# Safe Work Method Statement — SWMS (Australia)

- Australia · Employment / Health & Safety
- Legal basis: Fair Work Act 2009 (Cth)

## What Is a Safe Work Method Statement — SWMS (Australia)?

A Safe Work Method Statement — SWMS in Australia sets the scope of works, price, timeframe, and variation and completion procedures between the principal and the builder or contractor under the Fair Work Act 2009 (Cth).

A SWMS must: identify the work that is high risk construction work (by reference to Schedule 18); specify the hazards relating to the HRCW and the risks to health and safety; describe the measures to be implemented to control the risks; and describe how the control measures are to be implemented, monitored, and reviewed. Control measures must be selected and applied in accordance with the WHS hierarchy of controls (WHS Act 2011 ss 17-19 and WHS Regulation regs 34-38): elimination, substitution, isolation, engineering controls, administrative controls, and PPE.

A SWMS must be prepared before the HRCW commences, in consultation with the workers who will carry out the work. All workers who are to perform the HRCW must be given the opportunity to read and understand the SWMS, and must sign a register confirming their understanding before commencing the work. The SWMS must be kept at the construction site while the HRCW is being carried out and must be available for inspection by any WHS regulator inspector.

The legal framework governing the Safe Work Method Statement — SWMS (Australia) in Australia draws on several key statutes and regulatory bodies. Under the Fair Work Act 2009 (Cth), the Fair Work Commission (FWC) adjudicates workplace disputes. Section 394 of the Fair Work Act 2009 governs unfair dismissal claims. The Fair Work Ombudsman (FWO) enforces compliance with the National Employment Standards (NES). The Privacy Act 1988 (Cth) and Australian Privacy Principles (APPs) govern personal data handling. The Australian Taxation Office (ATO) administers PAYG withholding and superannuation guarantee obligations under the Superannuation Guarantee (Administration) Act 1992. Parties executing a Safe Work Method Statement — SWMS (Australia) in Australia should confirm the document reflects current law, including any amendments enacted since the original drafting date. The Fair Work Act 2009 (Cth) sets the foundational requirements.

## When Do You Need a Safe Work Method Statement — SWMS (Australia)?

A SWMS is legally required before any of the 19 categories of high risk construction work listed in Schedule 18 of the WHS Regulation 2017 (Cth) commences. The most common categories requiring a SWMS in Australian construction projects include:

Work at height: any construction work involving a risk of a person falling more than 2 metres — this includes scaffolding, roofing, formwork, crane operations, and work on elevated structures and platforms.

Demolition: demolition of a load-bearing element of a structure, or any demolition work that could affect the structural integrity of an adjacent structure.

Asbestos: any construction work involving the disturbance or removal of asbestos or asbestos-containing materials.

Confined spaces: construction work carried out in a confined space as defined by WHS Regulation reg 66 (including underground chambers, tanks, pits, ducts, and similar enclosed structures).

Trenching and excavation: any construction work involving a trench or shaft more than 1.5 metres deep.

Work near live services: work involving energised electrical installations or services, or work on pressurised gas, chemical, fuel, or refrigerant pipelines.

Tilt-up and precast concrete: erection and placement of precast concrete elements and tilt-up concrete panels.

Mobile plant: work in an area with movement of powered mobile plant (forklifts, excavators, cranes, concrete pumps) that creates a risk to workers in the area.

For each category of HRCW on a project, a separate SWMS may be needed, or one SWMS may cover multiple categories if they are performed as part of the same work activity.

Parties in Australia should prepare a Safe Work Method Statement — SWMS (Australia) proactively rather than waiting for a dispute to arise. Under the Fair Work Act 2009 (Cth), the Fair Work Commission (FWC) adjudicates workplace disputes. Section 394 of the Fair Work Act 2009 governs unfair dismissal claims. The Fair Work Ombudsman (FWO) enforces compliance with the National Employment Standards (NES). The Privacy Act 1988 (Cth) and Australian Privacy Principles (APPs) govern personal data handling. The Australian Taxation Office (ATO) administers PAYG withholding and superannuation guarantee obligations under the Superannuation Guarantee (Administration) Act 1992.

## What to Include in Your Safe Work Method Statement — SWMS (Australia)

A compliant Australian SWMS must include the following key elements as required by WHS Regulation 2017 reg 291:

**Project and contractor identification**: Full legal name and ABN of the principal contractor and (if different) the subcontractor preparing the SWMS; project name and site address; site supervisor details.

**SWMS identification**: A unique title or reference number and version, to support document control and confirm the correct version is used at the site.

**HRCW type identification**: Explicit identification of the type(s) of high risk construction work covered by the SWMS, by reference to Schedule 18 of the WHS Regulation.

**Work description**: A detailed description of the specific HRCW to be performed, including the scope, equipment, materials, and duration.

**Worker consultation record**: Names and roles of the workers consulted in preparing the SWMS — mandatory under WHS Regulation reg 291(2).

**Licences and permits**: HRW licence classes required for the HRCW (e.g., scaffolding, rigging, crane operation), any permits or approvals required, and emergency procedures.

**Hazard identification and risk assessment**: A systematic identification of all hazards associated with the HRCW, with a risk rating for each hazard using a risk matrix.

**Control measures — hierarchy of controls**: Controls structured from elimination and substitution through isolation and engineering to administrative and PPE.

**Step-by-step work sequence**: The specific sequence of tasks with the hazards and controls relevant to each step — the operational guide for workers and supervisors.

