbitration and Mediation Act 2023 with seat at the Lagos Court of Arbitration (LCA) or the Regional Centre for International Commercial Arbitration Lagos (RCICAL) is an alternative. Regulatory disputes with NERC are resolved before NERC's dispute resolution panel under the Electricity Act 2023.

Fillable version (PDF or Word): [Download the free template](https://forms-legal.com/nigeria/business/contracts/power-purchase-agreement-nigeria)

General information, not legal advice — see our [accuracy & editorial policy](https://forms-legal.com/accuracy-policy). Confirm the cited law is current before relying on it.