**Monitoring and review**: Monitoring and supervision arrangements, and the triggers requiring SWMS review and revision.

**Principal contractor approval and worker sign-on**: Approval signature from the principal contractor and a sign-on register for all workers performing the HRCW.

Additional compliance elements for a Safe Work Method Statement — SWMS (Australia) used in Australia include: Under the Fair Work Act 2009 (Cth), the Fair Work Commission (FWC) adjudicates workplace disputes. Section 394 of the Fair Work Act 2009 governs unfair dismissal claims. The Fair Work Ombudsman (FWO) enforces compliance with the National Employment Standards (NES). The Privacy Act 1988 (Cth) and Australian Privacy Principles (APPs) govern personal data handling. The Australian Taxation Office (ATO) administers PAYG withholding and superannuation guarantee obligations under the Superannuation Guarantee (Administration) Act 1992.

## Sources & Citations

- [Fair Work Act 2009 (Cth)](https://www.legislation.gov.au/)

## Frequently Asked Questions

### What is a SWMS and when is it legally required in Australia?

A Safe Work Method Statement (SWMS) is a document that describes how high risk construction work (HRCW) will be performed safely. It is legally required under Work Health and Safety Regulation 2017 (Cth) reg 291 for all 19 categories of HRCW listed in Schedule 18 of the WHS Regulation. HRCW includes work involving a risk of falling more than 2 metres, demolition, asbestos work, work in confined spaces, trenching more than 1.5 metres deep, tilt-up concrete, work near energised electrical installations, work involving explosives, tunnelling, and other high-risk construction activities. A SWMS must be prepared before the HRCW commences, must be prepared in consultation with the workers who will carry out the work, must be available at the construction site at all times during the HRCW, and must be reviewed and revised if conditions change. Under reg 292, workers must not begin HRCW unless they have been given the opportunity to read and understand the SWMS.

### Who is responsible for ensuring a SWMS is prepared — the principal contractor or the subcontractor?

Both the person who carries out the HRCW and the principal contractor have obligations under the WHS Regulation. Under reg 291, the person who is to carry out the HRCW (which may be the principal contractor or a subcontractor) must prepare the SWMS before the work commences. Under reg 309, the principal contractor must take all reasonable steps to obtain a copy of any SWMS prepared by a subcontractor and require that any HRCW on the project is carried out in accordance with a SWMS. In practice, the subcontractor typically prepares the SWMS for the specific HRCW they will perform, and the principal contractor reviews and approves the SWMS as part of their site management obligations. The principal contractor is also responsible for ensuring that the SWMS is made available to all workers performing the HRCW and that a worker sign-on register is completed before work commences.

### Does every worker on a construction site need to read and sign the SWMS?

Under WHS Regulation 2017 reg 292, only workers who are to carry out the specific high risk construction work covered by the SWMS must be given the opportunity to read and understand the SWMS before commencing that work. Other workers on the construction site who are not performing that specific HRCW are not required to sign the SWMS. However, all workers on a construction site generally require a construction induction card (CIC, formerly known as a 'white card') under WHS Regulation reg 317 before they can work on the site. A separate site-specific induction is also typically required by the principal contractor. The SWMS sign-on register serves as evidence that the workers performing the HRCW have been informed of and agreed to work in accordance with the SWMS — it is an important compliance and due diligence record that should be retained after the work is completed.

### When must a SWMS be reviewed and revised?

Under WHS Regulation 2017 reg 291(4), the SWMS must be reviewed and if necessary revised before work continues if: (a) the SWMS may no longer minimise the risks to health and safety of persons carrying out the HRCW; (b) a person with management or control of the workplace requests a review; or (c) a work health and safety representative requests a review. In practice, a SWMS should also be reviewed after any incident or near miss involving the HRCW, when there is a significant change in site conditions or weather, when new hazards are identified, when work methods change, or at regular intervals as part of the site's safety management routine. Reviewed and revised versions of the SWMS should be re-dated, version-numbered, and re-signed by the workers performing the HRCW before the revised SWMS is used.

### What high risk work licences are required for scaffolding work?

Under WHS Regulation 2017 Chapter 4 and Schedule 3, scaffolding work requires a high risk work (HRW) licence. The licence class depends on the type and height of the scaffold: a Basic Scaffolding licence (class SB) is required for basic scaffolding work up to 4 metres in height; an Intermediate Scaffolding licence (class SI) is required for more complex scaffolding work (including most suspended scaffolding, and cantilever, hung, and spur scaffolds); and an Advanced Scaffolding licence (class SA) is required for the most complex scaffolding configurations including hung, suspended, and mast-climber scaffolding. HRW licences are issued by the state and territory WHS regulators. A person must hold the required licence before performing the relevant scaffolding work, and the principal contractor must verify the licence before the worker commences the HRCW. Licences can be verified through the state regulator's online licence register.

### What are the principal contractor's obligations for construction sites where HRCW is performed?

Under WHS Regulation 2017, the principal contractor for a construction project where construction work costs more than $250,000 has extensive obligations, including: preparing a WHS management plan for the project (reg 309) that addresses the management of HRCW; taking all reasonable steps to obtain a copy of each SWMS prepared by any subcontractor performing HRCW on the project (reg 309); ensuring HRCW is not carried out unless a SWMS is in place; ensuring that the site is notified to the WHS regulator if the project involves notifiable construction work (cost above $250,000) before construction work begins (reg 291A); ensuring that all workers hold the required HRW licences before commencing HRCW; and requiring a construction induction card (CIC) from all workers before they enter the site. The principal contractor is also a PCBU with all the general duties under WHS Act ss 19-27, including officer due diligence obligations.